Envision AESC's $1.6 billion BMW battery plant near Florence, South Carolina remains paused.

The battery cell maker has not set a date to resume construction since halting work in June 2025, though it says it still intends to invest the full $1.6 billion.

Quick answer

Envision AESC US/BMW: $1.6 billion investment in Florence County, S.C. Stage: Under construction. Timeline: South Carolina announced the project Dec. 6, 2022 as an $810 million, 1,170 job battery cell plant on 870 acres in the Technology and Commerce Park near Florence, supplying BMW's Spartanburg plant. AESC broke ground June 7, 2023. In March 2024, AESC announced a second $1.5 billion building for 1,080 more jobs, and the state approved an additional $111 million in bonds. AESC pulled back from that second building in early 2025. On June 5, 2025, AESC said in a statement it was pausing construction at the Florence site, citing policy and market uncertainty, after investing more than $1 billion of its pledged $1.6 billion. South Carolina withdrew the $111 million tied to the canceled second phase; the original $135 million grant and $121 million in bonds were not affected. Local officials said in December 2025 the plant was roughly 75% complete. As of Oct. 30, 2026, AESC still had not set a restart date, though the company told local officials it still intends to invest the full $1.6 billion in Florence County. Likely to buy: site work and foundations, structural steel erection, electrical and substation, mechanical and hvac.

Close-up of a modern white steel structure against a bright blue sky
Illustrative photo. Photo: Jan van der Wolf / Pexels

By Capex Wire NewsroomPublished 2 min read

AESC's $1.6 billion battery cell plant near Florence, South Carolina remains paused as of Oct. 30, 2026, 17 months after the company halted construction and with no restart date set, according to the local outlet HERE Florence.

What is being built

South Carolina officials announced the project Dec. 6, 2022 as an $810 million, 1,170 job plant on 870 acres in the Technology and Commerce Park near Florence, intended to supply battery cells for BMW's assembly plant in Spartanburg. AESC broke ground June 7, 2023 on the roughly 1.5 million square foot facility, with a planned annual capacity of 30 gigawatt hours. In March 2024, the company announced a second, $1.5 billion building for an additional 1,080 jobs, and the state approved $111 million more in bonds on top of $121 million already committed. AESC pulled back from that second building in early 2025.

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 69 projects like this

$9.90/month · cancel anytime in one click

Why construction stopped

AESC halted work at the Florence site June 5, 2025. "Due to policy and market uncertainty, we are pausing construction at our South Carolina facility at this time," the company said in a statement provided by spokesman Brad Grantham. By that point AESC had invested more than $1 billion of its pledged $1.6 billion. Gov. Henry McMaster told reporters, "We hate to see that happen, but a pause is OK," and pointed to the potential loss of federal EV tax breaks and tariff uncertainty as pressures on the company. South Carolina withdrew the $111 million in bonds tied to the canceled second building; a Commerce Department spokeswoman, Alex Clark, said the remaining $135 million grant and $121 million in bonds for the first plant were "so far unaffected," adding, "South Carolina is fully and unequivocally committed to supporting existing companies, including AESC."

ItemFigure
Total pledged investment$1.6 billion
Invested before the pausemore than $1 billion
Jobs pledged1,600
Plant sizeabout 1.5 million sq ft
Planned capacity30 GWh per year
State incentives withdrawn$111 million (second building only)

Who is building it and what happens next

No restart date has been announced. Local officials said in December 2025 that the plant was roughly 75% complete and that major construction and hiring could resume within eight to 12 months, a window that has since passed without an announced restart. A $22 million worker training center the state and AESC built along Highway 327 is finished and has served other companies while the plant sits idle, according to HERE Florence. AESC has not named a general contractor publicly. BMW has said the pause does not change its own plans; in June 2025, BMW spokesman Steve Wilson said the company's battery assembly plans "are still on schedule to begin in 2026" at its separate Woodruff, South Carolina site. Capex Wire found no report that AESC has cancelled or withdrawn the Florence project outright.

Project fileSC
Owner
Envision AESC US/BMW
Investment
$1.6 billion (AESC's own pledged total investment, reaffirmed Oct. 30, 2026; more than $1 billion already spent before the June 2025 pause)
Location
Florence County, South Carolina
Type
Battery plant (cells, modules), new construction
Stage
Under construction
Timeline
South Carolina announced the project Dec. 6, 2022 as an $810 million, 1,170 job battery cell plant on 870 acres in the Technology and Commerce Park near Florence, supplying BMW's Spartanburg plant. AESC broke ground June 7, 2023. In March 2024, AESC announced a second $1.5 billion building for 1,080 more jobs, and the state approved an additional $111 million in bonds. AESC pulled back from that second building in early 2025. On June 5, 2025, AESC said in a statement it was pausing construction at the Florence site, citing policy and market uncertainty, after investing more than $1 billion of its pledged $1.6 billion. South Carolina withdrew the $111 million tied to the canceled second phase; the original $135 million grant and $121 million in bonds were not affected. Local officials said in December 2025 the plant was roughly 75% complete. As of Oct. 30, 2026, AESC still had not set a restart date, though the company told local officials it still intends to invest the full $1.6 billion in Florence County.
Contractor / EPC
Not announced
Sources
Office of the Governor of South Carolina, HERE Florence, Edward E. Bustamante Sr., South Carolina Daily Gazette, Jessica Holdman, Associated Press (Jeffrey Collins) via WCIV ABC News 4, The State (Joseph Bustos) via Yahoo

Why it matters

Contractors and suppliers lined up for site work, structural steel and electrical trades on the 1.5 million square foot plant have no new start date to plan around, even though the company and state say the project itself has not been cancelled.

What this project buys

  • Site work and foundations
  • Structural steel erection
  • Electrical and substation
  • Mechanical and HVAC
  • Process piping
  • Fire protection

When to approach: No restart date has been set. Local officials said in December 2025 that major construction and hiring could resume within eight to 12 months, a window that has passed without an announced restart as of Oct. 30, 2026.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Is AESC still building its battery plant in Florence, South Carolina?

AESC says it still intends to invest the full $1.6 billion, but construction has been paused since June 2025 and the company has not set a date to resume work, as of its most recent public statement on Oct. 30, 2026.

Why did AESC pause construction in Florence County?

AESC's June 2025 statement cited policy and market uncertainty without naming a specific cause. Gov. Henry McMaster pointed to the potential loss of federal EV tax credits and tariff uncertainty.

How many jobs is AESC planning to add in Florence County?

AESC says it still plans to create 1,600 jobs once conditions allow it to restart, on top of the more than $1 billion it says it had already invested when the pause began.

What happened to South Carolina's incentives for the project?

The state withdrew $111 million in bonds that had been approved for a second, separate expansion building after AESC pulled back from that building in early 2025. The original $135 million grant and $121 million in bonds for the first plant were not affected.

Does the pause affect BMW's Woodruff battery plant?

BMW said in June 2025 the pause did not change its plans, and that its separate Woodruff, South Carolina battery assembly plant remained on schedule to begin in 2026.