Takanock wins approval to build a data center and gas plant in Glendale, Arizona.
The Glendale City Council voted 6-1 to annex and rezone 160 acres for three data center buildings and an 18-turbine gas power plant.
Capex $10.3 billion
U.S. capital projects before the bid list closes.
Capex Wire · Project Map
Factories, power plants, data centers and industrial facilities announced, filed, financed or under construction in Arizona, with investment, stage and timeline.
Data center campus with on-site natural gas power plant, new construction
Glendale, AZ annexed and rezoned 160 acres for three data center buildings and an 18-turbine gas power plant.
Open pit copper mine and concentrator, new construction
Hudbay and Mitsubishi approved the $2.07 billion Copper World mine about 31 miles south of Tucson. First production in second half of 2029.
Battery storage, 400 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 150 MW + Solar photovoltaic, 125 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 225 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 225 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Solar photovoltaic, 200 MW + Battery storage, 200 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Solar photovoltaic, 275 MW + Battery storage, 275 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Natural gas combustion turbine, 242 MW
Likely to buy: Gas turbine installation, Mechanical and piping, Electrical and substation
Battery storage, 550 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Natural gas combined cycle, 1,250 MW
Likely to buy: Gas and steam turbine installation, Heat recovery steam generators, Mechanical and piping
Solar photovoltaic, 225 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Solar photovoltaic, 475 MW + Battery storage, 475 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Battery storage, 206 MW + Solar photovoltaic, 206 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 394 MW + Solar photovoltaic, 394 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 400 MW + Solar photovoltaic, 400 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 250 MW + Solar photovoltaic, 250 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Solar photovoltaic, 300 MW + Battery storage, 300 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Battery storage, 382 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Battery storage, 300 MW + Solar photovoltaic, 300 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Solar photovoltaic, 400 MW + Battery storage, 400 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Battery storage, 300 MW + Solar photovoltaic, 300 MW
Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage
Solar photovoltaic, 350 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Solar photovoltaic, 400 MW + Battery storage, 300 MW
Likely to buy: Site work and grading, Pile driving and racking, Module installation
Natural gas combustion turbine, 297 MW
Likely to buy: Gas turbine installation, Mechanical and piping, Electrical and substation
Natural gas combustion turbine, 392 MW
Likely to buy: Gas turbine installation, Mechanical and piping, Electrical and substation
Coconino CountyLa Paz CountyMaricopa CountyMohave CountyNavajo CountyPinal CountyYuma County
The Glendale City Council voted 6-1 to annex and rezone 160 acres for three data center buildings and an 18-turbine gas power plant.
Capex $10.3 billion
The partners made a final investment decision on the open pit copper project. First production is targeted for the second half of 2029.
Capex $2.1 billion