Takanock wins approval to build a data center and gas plant in Glendale, Arizona.
The Glendale City Council voted 6-1 to annex and rezone 160 acres for three data center buildings and an 18-turbine gas power plant.
Quick answer
Takanock LLC: $10.3 billion investment in Glendale, Ariz. Stage: Filed / permitted. Timeline: Glendale Planning Commission recommended approval 4-2 on Sept. 24, 2026. City Council approved annexation and rezoning 6-1 on Oct. 27, 2026. Construction was expected to start in November 2026, with the first data center building opening in 2028. Likely to buy: site grading and civil, electrical and substation work, gas turbine installation, structural steel erection.

By Capex Wire StaffPublished 3 min read
The Glendale, Arizona, City Council voted 6-1 on Oct. 27, 2026, to annex and rezone 160 acres for a data center campus and an on-site natural gas power plant proposed by Takanock LLC, a Michigan based developer.
The city calls the project Project Eagle. Its power supply component is known as Project Baccara. The site sits near Litchfield Road and Olive Avenue, about 2 miles northwest of Luke Air Force Base. The land had been under Maricopa County jurisdiction. Annexation brings it inside Glendale, giving the city oversight of landscaping, fencing and other design standards, KJZZ reported.
What is being built
Plans call for three data center buildings on about 108 acres, ABC15 reported. A separate roughly 33 acre parcel would hold the natural gas power plant, with 18 turbines generating about 700 megawatts, according to Construction Review Online and ABC15. About 12 more acres are set aside for a future Arizona Public Service substation. The power plant operator, Baccara Power, would sell electricity wholesale to Electric District No. 7, Construction Review Online reported. EPCOR, not the city of Glendale, would supply water and wastewater service to the site.
Glendale's own economic impact materials put the private investment at about $10.27 billion, broken into roughly $370 million for the data center buildings, $1.7 billion for the power plant and $8.2 billion in computing and electrical equipment, Construction Review Online reported. Other outlets, including azfamily.com, have described the project as a $36 billion undertaking without detailing that figure.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $126 billion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
Jobs and timeline
Glendale estimates the project will create about 200 permanent jobs and generate more than $150 million in direct city revenue over the next 10 years, according to ABC15, KJZZ and azfamily.com. No construction jobs figure has been released. City officials said construction was expected to begin in November 2026, with the first data center building scheduled to open in 2028, azfamily.com reported.
Before the council vote, the Glendale Planning Commission recommended the rezoning on a 4-2 vote Sept. 24, 2026, Bisnow reported. The Maricopa County Board of Supervisors separately approved a military compatibility permit for the site in May 2026, before annexation moved the property into the city.
| Item | Figure |
|---|---|
| Site | 160 acres: about 108 for data centers, 33 for the power plant, 12 for a future substation |
| Gas turbines | 18, about 700 megawatts |
| Permanent jobs | About 200 |
| City revenue | More than $150 million over 10 years |
| Private investment | About $10.27 billion per city materials; $36 billion per some media reports |
Who is building it
Takanock LLC is the developer. Phoenix attorney Ed Bull, of Burch & Cracchiolo, represented the company before the council, Bisnow reported. No general contractor, structural engineer or turbine supplier has been named publicly. Before site work begins, the developer must help pay for a new traffic signal and reach an agreement to fund specialized hazardous materials and fire services, KJZZ and azfamily.com reported.
What residents said
Fourteen residents spoke against the project at the public hearing and four spoke in favor, ABC15 reported. Surprise resident Lisa Everett supported it. "I've been to multiple meetings, and I've always felt confident in what I've heard, and the project is going to support our grid," she said. Waddell resident Tony Camisi raised concerns about water sourcing. "Even some of the councilmembers were a little bit confused, exactly knowing where that water is coming from. So I feel like there is a transparency issue," he said. A nearby resident, David Wirth, said he worried about air quality near the turbines. "The West Valley already has a low quality of air, and I have breathing problems myself, I know that a lot of people in the area have the same issues. I don't want that to increase," he said. Councilmember Lauren Tolmachoff said the city needs the infrastructure. "This is the world we are living in now and in order for this to continue on, we need the infrastructure," she said.
What happens next
Glendale's ordinance requires Takanock to meet standards set by Luke Air Force Base, including mitigating turbine emissions and avoiding interference with pilot visibility, KJZZ reported. No air quality permit for the power plant has been reported. Arizona Attorney General Kris Mayes has separately pushed for a statewide pause on new data center approvals, though any such pause would require action by the Arizona Legislature, which does not reconvene until January, ABC15 reported.
- Owner
- Takanock LLC
- Investment
- $10.3 billion (Glendale's own economic impact materials estimate about $10.27 billion in private investment ($370 million buildings, $1.7 billion power plant, $8.2 billion equipment), per Construction Review Online; some other outlets cite $36 billion for the total project without itemizing it)
- Location
- Glendale, Maricopa County, Arizona
- Type
- Data center campus with on-site natural gas power plant, new construction
- Stage
- Filed / permitted
- Timeline
- Glendale Planning Commission recommended approval 4-2 on Sept. 24, 2026. City Council approved annexation and rezoning 6-1 on Oct. 27, 2026. Construction was expected to start in November 2026, with the first data center building opening in 2028.
- Contractor / EPC
- Not announced
- Sources
- Construction Review Online, Bisnow, KJZZ, ABC15, AZFamily / KTVK-KPHO
Why it matters
A 160-acre campus with three data center buildings and an 18-turbine gas plant means sitework, electrical, substation and turbine installation trades should see bid activity as construction starts, with EPCOR handling water and APS adding a new substation.
What this project buys
- Site grading and civil
- Electrical and substation work
- Gas turbine installation
- Structural steel erection
- Security fencing
- HVAC and process cooling
When to approach: No general contractor, structural engineer or turbine supplier has been named. The developer must fund a new traffic signal and a hazmat and fire services agreement before site work begins.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Takanock's Project Eagle data center?
Near Litchfield Road and Olive Avenue in Glendale, Arizona, about 2 miles northwest of Luke Air Force Base, on 160 acres the city annexed from Maricopa County.
How many jobs will Project Eagle create?
Glendale estimates about 200 permanent jobs. Neither the city nor Takanock has released a construction jobs figure.
When will construction start on the Glendale data center?
City officials said construction was expected to begin in November 2026, with the first of three data center buildings opening in 2028.
Who is building the Glendale data center and gas plant?
Michigan based developer Takanock LLC is behind the project. No general contractor has been named publicly.
How big is the Project Eagle power plant?
Plans call for 18 natural gas turbines generating about 700 megawatts on roughly 33 of the site's 160 acres, with power sold wholesale through Baccara Power to Electric District No. 7.
Sources
- Glendale Approves Project Eagle: 160-Acre Data Center Campus to Include 700-MW Gas Power Plant, Construction Review Online, Oct. 30, 2026
- Maricopa County Data Center Project Moves Toward Approval Despite Pushback, Bisnow, Sept. 28, 2026
- Glendale approves Project Eagle data center development, KJZZ, Oct. 28, 2026
- Glendale City Council approves Project Eagle data center, natural gas power facility, ABC15, Oct. 28, 2026
- Glendale approves major step to start construction on data center, AZFamily / KTVK-KPHO, Oct. 28, 2026