Nexus Data Centers files two more $400 million buildings at its Hubbard, Texas data center campus.
State filings for Apex HB3 and HB4 bring the number of similarly sized buildings registered at the Hill County campus to four, each estimated at $400,000,000.
Quick answer
Nexus Data Centers Hubbard, LLC: $800 million investment in Hubbard, Texas. Stage: Under construction. Timeline: Filed with the state Nov. 17, 2026. Start date on record Aug. 31, 2026. Completion date on record Jan. 5, 2028. Likely to buy: electrical, mechanical and cooling, concrete, steel erection.

By Capex Wire StaffPublished 2 min read
Nexus Data Centers Hubbard, LLC has filed state paperwork for two more data center buildings at its Apex campus outside Hubbard, Texas, each carrying an estimated cost of $400,000,000, according to records the company filed with the Texas Department of Licensing and Regulation on Nov. 17, 2026.
The filings, for buildings named Apex HB3 and Apex HB4, list the same address, 357 HCR 3372 in Hill County, and the same square footage, 491,378 square feet each. Combined, the two new filings add $800 million in registered construction value to the campus.
What is being built
Apex HB3 and Apex HB4 are listed as new construction data centers with site improvements. The state filing shows a start date of Aug. 31, 2026, before the Nov. 17 registration, and a completion date of Jan. 5, 2028, for both buildings. HDR Engineering, Inc., based in Dallas, is the design firm of record. No contractor is listed. The owner is recorded as Nexus Data Centers Hubbard, LLC, at 4747 Research Forest Drive in The Woodlands, Texas.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $126 billion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
A bigger campus than one filing shows
HB3 and HB4 are not the first buildings Nexus has registered at the roughly 2,000 acre Apex campus. The Apex HB1 building is already under construction, and a second building matching it in size and construction value was registered earlier in 2026, according to Baxtel, bringing the number of similarly sized buildings at the campus to four. Hill County commissioners approved a tax reinvestment zone for the project on Feb. 10, 2026, a required first step before any abatement, The Lakelander reported. Nexus later withdrew its abatement request in April 2026, Baxtel reported.
Power and water
The campus is designed to run on its own natural gas generation, and Nexus has received air permits from the Texas Commission on Environmental Quality for the power plant, Baxtel reported. Company officials told a town hall that drew 250 people that the primary water source would be rainwater, with treated effluent and a backup groundwater well, The Lakelander reported. Nexus said it would keep noise at the site at 65 decibels or less.
Jobs and incentives
Hill County officials put construction employment at around 2,500 jobs campuswide, per The Lakelander. Megan Claydon, a Nexus vice president, told commissioners the company is negotiating a Payment in Lieu of Taxes agreement rather than an abatement. "That is not a free ride we are looking for," she said.
What is not disclosed
No tenant is currently assigned to either HB3 or HB4. Nexus has not named a general contractor for either building, and has not said how the filings fit into its overall buildout plan or whether a further tax agreement with Hill County has been finalized.
- Owner
- Nexus Data Centers Hubbard, LLC
- Investment
- $800 million ($400,000,000 filed for each of Apex HB3 and Apex HB4 with the Texas Department of Licensing and Regulation; combined figure is our own addition)
- Location
- Hubbard, Hill County, Texas
- Type
- Data center, new construction
- Stage
- Under construction
- Timeline
- Filed with the state Nov. 17, 2026. Start date on record Aug. 31, 2026. Completion date on record Jan. 5, 2028.
- Contractor / EPC
- Not announced
- Sources
- Texas Department of Licensing and Regulation, Texas Department of Licensing and Regulation, The Lakelander, Baxtel
Why it matters
Two more $400 million buildings at an already active campus means ongoing demand for electrical, mechanical and site work in Hill County, with HDR Engineering already engaged as designer but no general contractor named yet.
What this project buys
- Electrical
- Mechanical and cooling
- Concrete
- Steel erection
- Fire protection
- Low voltage and controls
When to approach: No contractor named yet for HB3 or HB4. Design firm HDR Engineering is already on record, so bid packages for site and building trades are likely being assembled now.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is the Nexus Data Centers Apex campus?
At 357 HCR 3372 near Hubbard, Texas, in Hill County, on a site Hill County meeting records describe as about 2,000 acres.
How much do the new Apex HB3 and HB4 buildings cost?
Each carries an estimated cost of $400,000,000 in the state filing, for a combined $800 million across the two newest buildings.
When will Apex HB3 and HB4 be finished?
The state filing lists a completion date of Jan. 5, 2028 for both buildings, with a start date on record of Aug. 31, 2026.
Who is building the Nexus Hubbard data centers?
HDR Engineering, Inc. is the design firm of record. No general contractor is listed on the state filings for HB3 or HB4.
How many jobs will the Nexus Hubbard campus create?
Hill County officials have cited around 2,500 construction jobs across the whole campus, with permanent jobs to follow once buildings are operating.
Sources
- TABS Project Details, Apex HB3, Texas Department of Licensing and Regulation, Nov. 17, 2026
- TABS Project Details, Apex HB4, Texas Department of Licensing and Regulation, Nov. 17, 2026
- Commissioners approve Hubbard data center reinvestment zone, The Lakelander, Feb. 19, 2026
- Nexus: Apex DFW HB1, Baxtel, June 27, 2026