Data Centers · UT

Qlevr seeks permits for $105 million data center in Salt Lake City, Utah.

A city building permit application and a state air quality filing point to a one-story facility in the Northpoint neighborhood. Neither has been approved.

Quick answer

Qlevr LLC: $105 million investment in Salt Lake City, Utah. Stage: Announced. Timeline: City building permit application submitted May 21, 2026. Air quality application filed in late September 2026. Neither approved as of Nov. 12, 2026. No construction dates. Likely to buy: electrical and switchgear, mechanical and cooling, backup generators and fuel systems, concrete and foundations.

Aisle of server cabinets inside a data center
Illustrative photo. Photo: Brett Sayles / Pexels

By Capex Wire StaffPublished 2 min read

Qlevr LLC is seeking permits for a one-story data center that would cost at least $105 million to build in Salt Lake City, Utah, according to public filings reported by The Salt Lake Tribune.

The site is at 2258 W. 2950 North in the Northpoint neighborhood, in Salt Lake County, across 2200 West from several homes. The Tribune reported Nov. 11 that the parcel appears to be part of the larger Scannell Logistics Campus project.

Two filings

  • A city building permit application for the address describes a one-story data center with a cost of at least $105 million. The application does not list Qlevr's name, the Tribune reported. KUTV reported that it was submitted May 21 and that the project is called Project Bedrock.
  • Qlevr filed in late September with the Utah Division of Air Quality for diesel-fired emergency engines and fuel tanks that would provide backup power.

Neither has been approved. The city must approve the building permit before construction can start. The air quality application has not been deemed complete, and a state engineer told the Tribune he had requested more information from the applicant. The state review can take about 180 days, depending on what is submitted, KUTV reported, and it includes a public comment period.

Capex Wire

Get there first: every project owner on the U.S. Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $126 billion

in announced or filed value

Subscribe for $9.90/month

Cancel anytime in one click.

Power and water

The facility would draw its primary power from the existing electrical grid, with the generators as backup. It would use a closed-loop cooling system, in which water is recirculated. The property is zoned business park, which limits water use to less than 200,000 gallons a day, the Tribune reported.

Who is behind it

The Tribune described Qlevr as a Florida development company and said it did not reply to questions. Salt Lake County records list the parcel owner as AC II 2691 NORTH 2200 WEST, LLC, a Delaware-registered entity. Scannell Properties and the brokerage JLL did not respond to the newspaper's requests about the property.

The City Council member who represents Northpoint told the Tribune she had not yet heard about the project. KUTV reported that residents are concerned about the pace of industrial development in the neighborhood.

What is not disclosed

The square footage, the acreage, the power capacity in megawatts and the end user have not been made public. No architect, engineer or general contractor is named in the reports. There is no construction schedule and no hearing date. The cost figure is the amount declared on the permit application and has not been confirmed by the developer.

Project fileUT
Owner
Qlevr LLC
Investment
$105 million (at least $105 million, as declared on the city building permit application)
Location
Salt Lake City, Salt Lake County, Utah
Type
Data center, one story, new construction
Stage
Announced
Timeline
City building permit application submitted May 21, 2026. Air quality application filed in late September 2026. Neither approved as of Nov. 12, 2026. No construction dates.
Contractor / EPC
Not announced
Sources
The Salt Lake Tribune, KUTV

Why it matters

A filed building permit with a declared value is an early signal that design is far enough along to price. With no builder named and two approvals pending, electrical, mechanical and generator suppliers can still get in front of the developer.

What this project buys

  • Electrical and switchgear
  • Mechanical and cooling
  • Backup generators and fuel systems
  • Concrete and foundations
  • Structural steel
  • Site work

When to approach: Permits pending. State air quality review can take about 180 days. No contractor named.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.