Hudbay and Mitsubishi approve $2.07 billion Copper World mine south of Tucson, Arizona.
The partners made a final investment decision on the open pit copper project. First production is targeted for the second half of 2029.
Quick answer
Hudbay Minerals (70%) and Mitsubishi Corporation (30%): $2.1 billion investment in Arizona. Stage: Financed. Timeline: Final investment decision Oct. 21, 2026. Material change report filed Oct. 30, 2026. First production targeted for the second half of 2029. Likely to buy: earthwork and mine development, concrete and foundations, structural steel, mechanical and process equipment installation.

By Capex Wire StaffPublished 2 min read
Hudbay Minerals and Mitsubishi Corporation have approved construction of the Copper World copper mine, about 31 miles south of Tucson, Arizona, with initial capital spending of approximately $2.07 billion.
The partners announced the final investment decision Oct. 21, and Hudbay filed a material change report on the decision dated Oct. 30. Hudbay owns 70% of Copper World and Mitsubishi owns 30% under a joint venture agreement signed in January 2026.
First production is targeted for the second half of 2029. The capital figure is net of equipment financing, stated in 2026 dollars and on a 100% basis, according to the filing.
How it is funded
- $600 million: Mitsubishi's initial equity investment in the joint venture.
- $230 million: deposit from Wheaton Precious Metals under an existing precious metals stream.
- About $650 million: anticipated project-level debt.
- Balance: equity contributions from Hudbay and Mitsubishi in proportion to their stakes, not expected until 2028.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $126 billion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
The mine plan
The base case is a 15-year mine built on mineral reserves that requires only state and local permits, Hudbay said. An extension case of 37 years would expand mining onto federal lands in year 10 and would need federal permits.
Pulse 2.0, reporting on the announcement, said the concentrator will start at 60,000 tons a day. From year five, Hudbay plans in-pit crushing and conveying and an increase to 90,000 tons a day. Copper output is expected to average about 102,000 tonnes a year in the first 10 years.
The mine will have four open pits on the west slope of the Santa Rita Mountains, according to AZFamily.
Jobs and local buying
The project is expected to create more than 1,000 construction jobs, about 500 permanent positions and up to 3,000 indirect jobs in Arizona. Hudbay said it will prioritize locally sourced goods and services, AZFamily reported.
Peter Kukielski, Hudbay's chief executive, called the approval "a significant milestone."
Opposition
Save the Scenic Santa Ritas, a group that has fought mining at the site since the 1990s, says the mine will damage groundwater and wildlife. John Dougherty of the group told AZFamily he plans to push the Legislature to change Arizona's mining laws.
What is not disclosed
The filing does not name an engineering, procurement and construction management firm, a mining contractor or equipment suppliers. A date for the start of major construction is not given. The lenders and terms of the project debt were not disclosed, and the sources opened for this story do not name the county.
- Owner
- Hudbay Minerals (70%) and Mitsubishi Corporation (30%)
- Investment
- $2.1 billion (initial growth capital of approximately $2.07 billion, net of equipment financing, in 2026 dollars, on a 100% basis)
- Location
- Arizona
- Type
- Open pit copper mine and concentrator, new construction
- Stage
- Financed
- Timeline
- Final investment decision Oct. 21, 2026. Material change report filed Oct. 30, 2026. First production targeted for the second half of 2029.
- Contractor / EPC
- Not announced
- Sources
- U.S. Securities and Exchange Commission, EDGAR, Pulse 2.0, Arizona's Family (AZFamily)
Why it matters
A sanctioned and funded mine build of more than $2 billion with a 2029 production target means procurement is active. Hudbay says it will prioritize locally sourced goods and services, an opening for Southern Arizona contractors and suppliers.
What this project buys
- Earthwork and mine development
- Concrete and foundations
- Structural steel
- Mechanical and process equipment installation
- Electrical and power distribution
- Piping and tailings infrastructure
When to approach: Construction approved and funded. Contracts for site work, the concentrator and mine infrastructure should be in play now. EPCM firm not named.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Sources
- Hudbay Minerals Inc. material change report, Form 51-102F3 (Exhibit 99.1 to Form 6-K), U.S. Securities and Exchange Commission, EDGAR, Oct. 30, 2026
- Hudbay And Mitsubishi Approve $2.07 Billion Copper World Development In Arizona, Pulse 2.0, Oct. 22, 2026
- Copper World mine approved for construction in Santa Rita Mountains, Arizona's Family (AZFamily), Oct. 22, 2026


