Audi selects Peach County, Georgia, for $4 billion first U.S. plant, with grading in 2027.
The Middle Georgia Megasite plant is planned for 200,000 SUVs a year. Construction is set for 2028 and full production for 2031.
Quick answer
Audi AG: $4 billion investment in Peach County, Ga. Stage: Announced. Timeline: Announced Oct. 24, 2026. Grading begins in 2027. Construction starts in 2028. Full production expected in 2031. Likely to buy: mass grading and site work, rail spur and utilities, structural steel, concrete and foundations.

By Capex Wire StaffPublished 2 min read
Audi AG plans to invest approximately $4 billion in its first U.S. manufacturing plant at the Middle Georgia Megasite in Peach County, near Macon, Georgia, Gov. Brian Kemp's office and the Georgia Department of Economic Development announced Oct. 24.
The plant will build premium SUVs tailored to North American customers, with full production expected at 200,000 units a year. The state says the project will create approximately 4,500 jobs.
Schedule
- 2027: grading begins.
- 2028: construction starts.
- 2031: full production expected.
The schedule comes from the state's announcement. FOX 5 Atlanta, reporting on a news conference Kemp held at the Georgia State Capitol on Oct. 26, said factory construction would start next year, which matches the grading date.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $126 billion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
The site
The Middle Georgia Megasite is marketed by the Development Authority of Peach County and the Mid-Georgia Gateway Joint Development Authority, which covers Peach, Houston and Macon-Bibb counties. The site has access to Norfolk Southern rail. The ports of Savannah and Brunswick can be reached by rail in under five hours, and Hartsfield-Jackson Atlanta International Airport is a 90-minute drive, according to the state.
Audi cited speed to market, workforce, access to consumer markets and an established automotive supply chain as reasons for the choice. Georgia Quick Start, the state's workforce program, will design a dedicated training facility for the plant and build a customized curriculum with the Technical College System of Georgia.
Still pending
The deal is not final. Capitol Beat reported that the contracts have not been signed and that Audi's board of directors must still approve the project. Kemp declined to detail the incentive package and said the information would become public later.
Pat Wilson, commissioner of the Georgia Department of Economic Development, said the jobs will pay an average above $63,000 a year. "This is not the manufacturing of yesteryear," Wilson said, according to FOX 5 Atlanta.
Gernot Döllner, chief executive of Audi AG, described the project as "a new home for Audi in America."
What is not disclosed
The announcement does not give the size of the buildings, the acreage Audi will occupy or a city address. No general contractor, engineering firm or grading contractor has been named. The incentive package has not been released, and the date of the Audi board vote was not given. Who pays for site grading, the state, the local authorities or Audi, is not stated.
- Owner
- Audi AG
- Investment
- $4 billion (approximately $4 billion, per state announcement; Audi board approval still pending per news reports)
- Location
- Peach County, Georgia
- Type
- Auto assembly plant, new construction
- Stage
- Announced
- Timeline
- Announced Oct. 24, 2026. Grading begins in 2027. Construction starts in 2028. Full production expected in 2031.
- Contractor / EPC
- Not announced
- Sources
- Georgia Department of Economic Development, Capitol Beat via Rough Draft Atlanta, FOX 5 Atlanta
Why it matters
The state has given a clear sequence: grading in 2027 and construction in 2028. Earthwork, utility and rail contractors are first in line, and no builder has been named, so there is time to qualify.
What this project buys
- Mass grading and site work
- Rail spur and utilities
- Structural steel
- Concrete and foundations
- Electrical
- Mechanical and process equipment installation
When to approach: Grading in 2027 and building construction in 2028. Site work packages come first. Builder not announced.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Sources
- Audi AG Selects Georgia to Invest $4 Billion in First US Manufacturing Facility, Georgia Department of Economic Development, Oct. 24, 2026
- Audi selects Peach County for its first U.S. plant, Capitol Beat via Rough Draft Atlanta, Oct. 27, 2026
- Kemp, state officials detail planned $4B Audi factory in Georgia, FOX 5 Atlanta, Oct. 26, 2026