Edwards Vacuum finishes a $319 million semiconductor pump plant in Genesee County, New York.

Gov. Kathy Hochul announced the completion of the dry pump factory at the STAMP site near Basom, with up to 600 jobs pledged as hiring ramps through 2027.

Quick answer

Edwards Vacuum (Atlas Copco Group): $319 million investment in Alabama, N.Y. Stage: Operating. Timeline: New York and Sen. Chuck Schumer announced the project for the STAMP site in the town of Alabama on Nov. 2, 2022, with a groundbreaking ceremony roughly two years before the 2026 opening. The U.S. Department of Commerce reached a preliminary $18 million CHIPS Act funding agreement with Edwards in October 2024, finalized in January 2025. By a Sept. 3, 2026 company release, Edwards general manager Dan Papsidero said the 250,000 square foot plant at 6685 Crosby Road was making a small number of pumps and had posted about half of this year's planned hiring, with headcount likely around 100 professionals by the end of 2026, potentially climbing to 200 or more in 2027 and as high as 300 or more if demand grows. The Batavian reported Oct. 15, 2026 that the plant held only a temporary certificate of occupancy, with a punch list covering a fire alarm configuration, landscaping and lighting, and that it had just received LEED certification. Edwards held a ribbon cutting and grand opening on Oct. 29, 2026, the same day Gov. Hochul's office announced the completion of construction, putting the campus at 240,000 square feet. Likely to buy: precision equipment installation and commissioning, electrical and switchgear systems, mechanical, hvac and process piping, material handling and warehousing.

Precision rollers and belts on an automated machine inside a modern manufacturing facility
Illustrative photo. Photo: Freek Wolsink / Pexels

By Capex Wire NewsroomPublished 4 min read

Edwards Vacuum has finished construction of a $319 million dry pump manufacturing plant in Genesee County, New York, Gov. Kathy Hochul's office announced Oct. 29, 2026. The facility, at the Western New York Science & Technology Advanced Manufacturing Park (STAMP) near Basom in the town of Alabama, is pledged to support up to 600 jobs as the company ramps up hiring.

What is being built

The plant produces dry vacuum pumps used to manipulate silicon wafers and control industrial gases in chipmaking, with a stated capacity of up to 10,000 pumps a year. The state's announcement puts the campus at 240,000 square feet; Edwards' and the Genesee County Economic Development Center's own press materials have described it as 250,000 square feet, at 6685 Crosby Road. The all electric facility is seeking LEED certification, which it has since received, and draws most of its power from hydroelectricity generated at nearby Niagara Falls, the company has said. Martin Tollner, president of Atlas Copco Group's Semiconductor division, said the opening marks a milestone in Edwards' commitment to serving the global semiconductor industry. "As chip manufacturers continue to invest in next-generation technologies and expanded production in the United States, Edwards is proud to invest alongside them," Tollner said. "This facility strengthens domestic manufacturing capabilities, supports a more resilient semiconductor supply chain, and demonstrates our commitment to providing world-class vacuum technology built in the United States."

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 118 projects like this

$9.90/month · cancel anytime in one click

Jobs and timeline

State and company officials have cited up to 600 jobs since the project was first announced in 2022, a figure tied to New York's incentive package. The pace on the ground has been more gradual. In a company release, "We're undergoing a massive hiring push as we ramp up production," said Dan Papsidero, Edwards general manager. "Machine installations and prove-out activities are well underway. We are making parts, we are making a small number of pumps, and that's only going to increase in the very near future." Papsidero said the company had posted roughly half of this year's planned positions. "We will likely be around 100 (professionals) by the end of this year and into the next year will potentially climb to 200 or more ... as demand increases this facility could max out with over 300 people, and then we could be expanding the facility in the future." The Batavian reported Oct. 15, 2026 that the facility held only a temporary certificate of occupancy, after Town of Alabama Supervisor Rob Crossen said firefighters had responded to a fire alarm at the unopened plant over a weekend. "That just brought some issues with how the fire alarms are configured and how we have to work better with that alarm," Crossen said. Project manager Dave Ciurzynski said the cause was a shut valve that lowered pressure and tripped the alarm, and said the site had just received its LEED certification days before the grand opening.

Who is building it

Edwards Vacuum is a subsidiary of Atlas Copco Group. Sen. Chuck Schumer said he personally asked Edwards about four years ago to build its first American plant along Upstate New York's semiconductor corridor, and secured the $18 million in federal CHIPS Act funding. "Edwards Vacuum, America's first semiconductor dry pump manufacturing facility, is open for business right here in Genesee County!" Schumer said at the Oct. 29 ribbon cutting. "Today, major semiconductor companies will now look to Genesee County as home to the advanced vacuum technology they need for their chip fabs that Edwards Vacuum will now make in the USA, bringing this critical high-tech supply chain to our shores and our state." No general contractor has been named publicly in state, company or local reporting.

ItemFigure
Total investment$319 million
Facility size240,000 to 250,000 square feet, depending on the source
Jobs pledgedup to 600
Pump production capacityup to 10,000 a year
Federal CHIPS Act funding$18 million
State tax credits (Excelsior and investment)up to $21 million

What the project bought

Empire State Development awarded Edwards up to $21 million through Excelsior Jobs Tax Credits and Investment Tax Credits tied to the jobs pledge, plus an additional $1 million for workforce training. The New York Power Authority is supplying a 4.9 megawatt Niagara hydropower allocation plus 2.1 megawatts of high load factor power procured on the open market. Empire State Development President, CEO and Commissioner Hope Knight said the facility represents hundreds of good paying jobs and millions of dollars invested in Upstate New York. "Under Gov. Kathy Hochul's leadership, New York is building a strong semiconductor ecosystem statewide, furthering its global reputation as the preeminent hub for advanced manufacturing," Knight said.

What happens next

With construction complete, the near term work at the site shifts to hiring, training and ramping output toward the plant's rated capacity. Edwards is working with Genesee Community College, Monroe Community College, Erie Community College and the Northland Workforce Training Center to recruit and train workers. Capex Wire found no report that the project has been paused, denied or canceled. Local reporting suggests the jobs ramp may take longer than the original 600 job pledge implies, so trade contractors and workforce vendors in the Finger Lakes region should watch Edwards' own hiring updates rather than the 2022 announcement alone.

Project fileNY
Owner
Edwards Vacuum (Atlas Copco Group)
Investment
$319 million (company and state figure for the Genesee County facility, as stated in New York's Oct. 29, 2026 completion announcement)
Location
Alabama, Genesee County, New York
Type
Semiconductor equipment plant, new facility
Stage
Operating
Timeline
New York and Sen. Chuck Schumer announced the project for the STAMP site in the town of Alabama on Nov. 2, 2022, with a groundbreaking ceremony roughly two years before the 2026 opening. The U.S. Department of Commerce reached a preliminary $18 million CHIPS Act funding agreement with Edwards in October 2024, finalized in January 2025. By a Sept. 3, 2026 company release, Edwards general manager Dan Papsidero said the 250,000 square foot plant at 6685 Crosby Road was making a small number of pumps and had posted about half of this year's planned hiring, with headcount likely around 100 professionals by the end of 2026, potentially climbing to 200 or more in 2027 and as high as 300 or more if demand grows. The Batavian reported Oct. 15, 2026 that the plant held only a temporary certificate of occupancy, with a punch list covering a fire alarm configuration, landscaping and lighting, and that it had just received LEED certification. Edwards held a ribbon cutting and grand opening on Oct. 29, 2026, the same day Gov. Hochul's office announced the completion of construction, putting the campus at 240,000 square feet.
Contractor / EPC
Not announced
Sources
Office of Governor Kathy Hochul, FingerLakes1.com, The Batavian, The Batavian (Brian Quinn), The Batavian (press release)

Why it matters

A completed, ramping dry pump plant means near term demand for process technicians, maintenance contractors and precision tooling and components suppliers in the Finger Lakes region, and it keeps momentum behind the STAMP megasite as New York courts further semiconductor supply chain tenants.

What this project buys

  • Precision equipment installation and commissioning
  • Electrical and switchgear systems
  • Mechanical, HVAC and process piping
  • Material handling and warehousing
  • Fire protection and life safety systems
  • Controls and automation

When to approach: Construction is finished; Edwards is hiring toward its pledged ceiling of up to 600 jobs as production ramps. No general contractor has been named publicly, and no new bid packages are expected at the site since the build is complete.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is Edwards Vacuum's new plant in New York?

At 6685 Crosby Road in the town of Alabama, Genesee County, at the Western New York Science & Technology Advanced Manufacturing Park (STAMP), near Basom.

How many jobs will the Genesee County plant create?

New York state says up to 600. Edwards' own general manager said the company would likely employ around 100 people by the end of 2026, potentially climbing to 200 or more in 2027 and as high as 300 or more if demand grows.

When did construction finish on the Edwards Vacuum plant?

Gov. Kathy Hochul announced completion of construction on Oct. 29, 2026, with a grand opening the next day, though local reporting in mid-October described a temporary certificate of occupancy and remaining punch-list work.

Who built and owns the Edwards Vacuum facility?

Edwards Vacuum, part of the Atlas Copco Group, owns the plant. No general contractor has been named publicly.

What does the Genesee County plant make?

Dry vacuum pumps used to control conditions inside semiconductor manufacturing processes, with a stated capacity of up to 10,000 pumps a year.

Sources