Fermi America gets draft NRC environmental review for four reactors in Carson County, Texas.
The Nuclear Regulatory Commission issued a draft environmental impact statement for Fermi America's four-unit AP1000 project at Project Matador, with a final decision targeted for December.
Quick answer
Fermi America LLC (dba Fermi America): investment not disclosed in Carson County, Texas. Stage: Announced. Timeline: Combined license application submitted June 2025; NRC opened the environmental scoping process in March 2026; draft EIS issued for comment Oct. 9, 2026; comment period closed Nov. 23, 2026; final EIS targeted for December 2026, according to the NRC's project schedule. Likely to buy: nuclear island civil works, reactor and module installation, mechanical and piping, electrical and substation.

By Capex Wire NewsroomPublished 3 min read
The Nuclear Regulatory Commission has issued a draft environmental impact statement for Fermi America's plan to build four AP1000 reactors in the Texas Panhandle, a licensing milestone that moves the project closer to a construction decision. The draft, published for comment on Oct. 9, 2026, evaluates the environmental effects of granting or denying a combined license for the reactors, which the company calls Project Matador Nuclear Units 1 through 4.
What is being reviewed
Fermi America LLC, doing business as Fermi America, first submitted its combined license application to the NRC in June 2025 for four AP1000 pressurized water reactors, a standard design also used at the Vogtle plant in Georgia. The reactors would be built at the Project Matador Advanced Energy and Intelligence Campus in Carson County, Texas, next to the U.S. Department of Energy's Pantex Plant near Amarillo, according to the NRC's Federal Register notice. The draft EIS weighs the environmental, economic and technical costs and benefits of issuing the license against a no action alternative that would deny it. The NRC staff's preliminary recommendation favors issuing the license, contingent on Fermi America separately passing the agency's safety review, the notice said. The full draft is on file with the NRC under Accession No. ML26261A417 and under Docket ID NRC-2026-0100 on regulations.gov.
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 948 projects like this$9.90/month · cancel anytime in one click
Timeline and the EIS pilot program
What sets this review apart is who wrote it. Project Matador is the first project in an NRC pilot program under which the applicant, not NRC staff, prepares the draft environmental review, with the agency supervising and checking the work. The program is meant to speed up licensing for new reactors without skipping required environmental analysis. The public comment period on the draft ran 45 days, from Oct. 9 through Nov. 23, 2026, and could be submitted through regulations.gov, by mail or by email to the NRC. The agency's project schedule lists a final environmental impact statement as targeted for December 2026, after NRC staff finish responding to the public comments it received.
| Milestone | Status or date |
|---|---|
| Reactors proposed | Four AP1000 units (PMN Units 1 through 4) |
| Combined nuclear capacity | About 4.4 gigawatts |
| Draft EIS comment deadline | Nov. 23, 2026 |
| Final EIS target | December 2026 |
Who is building it
Fermi America was founded with Texas Tech University System, which leased the company the land for the Project Matador campus. The campus is designed around four AP1000 reactors supplying about 4.4 gigawatts of nuclear capacity, part of a larger power campus the company has said it plans to expand with natural gas, solar and battery storage. The NRC's review covers only the nuclear units. No general contractor or design firm for the reactor construction itself has been confirmed in NRC filings; Westinghouse Electric Company designed the AP1000 reactor model named in the application.
What happens next
With the comment period closed, NRC staff must now respond to the input it received before finishing the final EIS, which the agency's schedule points to in December 2026. A final EIS is a required step before the NRC's commissioners can hold a mandatory hearing and decide whether to grant the combined license, a decision that is separate from, and in addition to, the agency's ongoing safety review of the application. Companies that sell site work, concrete, steel, piping, electrical and controls work to nuclear construction typically see bid activity accelerate once a combined license is granted, not before, so contractors watching Project Matador should treat the environmental review as a signal of progress rather than a greenlight to bid.
- Owner
- Fermi America LLC (dba Fermi America)
- Investment
- Not disclosed
- Location
- Carson County, Texas
- Type
- Nuclear, 4,468 MW
- Stage
- Announced
- Timeline
- Combined license application submitted June 2025; NRC opened the environmental scoping process in March 2026; draft EIS issued for comment Oct. 9, 2026; comment period closed Nov. 23, 2026; final EIS targeted for December 2026, according to the NRC's project schedule.
- Contractor / EPC
- Not announced
- Sources
- Federal Register (NRC notice), American Nuclear Society (Nuclear News), World Nuclear News
Why it matters
A completed draft EIS and a December target for the final review show Fermi America's four reactor license is advancing through the NRC's newest, faster review pilot, a step construction and engineering firms can track before bid packages for the reactors themselves are released.
What this project buys
- Nuclear island civil works
- Reactor and module installation
- Mechanical and piping
- Electrical and substation
- Concrete and rebar
- Controls and instrumentation
When to approach: Not disclosed; construction bid packages are not expected until after the NRC grants the combined license, which follows the final EIS and a mandatory commission hearing.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Fermi America's nuclear plant?
At the Project Matador Advanced Energy and Intelligence Campus in Carson County, Texas, next to the U.S. Department of Energy's Pantex Plant near Amarillo, according to the NRC's Federal Register notice.
How many reactors will Project Matador have?
Four AP1000 pressurized water reactors, designated PMN Units 1 through 4, with a combined capacity of about 4.4 gigawatts.
When will the NRC finish its environmental review?
The public comment period on the draft environmental impact statement closed Nov. 23, 2026. The NRC's project schedule targets December 2026 for the final environmental impact statement.
Who is building it?
Fermi America LLC, doing business as Fermi America, is the applicant. The AP1000 reactor design is Westinghouse Electric Company's. No construction contractor for the reactors has been confirmed in NRC filings.
Is this the first time the NRC has let a company write its own environmental review?
Yes. Project Matador is the first application in an NRC pilot program in which the applicant prepares the draft environmental impact statement under NRC supervision, rather than NRC staff writing it.
Sources
- Fermi America LLC (dba Fermi America); Project Matador Advanced Energy and Intelligence Campus AP1000 Units 1-4; Draft Environmental Impact Statement, Federal Register (NRC notice), Oct. 9, 2026
- Fermi America, Blue Energy make strides in Texas, American Nuclear Society (Nuclear News), Oct. 9, 2026
- NRC seeks public comments on Project Matador environmental review, World Nuclear News, March 25, 2026