Intel moves its Fab 62 chip plant in Chandler, Arizona, into tool installation, targeting 2028.

Intel says construction and tool installation are now fully underway at Fab 62, its sixth large scale chip factory at the Ocotillo campus in Chandler, with operations targeted for late 2028.

Quick answer

Intel Corporation: investment not disclosed in Chandler, Ariz. Stage: Under construction. Timeline: Intel began a $20 billion expansion of its Ocotillo campus in Chandler, Arizona, in 2021, covering Fab 52 and Fab 62. Fab 52 opened in 2025 and now runs Intel's 18A process, which entered high volume manufacturing that year. Fab 62 construction slowed for more than a year while Intel confirmed sufficient chip demand to proceed. On Oct. 22, 2026, industry researcher TrendForce reported that equipment installation had begun at Fab 62. On Nov. 9, 2026, KTAR News reported that Intel had confirmed construction and tool installation were fully underway, with operations targeted for the end of 2028. Intel's own account of the milestone appeared in a company newsroom post by Naga Chandrasekaran, Intel Foundry's executive vice president and chief technology and operations officer. Likely to buy: semiconductor tool rigging and installation, cleanroom certification and commissioning, process piping and ultrapure water systems, electrical and power distribution.

Aerial view of Intel's Ocotillo semiconductor campus in Chandler, Arizona, where Fab 62 is now under construction.
Illustrative photo. Photo: neepster / Wikimedia Commons, CC BY-SA 2.0

By Capex Wire NewsroomPublished 2 min read

Intel said construction and tool installation are now fully underway at Fab 62, a new chip factory on its Ocotillo campus in Chandler, Arizona, with chip production targeted to begin by the end of 2028. The plant is part of a $20 billion expansion of Intel's Arizona operations that the company began in 2021, and it will become Intel's sixth large scale chip factory at the Ocotillo campus.

What is being built

Fab 62 sits next to a factory Intel opened at Ocotillo in 2025, which makes the company's most advanced chips, including Panther Lake processors for laptops, on its 18A manufacturing process. "Today, I am pleased to share that construction and tool installation at Fab 62 are now fully underway," Naga Chandrasekaran, Intel Foundry's executive vice president and chief technology and operations officer, wrote in a company newsroom post, adding that operations are expected to begin by the end of 2028. Intel has not said which chipmaking process Fab 62 will run. Industry researcher TrendForce reported that the plant could support Intel's 18A, 18A-P or 14A nodes, and that the neighboring Fab 52 already manufactures 18A chips, though Intel has not confirmed which node the new factory will produce.

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 118 projects like this

$9.90/month · cancel anytime in one click

Jobs and timeline

Intel has not disclosed how much Fab 62 itself will cost or how many jobs it will create. "Meeting demand requires scale," Chandrasekaran wrote in the same post, according to KTAR News, which reported that construction had slowed for more than a year while Intel confirmed there was enough demand to move ahead. Fab 62 and the neighboring Fab 52 were both part of the $20 billion Arizona expansion Intel began in 2021, the Phoenix Business Journal reported, according to KTAR. Intel's regional headcount has fallen since that announcement. The company employed nearly 10,000 people in the Phoenix area as of October 2025, down from more than 12,000 in 2024, the Business Journal reported.

ItemFigure
Arizona expansion Intel began in 2021$20 billion
Target year for Fab 62 operations2028
Intel Phoenix area employees, October 2025about 10,000
Intel Phoenix area employees, 2024more than 12,000

Who is building it

Intel owns and is building Fab 62 itself, with no general contractor or equipment vendor named publicly for the project. Chandrasekaran's column also described Intel's broader United States supply chain, saying the company works with more than 4,500 suppliers in 49 states, generating more than $29 billion in annual domestic spending. Those figures describe Intel's nationwide operations and are not specific to the Chandler project. The company has also said its 18A node, the process already running at the neighboring Ocotillo fab, entered high volume manufacturing in 2025.

What happens next

Intel has not published a construction schedule or bid calendar for the remaining Fab 62 work. The company says tool installation is underway now, with chip production targeted for the end of 2028, after a slowdown of more than a year while it waited to confirm sufficient demand, according to KTAR News. Capex Wire found no report that the Fab 62 project has been paused, denied or canceled since Intel confirmed construction and tool installation were underway.

Project fileAZ
Owner
Intel Corporation
Investment
Not disclosed (Intel has not disclosed a cost figure specific to Fab 62. The plant is part of a $20 billion Arizona expansion the company began in 2021, covering both Fab 62 and the neighboring Fab 52, according to the Phoenix Business Journal as reported by KTAR News.)
Location
Chandler, Maricopa County, Arizona
Type
Semiconductor fab, new and modernization
Stage
Under construction
Timeline
Intel began a $20 billion expansion of its Ocotillo campus in Chandler, Arizona, in 2021, covering Fab 52 and Fab 62. Fab 52 opened in 2025 and now runs Intel's 18A process, which entered high volume manufacturing that year. Fab 62 construction slowed for more than a year while Intel confirmed sufficient chip demand to proceed. On Oct. 22, 2026, industry researcher TrendForce reported that equipment installation had begun at Fab 62. On Nov. 9, 2026, KTAR News reported that Intel had confirmed construction and tool installation were fully underway, with operations targeted for the end of 2028. Intel's own account of the milestone appeared in a company newsroom post by Naga Chandrasekaran, Intel Foundry's executive vice president and chief technology and operations officer.
Contractor / EPC
Not announced
Sources
Intel Newsroom (opinion column by Naga Chandrasekaran), KTAR News, TrendForce

Why it matters

A sixth high volume fab at an existing campus means more process tool installation, cleanroom commissioning and utility work layered onto standing infrastructure, a different trade mix than greenfield construction, and it signals Intel is still committing capital to U.S. leading edge capacity despite the earlier slowdown.

What this project buys

  • Semiconductor tool rigging and installation
  • Cleanroom certification and commissioning
  • Process piping and ultrapure water systems
  • Electrical and power distribution
  • HVAC and cleanroom air systems
  • Specialty gas and chemical delivery systems

When to approach: Tool installation is underway now. Intel has not published a bid schedule or named a general contractor, so trade contractors should watch for equipment vendor announcements and any update tied to the end of 2028 production target.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is Intel building its new Fab 62 chip factory?

At Intel's Ocotillo campus in Chandler, Arizona, next to the fab the company opened there in 2025.

How many jobs will Intel's Fab 62 in Chandler create?

Intel has not disclosed a jobs figure for Fab 62. The company's total Phoenix area headcount was nearly 10,000 as of October 2025, down from more than 12,000 in 2024, according to the Phoenix Business Journal.

When will construction finish and production start at Fab 62?

Intel says construction and tool installation are fully underway now, with chip production targeted to begin by the end of 2028.

Who is building the Intel Fab 62 plant in Arizona?

Intel Corporation owns and is building Fab 62 itself. The company has not named a general contractor or primary equipment vendor publicly.

What chips will Intel's Fab 62 in Chandler make?

Intel has not confirmed the process node. Industry researcher TrendForce reported the plant could support Intel's 18A, 18A-P or 14A nodes.