Public Service Company of Oklahoma breaks ground on a $540 million, 450 MW gas plant near Oologah.
The utility started construction on two new gas turbines at its Northeastern Energy Campus in Rogers County even as a zoning lawsuit with the county remains unresolved.
Quick answer
Public Service Company of Oklahoma (AEP): $539.8 million investment in Oologah, Okla. Stage: Under construction. Timeline: Groundbreaking Nov. 9, 2026. Commercial operation expected December 2028. Likely to buy: site work and foundations, structural steel erection, electrical and controls, gas pipeline tie-in.

By Capex Wire StaffPublished 2 min read
Public Service Company of Oklahoma said Nov. 9, 2026 that it broke ground on two new natural gas generating units at its Northeastern Energy Campus near Oologah, in Rogers County, adding 450 megawatts of dispatchable power to the AEP subsidiary's fleet.
The project, called Northeastern Units 5 and 6, will install two General Electric combustion turbines in a simple cycle configuration at the existing campus rather than at a new site. PSO President and Chief Operating Officer Leigh Anne Strahler said in the company's release, "Reliable electricity starts with planning ahead and making responsible investments that add value for our customers," adding, "By adding new generation at an existing site, we're making practical use of infrastructure already in place."
What is being built
Energy Transfer was selected through a competitive bidding process to handle natural gas delivery to the new units, PSO said. The release does not disclose a dollar figure for the project. Construction Review Online, citing PSO's regulatory filings, put the estimated capital cost at approximately $539.8 million, covering direct project costs, indirect costs and owner expenses.
| Item | Figure |
|---|---|
| Capacity | 450 MW (two GE combustion turbines) |
| Estimated cost | About $539.8 million, per regulatory filings cited by Construction Review Online |
| Groundbreaking | Nov. 9, 2026 |
| Commercial operation | December 2028 |
| Wider portfolio | About 1,300 MW of new gas, wind and battery capacity |
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $126 billion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
Jobs and timeline
Neither PSO's release nor the independent coverage gives a construction jobs figure. PSO expects the units to reach commercial operation in December 2028. The utility has forecast summer capacity deficits of 10 MW in 2027, growing to 470 MW in 2028 and 1,766 MW in 2029, which the new units are meant to help cover.
Who is building it
PSO has not named a construction contractor for Units 5 and 6. General Electric is supplying the combustion turbines, and Energy Transfer will handle gas delivery under its competitively bid contract. No pipeline length, EPC arrangement or emissions permit detail has been disclosed.
A zoning fight still in court
The Oklahoma Corporation Commission conditionally approved PSO's roughly $1.2 billion generation buildout, which includes Units 5 and 6, three battery storage systems and wind and gas agreements, in an order in May 2026. That order blocks PSO from recovering construction costs for Units 5 and 6 until a final, non-appealable court order grants the zoning the company needs.
The Rogers County Board of Adjustment denied PSO's request for a special exception covering the project in November 2025. PSO sued the county in Rogers County District Court, and a second suit followed in January 2026 against the county commissioners. A hearing on the county's motion to dismiss was pending as of May 2026. Construction Review Online noted that PSO's November 2026 groundbreaking announcement does not explain how the zoning dispute was resolved.
What happens next
With construction underway, PSO's own schedule points to bid packages for site work, foundations, structural steel, electrical and mechanical piping over the next roughly two years, ahead of the December 2028 commercial operation target. The outcome of the Rogers County litigation could still affect PSO's ability to recover project costs from ratepayers, though it has not stopped construction.
- Owner
- Public Service Company of Oklahoma (AEP)
- Investment
- $539.8 million (estimated capital cost of about $539.8 million from PSO's regulatory filings, per Construction Review Online; PSO's own groundbreaking release does not state a dollar figure)
- Location
- Oologah, Rogers County, Oklahoma
- Type
- Natural gas power plant, two combustion turbine units (expansion of existing campus)
- Stage
- Under construction
- Timeline
- Groundbreaking Nov. 9, 2026. Commercial operation expected December 2028.
- Contractor / EPC
- Not announced
- Sources
- Public Service Company of Oklahoma, Construction Review Online
Why it matters
A 450 MW gas plant expansion means foundation, structural steel, electrical and gas pipeline work bidding out over the next two years, plus a separate battery storage project and new gas lateral at the same Rogers County site.
What this project buys
- Site work and foundations
- Structural steel erection
- Electrical and controls
- Gas pipeline tie-in
- Mechanical piping
- Instrumentation
When to approach: No contractor has been named for the two combustion turbine units. Site work, foundations and balance of plant construction would need to ramp up now for a December 2028 commercial operation date.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is PSO building its new gas plant?
At the Northeastern Energy Campus near Oologah, in Rogers County, Oklahoma, expanding an existing generation site rather than building on a new one.
How much will the PSO Northeastern Units 5 and 6 project cost?
PSO's own groundbreaking release does not give a dollar figure. Construction Review Online puts the estimated capital cost at about $539.8 million, citing PSO's regulatory filings.
When will the new gas units start operating?
PSO expects Northeastern Units 5 and 6 to enter commercial operation in December 2028.
Who is building the PSO Northeastern expansion?
PSO has not named a construction contractor. Energy Transfer was selected through competitive bidding to handle natural gas delivery to the new units. General Electric is supplying the combustion turbines.
Is there a dispute over the PSO Oologah project?
Yes. The Rogers County Board of Adjustment denied PSO a special exception for the site in November 2025, and PSO sued the county. As of PSO's November 2026 groundbreaking, the litigation was still pending in Rogers County District Court.
Sources
- PSO Breaks Ground on New Natural Gas Generation at Northeastern Energy Campus, Public Service Company of Oklahoma, Nov. 9, 2026
- PSO Breaks Ground on $540 Million, 450 MW Natural Gas Project in Oklahoma, Construction Review Online, Nov. 10, 2026


