Applied Materials, Inc.

Applied Materials is converting a 181,655 sq ft building in Chandler, AZ into a semiconductor equipment plant, with more than $200 million planned.

Chandler, Maricopa County, Arizona

Investment

$200 million

Applied Materials' Aug. 6, 2025 figure for its total planned investment in the Chandler facility, covering the building purchase, renovation and equipment.

Project fileAZ
Owner
Applied Materials, Inc.
Investment
$200 million (Applied Materials' Aug. 6, 2025 figure for its total planned investment in the Chandler facility, covering the building purchase, renovation and equipment.)
Location
Chandler, Maricopa County, Arizona
Address
2377 South Arizona Avenue
Sector
Semiconductors & Electronics
Type
Semiconductor equipment plant, building conversion
Stage
Financed
Construction start
Not disclosed
Completion
Not disclosed
Size
181,655 sq. ft.
Contractor / EPC
Not announced
Source
AZ Big Media, Aug. 13, 2025
Added to the map
Nov. 26, 2026

What this project buys

  • Interior tenant improvements and demolition
  • Cleanroom build-out and certification
  • Electrical and power distribution upgrades
  • HVAC and process cooling systems
  • Process piping and specialty gas systems
  • Fire protection

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in Arizona

  • Nov. 22, 2026
    Tombstone Resources, LLCopen record

    Data center and battery energy storage system campus, proposed

    Tombstone Resources, tied to SpaceX, seeks a Cochise County permit for a 6 GW, nine building data center campus.

    Cochise, AZData Centers$50 billionAnnounced
  • Nov. 20, 2026
    Owner hidden

    Battery storage project, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Maricopa County, AZPower & Energy$120.2 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery storage project plus solar power plant, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Cochise County, AZPower & Energy$208.4 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery storage project plus solar power plant, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Cochise County, AZPower & Energy$208.4 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Solar power plant, new construction

    Likely to buy: Site work and grading, Pile driving and racking, Electrical and collection system

    Mohave County, AZPower & Energy$29.3 millionAnnounced