Capex WireMore than $126 billion in U.S. capital projects on the map, with new ones every day. Just $9.90/month, cancel anytime.Subscribe ›
Thursday, Nov. 19, 2026 · U.S. editionNov. 19, 2026How we reportLog inSubscribe to Capex Wire

U.S. capital projects before the bid list closes.

Power & Energy · Announced

Owner hidden

Natural gas combustion turbine, 467 MW in Hot Spring County, Arkansas.

Hot Spring County, Arkansas

Investment

Not disclosed

EIA does not report project cost

Project fileAR
Owner
Owner hidden
Investment
Not disclosed (EIA does not report project cost)
Location
Hot Spring County, Arkansas
Address
Owner hidden
Sector
Power & Energy
Type
Natural gas combustion turbine, 467 MW
Stage
Announced
Construction start
Not disclosed
Completion
July 31, 2028
Design firm
Owner hidden
Contractor / EPC
Owner hidden
Source
Federal energy filing (EIA), Sept. 30, 2026
Added to the map
Nov. 17, 2026

Owner hidden

Get there first: every project owner on the U.S. Project Map.

The owner and source of this project are hidden in the open version. They are part of the full Project Map. Subscribers see every owner, address, design firm and source on the Project Map. $9.90 per month. Cancel anytime in one click.

What this project buys

  • Gas turbine installation
  • Mechanical and piping
  • Electrical and substation
  • Concrete and foundations
  • Gas interconnect
  • Controls and instrumentation

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in Arkansas

  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 500 MW + Battery storage, 250 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Mississippi County, ARPower & EnergyNot disclosedUnder construction
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 500 MW + Battery storage, 250 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Mississippi County, ARPower & EnergyNot disclosedUnder construction
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 500 MW + Battery storage, 250 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Mississippi County, ARPower & EnergyNot disclosedUnder construction
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 600 MW + Battery storage, 350 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Jefferson County, ARPower & EnergyNot disclosedAnnounced
  • Nov. 17, 2026
    Owner hidden

    Natural gas combined cycle, 820 MW

    Likely to buy: Gas and steam turbine installation, Heat recovery steam generators, Mechanical and piping

    Jefferson County, ARPower & EnergyNot disclosedAnnounced