Manufacturing · Under construction

Owner hidden

Battery plant (cells, modules), new construction in Queen Creek, Maricopa County, Arizona.

Queen Creek, Maricopa County, Arizona

Investment

$2.5 billion

estimated investment per Rhodium Group-MIT/CEEPR Clean Investment Monitor (CC BY 4.0)

Project fileAZ
Owner
Owner hidden
Investment
$2.5 billion (estimated investment per Rhodium Group-MIT/CEEPR Clean Investment Monitor (CC BY 4.0))
Location
Queen Creek, Maricopa County, Arizona
Address
Owner hidden
Sector
Manufacturing
Type
Battery plant (cells, modules), new construction
Stage
Under construction
Construction start
Not disclosed
Completion
Not disclosed
Design firm
Owner hidden
Contractor / EPC
Owner hidden
Source
, Nov. 20, 2026
Added to the map
Nov. 20, 2026

Owner hidden

Get there first: every project owner on the U.S. Project Map.

The owner and source of this project are hidden in the open version. They are part of the full Project Map. Subscribers see every owner, address, design firm and source on the Project Map. $9.90 per month. Cancel anytime in one click.

What this project buys

  • Site work and foundations
  • Structural steel erection
  • Electrical and substation
  • Mechanical and HVAC
  • Process piping
  • Fire protection

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in Arizona

  • Nov. 20, 2026
    Owner hidden

    Battery storage project, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Maricopa County, AZPower & Energy$120.2 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery storage project plus solar power plant, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Cochise County, AZPower & Energy$208.4 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery storage project plus solar power plant, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Cochise County, AZPower & Energy$208.4 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Solar power plant, new construction

    Likely to buy: Site work and grading, Pile driving and racking, Electrical and collection system

    Mohave County, AZPower & Energy$29.3 millionAnnounced
  • Nov. 20, 2026
    Owner hidden

    Battery storage project, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Maricopa County, AZPower & Energy$167.3 millionAnnounced