Oil, Gas & LNG · Filed / permitted

Owner hidden

Natural gas pipeline, expansion, 4.7 miles, 20-inch in Nevada.

Nevada

Investment

$18.9 million

estimated cost per EIA natural gas pipeline projects tracker

Project fileNV
Owner
Owner hidden
Investment
$18.9 million (estimated cost per EIA natural gas pipeline projects tracker)
Location
Nevada
Address
Owner hidden
Sector
Oil, Gas & LNG
Type
Natural gas pipeline, expansion, 4.7 miles, 20-inch
Stage
Filed / permitted
Construction start
Not disclosed
Completion
Not disclosed
Design firm
Owner hidden
Contractor / EPC
Owner hidden
Source
, Oct. 16, 2026
Added to the map
Nov. 19, 2026

Owner hidden

Get there first: every project owner on the U.S. Project Map.

The owner and source of this project are hidden in the open version. They are part of the full Project Map. Subscribers see every owner, address, design firm and source on the Project Map. $9.90 per month. Cancel anytime in one click.

What this project buys

  • Pipeline construction and welding
  • Right-of-way clearing and grading
  • Horizontal directional drilling
  • Compressor station construction
  • Coating and inspection
  • Hydrostatic testing

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in Nevada

  • Nov. 20, 2026
    Owner hidden

    Battery storage project, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Clark County, NVPower & Energy$152 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery plant (eam), expansion

    Likely to buy: Site work and foundations, Structural steel erection, Electrical and substation

    Sparks, NVManufacturing$2.1 billionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Critical minerals plant (lithium carbonate), new construction

    Likely to buy: Site work and foundations, Process piping, Electrical and instrumentation

    Thacker Pass, NVMetals & Mining$3.4 billionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Geothermal plant, new construction

    Likely to buy: Civil and concrete works, Mechanical and turbine installation, Electrical and substation

    Esmeralda County, NVPower & Energy$156.2 millionAnnounced
  • Nov. 20, 2026
    Owner hidden

    Sustainable aviation fuel plant (HEFA), expansion

    Likely to buy: Site work and foundations, Process piping, Electrical and instrumentation

    Clark County, NVOil, Gas & LNG$1.1 billionAnnounced