Capex WireMore than $126 billion in U.S. capital projects on the map, with new ones every day. Just $9.90/month, cancel anytime.Subscribe ›
Thursday, Nov. 19, 2026 · U.S. editionNov. 19, 2026How we reportLog inSubscribe to Capex Wire

U.S. capital projects before the bid list closes.

Power & Energy · Financed

Pecos Power Plant LLC

Pecos Power Plant LLC closed a Texas Energy Fund loan of about $459 million for a 452 MW gas plant in Reeves County. Power expected in 2027.

Reeves County, Texas

Investment

$459 million

state loan only; total project cost not disclosed

Project fileTX
Owner
Pecos Power Plant LLC
Parent company
Affiliates of Mercuria Energy Group and Continental Resources
Investment
$459 million (state loan only; total project cost not disclosed)
Location
Reeves County, Texas
Sector
Power & Energy
Type
Natural gas power plant, about 452 MW
Stage
Financed
Construction start
Not disclosed
Completion
Not disclosed
Contractor / EPC
Not announced
Source
Latham & Watkins, Oct. 20, 2026
Added to the map
Nov. 17, 2026

What this project buys

  • Gas turbine installation
  • Electrical and substation
  • Mechanical and piping
  • Concrete and foundations
  • Controls and instrumentation

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.