CF Industries, JERA and Mitsui break ground on $4 billion ammonia plant in Louisiana.
Blue Point One in Ascension Parish is set to be one of the world's largest low carbon ammonia plants, with production targeted for 2029.
Quick answer
CF Industries, JERA Co., Mitsui & Co.: $4 billion investment in Modeste, La. Stage: Under construction. Timeline: CF Industries, JERA and Mitsui announced a final investment decision in April 2025. Louisiana and the U.S. Army Corps of Engineers issued construction permits in July 2026. The joint venture broke ground Aug. 26, 2026. Production is targeted to start in 2029. Likely to buy: site work and civil construction, process piping, structural steel erection, electrical and instrumentation.

By Capex Wire NewsroomPublished 3 min read
CF Industries, JERA Co. and Mitsui & Co. broke ground on the Blue Point One ammonia plant in Ascension Parish, Louisiana, the companies and Louisiana Economic Development announced Aug. 26, 2026. The joint venture is building what the partners call one of the world's largest low carbon ammonia plants, with production targeted to start in 2029.
What is being built
Blue Point One will rise at the Blue Point Complex in Modeste, in Ascension Parish, part of the RiverPlex MegaPark on the west bank of the Mississippi River, about nine miles north of CF Industries' existing Donaldsonville Complex. The plant is designed to produce approximately 1.4 million metric tons of low carbon ammonia per year, according to CF Industries. The company reached a final investment decision on the roughly $4 billion project in April 2025, alongside a deal for Occidental's 1PointFive to capture and permanently store the plant's carbon dioxide. "We are proud to break ground on the Blue Point One joint venture, a transformative project," said Chris Bohn, CF Industries' president and CEO. Louisiana Economic Development Secretary Susan Bourgeois said "this is Louisiana doing what we do best."
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 66 projects like this$9.90/month · cancel anytime in one click
Ownership and cost
CF Industries holds 40% of the joint venture, JERA 35% and Mitsui 25%, under the structure the three companies announced when they took the final investment decision in April 2025. CF Industries has put the ammonia production facility's cost at approximately $4 billion, shared among the three equity partners, with the company separately funding an estimated $550 million in supporting infrastructure. CF Industries' own Blue Point project page lists the equity partners' direct project development cost at approximately $3.7 billion, a figure the company has used since construction began; this story uses the $4 billion figure from the companies' 2025 announcement for the full ammonia facility and notes the lower number as CF's updated project-page estimate.
Jobs and timeline
CF Industries estimates the project will generate about 3,900 direct construction jobs over four years, bringing roughly $800 million in construction wages and benefits, plus an estimated 3,400 additional indirect and induced jobs in the region. Once operating, the company expects about 103 permanent full-time jobs at the plant, averaging about $110,000 a year. Civil construction began after Louisiana and the U.S. Army Corps of Engineers issued permits in July 2026 for the ammonia plant and common infrastructure, CF Industries has said. The companies are targeting the start of ammonia production in 2029.
Who is building it and what the project will buy
Technip Energies holds the engineering, procurement and module fabrication contract for the plant, and Topsoe is supplying the process technology license, according to CF Industries' April 2025 announcement. No general site contractor was named in the sources reviewed for this story. A project of this scale typically draws heavy civil and site work, process piping, structural steel, electrical and instrumentation, large tanks and pressure vessels, and specialty insulation and coatings contractors over a multiyear build.
What happens next
With groundbreaking complete, the joint venture's near-term work is civil construction and site preparation at the Blue Point Complex, ahead of major equipment installation in the years ahead. CF Industries has not disclosed a detailed public construction schedule beyond the 2029 production target.
| Item | Figure |
|---|---|
| Ammonia facility cost (2025 announcement) | Approximately $4 billion |
| Ammonia facility cost (current CF project page) | Approximately $3.7 billion |
| Shared infrastructure cost | Approximately $550 million |
| Annual capacity | About 1.4 million metric tons of low carbon ammonia |
| Ownership | CF Industries 40%, JERA 35%, Mitsui 25% |
| Construction jobs | About 3,900 over four years |
| Construction wages and benefits | About $800 million |
| Permanent jobs | About 103, averaging about $110,000 a year |
| Target production start | 2029 |
- Owner
- CF Industries, JERA Co., Mitsui & Co.
- Investment
- $4 billion (approximately $4 billion for the ammonia production facility per the companies' April 2025 final investment decision; CF Industries' current project page lists about $3.7 billion, plus a separate estimated $550 million in shared infrastructure)
- Location
- Modeste, Ascension Parish, Louisiana
- Type
- Ammonia plant (low carbon, ATR with CCS), new construction
- Stage
- Under construction
- Timeline
- CF Industries, JERA and Mitsui announced a final investment decision in April 2025. Louisiana and the U.S. Army Corps of Engineers issued construction permits in July 2026. The joint venture broke ground Aug. 26, 2026. Production is targeted to start in 2029.
- Contractor / EPC
- Technip Energies (engineering, procurement and module fabrication)
- Sources
- Louisiana Economic Development, CF Industries, CF Industries
Why it matters
The multiyear build of a roughly $4 billion ammonia complex means years of work for heavy civil, process piping, structural steel, electrical and tank-erection contractors in Ascension Parish, plus an estimated 3,900 construction jobs.
What this project buys
- Site work and civil construction
- Process piping
- Structural steel erection
- Electrical and instrumentation
- Tanks and pressure vessels
- Insulation and coatings
When to approach: Civil construction and site preparation underway now; major trade subcontracts expected to build through the multiyear construction toward 2029 production.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is the new CF Industries ammonia plant in Louisiana?
In Modeste, Ascension Parish, at the Blue Point Complex in the RiverPlex MegaPark, about nine miles north of CF Industries' Donaldsonville Complex.
How much does the Blue Point One ammonia plant cost?
CF Industries, JERA and Mitsui put the ammonia facility at approximately $4 billion when they took their final investment decision in April 2025; CF's current project page lists about $3.7 billion, plus roughly $550 million in shared infrastructure.
When will construction start on Blue Point One?
The joint venture broke ground Aug. 26, 2026, after Louisiana and the U.S. Army Corps of Engineers issued construction permits in July 2026. Production is targeted for 2029.
Who owns and is building the Blue Point One ammonia plant?
A joint venture of CF Industries (40%), JERA Co. (35%) and Mitsui & Co. (25%). Technip Energies holds the engineering, procurement and module fabrication contract, and Topsoe is supplying the process technology.
How many jobs will the Blue Point One project create?
CF Industries estimates about 3,900 construction jobs over four years and about 103 permanent full-time jobs once the plant is operating.
Sources
- ICYMI: CF Industries, JERA Co. and Mitsui Co., Ltd. Break Ground on Blue Point One, Louisiana Economic Development, Aug. 26, 2026
- Blue Point Joint Venture, CF Industries, April 8, 2025
- Blue Point Complex, CF Industries, Nov. 28, 2026