Lithium Americas raises Thacker Pass lithium plant cost to $3.83 billion in Humboldt County, Nevada.
Lithium Americas now needs about $995 million in extra funding for Phase 1 of its Thacker Pass lithium carbonate project, which is under construction in Humboldt County and backed by a federal loan.
Quick answer
Lithium Americas Corp. (Lithium Nevada LLC): $3.8 billion investment in Thacker Pass, Nev. Stage: Under construction. Timeline: DOE loan arrangement dated Oct. 28, 2024, since amended several times, most recently by Omnibus Waiver, Consent and Amendment No. 3 signed Nov. 10, 2026; revised capital cost estimate announced Nov. 11, 2026; mechanical completion targeted for late 2027; ramp-up to full commercial production targeted for 2028. Likely to buy: process piping, structural steel erection, electrical and instrumentation, tanks and vessels.

By Capex Wire NewsroomPublished 3 min read
Lithium Americas Corp. has raised its cost estimate for Phase 1 of the Thacker Pass lithium project in Humboldt County, Nevada, to $3.83 billion, up from a prior $2.93 billion, as construction continues on what the company calls the largest planned source of domestic battery-quality lithium carbonate. The company disclosed the new estimate in a Nov. 11, 2026 press release and in a Form 8-K filed with the Securities and Exchange Commission.
What is being built
Thacker Pass is a lithium clay mine and processing complex that will produce battery-quality lithium carbonate. Phase 1 is designed for a nominal output of 40,000 tonnes per year, according to the company's Nov. 11 release. The project is a joint venture between Lithium Americas and General Motors Holdings LLC, operating through Lithium Nevada LLC. Cumulative Phase 1 construction spending reached about $2.26 billion as of Sept. 30, 2026.
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 24 projects like this$9.90/month · cancel anytime in one click
Jobs and construction progress
About 1,900 personnel, including more than 1,600 craft workers, were on site as of Sept. 30, 2026, a figure the company expects to rise to about 2,200 by the end of the year. Chief Executive Jonathan Evans said the project is "already putting nearly 2,000 skilled craftspeople to work in Humboldt County." The company reported 4.7 million work hours without a serious injury or lost-time incident. Engineering is complete, procurement is more than 90 percent complete, and all major structural steel was delivered by the end of August 2026. Rail stabilization and sub-ballast work at the project's transload terminal near Winnemucca was 95 percent complete in the third quarter. The company has poured its first concrete and targets completing concrete foundations before the end of 2026.
Why the cost went up
Lithium Americas attributed the $895 million in incremental capital costs to six factors: higher labor hours to install piping, structural steel and equipment, estimated at $245 million; craft labor wage and compensation inflation, $150 million; engineering, procurement and construction management staffing levels, $100 million; wage inflation for that same contractor and engineering staff, $150 million; added contingency on uncommitted costs, $150 million; and tariffs and logistics, about $100 million. The company said its tariff exposure has since narrowed to about $60 million because most equipment and materials have already been received.
Who is paying for it
The company said the new estimate creates a $995 million incremental funding requirement, which it plans to meet with about $650 million in additional contributions to the joint venture and $315 million drawn from reserve accounts tied to its U.S. Department of Energy loan. On Nov. 10, 2026, Lithium Americas, GM and the DOE signed a third omnibus waiver, consent and amendment to the project's 2024 loan agreement, which the SEC filing says lets the parties adopt an amended construction budget, financial model, mine plan and project schedule, and reduces a sustaining capital reserve requirement by about $30 million. The DOE has provided $1.448 billion in cumulative loan advances, including a $239 million payment in August 2026. GM also signed a separate letter agreement the same day addressing its rights in the joint venture.
What happens next
Lithium Americas is targeting mechanical completion of Phase 1 in late 2027, with ramp-up to full commercial production in 2028. Evans said the company, "including Bechtel," is focused on bringing Thacker Pass to full commercial production on that schedule. The company raised its 2026 capital spending guidance to a range of $1.7 billion to $2.0 billion, up from $1.3 billion to $1.6 billion, and said spending is expected to peak this year before tapering through 2027 and into 2028.
| Item | Figure | Source |
|---|---|---|
| Revised Phase 1 cost estimate | $3.83 billion | Lithium Americas Corp. |
| Prior cost estimate | $2.93 billion | Lithium Americas Corp. |
| Incremental funding need | $995 million | Lithium Americas Corp. |
| Personnel on site (Sept. 30, 2026) | About 1,900 | Lithium Americas Corp. |
| Cumulative DOE loan advances | $1.448 billion | Lithium Americas Corp. (SEC filing) |
| Targeted mechanical completion | Late 2027 | Lithium Americas Corp. |
- Owner
- Lithium Americas Corp. (Lithium Nevada LLC)
- Investment
- $3.8 billion (revised Phase 1 capital cost estimate including contingency, as announced by Lithium Americas Nov. 11, 2026; up from a prior $2.93 billion estimate)
- Location
- Thacker Pass, Humboldt County, Nevada
- Type
- Critical minerals plant (lithium carbonate), new construction
- Stage
- Under construction
- Timeline
- DOE loan arrangement dated Oct. 28, 2024, since amended several times, most recently by Omnibus Waiver, Consent and Amendment No. 3 signed Nov. 10, 2026; revised capital cost estimate announced Nov. 11, 2026; mechanical completion targeted for late 2027; ramp-up to full commercial production targeted for 2028.
- Contractor / EPC
- Bechtel (EPCM contractor, referenced by the company)
- Sources
- U.S. Securities and Exchange Commission, Lithium Americas Corp. via SEC, Indian Chemical News, The National
Why it matters
A $3.83 billion lithium plant under construction in rural Humboldt County means years of piping, structural steel, electrical and tank work for contractors, plus nearly 2,000 craft jobs already on site.
What this project buys
- Process piping
- Structural steel erection
- Electrical and instrumentation
- Tanks and vessels
- Site work and foundations
- Rail and transload infrastructure
When to approach: Peak construction activity is expected by year end 2026, with mechanical completion targeted for late 2027 and ramp-up to commercial production in 2028; remaining procurement and subcontract packages are being awarded now.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is the Thacker Pass lithium project in Nevada?
It is in Humboldt County, Nevada, at Thacker Pass, with a transload terminal near Winnemucca.
How many jobs does the Thacker Pass project have now?
About 1,900 personnel, including more than 1,600 craft workers, were on site as of Sept. 30, 2026, a number the company expects to reach about 2,200 by the end of the year.
When will the Thacker Pass plant start producing lithium?
Lithium Americas is targeting mechanical completion of Phase 1 in late 2027, with ramp-up to full commercial production in 2028.
Who is building and financing the Thacker Pass project?
Lithium Americas Corp. is developing the project through Lithium Nevada LLC, in a joint venture with General Motors, with financing that includes a U.S. Department of Energy loan and Bechtel named as the EPCM contractor.
Why did the cost of the Thacker Pass project increase?
Lithium Americas cited higher labor installation hours, craft and contractor wage inflation, engineering and construction management staffing costs, added contingency, and tariffs and logistics, raising the Phase 1 estimate from $2.93 billion to $3.83 billion.
Sources
- Lithium Americas Corp. Form 8-K, U.S. Securities and Exchange Commission, Nov. 16, 2026
- Lithium Americas Provides Thacker Pass Project Update (Exhibit 99.1), Lithium Americas Corp. via SEC, Nov. 11, 2026
- Thacker Pass lithium project cost surges $900 million to $3.83 billion as construction advances, Indian Chemical News, Nov. 16, 2026
- Lithium Americas raises Thacker Pass cost estimate by 31% to $3.83bn, The National, Nov. 11, 2026