Hyundai-POSCO Louisiana Steel wins its final air permit for a $5.8 billion mill in Ascension Parish.
Louisiana regulators approved the permit Oct. 29, more than a month after a ceremonial groundbreaking, clearing the way for construction toward a 2029 production start.
Quick answer
Hyundai-POSCO Louisiana Steel: $5.8 billion investment in Donaldsonville, La. Stage: Under construction. Timeline: Hyundai-POSCO Louisiana Steel held a ceremonial groundbreaking on Sept. 4, 2026, before it had its air permit. The Louisiana Department of Environmental Quality approved the final air permit on Oct. 29, 2026. Construction is scheduled to continue through the end of 2028, with commercial steel production targeted for the first quarter of 2029. Likely to buy: site work and foundations, structural steel erection, electrical and substation, mechanical and process piping.

By Capex Wire NewsroomPublished 3 min read
Hyundai-POSCO Louisiana Steel has its final air permit for a $5.8 billion steel mill in Ascension Parish, Louisiana, clearing a regulatory hurdle more than a month after the company held a ceremonial groundbreaking without one. The Louisiana Department of Environmental Quality approved the permit on Oct. 29, 2026, for the electric arc furnace mill planned near Donaldsonville, according to a report from ScrapMonster.
Gov. Jeff Landry's office announced the project in March 2025. "Louisiana's manufacturing sector is roaring back, thanks to our historic tax reforms," Landry said at the time, according to Louisiana Economic Development, which organized the deal. Hyundai Steel Company President and CEO Gang Hyun Seo said the plant would make products for the company's own brands and beyond. "We plan to supply automotive steel plates not only for Hyundai Motor and Kia's strategic models," Seo said.
What is being built
The mill will sit on about 1,700 acres within the 17,000 acre RiverPlex MegaPark, on the west bank of the Mississippi River in Ascension Parish, Louisiana Economic Development said. It is designed as an electric arc furnace, or EAF, based integrated steel mill, which the state says produces about 70 percent lower emissions than a traditional blast furnace mill. The plant is expected to import about 3.6 million tons of iron ore annually as feedstock and to produce 2.7 million metric tons of steel a year, mostly automotive steel plates and coils for Hyundai Motor, Kia and other U.S. automakers, according to the state's announcement and ScrapMonster's coverage of the permit approval.
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 24 projects like this$9.90/month · cancel anytime in one click
Jobs and timeline
Hyundai-POSCO Louisiana Steel plans more than 1,300 direct jobs at an average salary of about $95,000, with Louisiana Economic Development estimating about 4,100 additional indirect jobs, for roughly 5,400 total positions tied to the project in the Capital Region. The company held its ceremonial groundbreaking on Sept. 4, 2026, in Donaldsonville, though it still lacked the air permit needed before construction could formally begin, local station WAFB reported. With the permit now approved, construction is scheduled to run through the end of 2028, and commercial production is targeted for the first quarter of 2029, ScrapMonster reported. The company has opened recruitment for nearly 40 positions so far, aiming for as many as 300 workers hired by the end of 2027, and a workforce training center for the project at River Parishes Community College, on Highway 945 in Donaldsonville, is under construction and expected to be finished in the first quarter of 2028.
Who is building it
Hyundai-POSCO Louisiana Steel is a joint venture of Hyundai Steel Company and POSCO, part of Hyundai Motor Group. No outside general contractor has been named publicly. State incentives include a $100 million performance based grant for infrastructure from Louisiana Economic Development, and the Louisiana State Bond Commission approved up to $1.3 billion in tax exempt financing for the project in September 2026, according to ScrapMonster. Entergy Louisiana has said it is planning transmission projects on the Westbank to serve the mill, and the Port of South Louisiana is building a deep water dock with the company. At the September groundbreaking, U.S. Rep. Troy Carter told the crowd, "So get ready, good jobs are coming, career pathways are coming."
What the project will buy
| Metric | Figure |
|---|---|
| Total investment | $5.8 billion |
| Site | About 1,700 acres in the 17,000 acre RiverPlex MegaPark |
| Annual capacity | 2.7 million metric tons of steel |
| Direct jobs | More than 1,300, average salary about $95,000 |
| Construction window | Through the end of 2028, production starting Q1 2029 |
The buildout calls for site work and foundations, structural steel erection, electrical and substation work, mechanical and process piping, refractory and furnace work, and overhead cranes, the trades Capex Wire tracks for projects of this type.
What happens next
The project has drawn sustained opposition from environmental groups and a local steelworkers' union organizer over air quality and the pace of the permitting process. A public hearing on the draft permit was held Sept. 1, 2026, and the Louisiana Department of Environmental Quality extended the public comment period before issuing the final permit in October. United Steelworkers organizer Jacob Horwitz criticized the state's pace. "The message that sends is we're going to move forward, whether you like it or not," Horwitz said, according to Manufacturing Dive. A Louisiana judge has already dismissed one legal challenge to the project from Rural Roots Louisiana and the Louisiana Bucket Brigade, Manufacturing Dive reported, though other legal challenges to the permit remain possible as construction continues toward the 2029 production target.
- Owner
- Hyundai-POSCO Louisiana Steel
- Investment
- $5.8 billion (Investment figure as announced by Hyundai Steel Company and Louisiana Economic Development; Gov. Jeff Landry's office has also called it nearly $6 billion.)
- Location
- Donaldsonville, Ascension Parish, Louisiana
- Type
- Metals and minerals plant, new investment
- Stage
- Under construction
- Timeline
- Hyundai-POSCO Louisiana Steel held a ceremonial groundbreaking on Sept. 4, 2026, before it had its air permit. The Louisiana Department of Environmental Quality approved the final air permit on Oct. 29, 2026. Construction is scheduled to continue through the end of 2028, with commercial steel production targeted for the first quarter of 2029.
- Contractor / EPC
- Not announced
- Sources
- Louisiana Economic Development, ScrapMonster, WAFB, Manufacturing Dive
Why it matters
The 2.7 million metric ton mill will need site work, structural steel, electrical, process piping, refractory and crane trades through 2028, and the company has already opened recruitment for its first workers.
What this project buys
- Site work and foundations
- Structural steel erection
- Electrical and substation
- Mechanical and process piping
- Refractory and furnace work
- Overhead cranes
When to approach: The air permit is now final and site work is underway, but no general contractor has been named and no bid timeline has been disclosed. A workforce training center at River Parishes Community College is under construction, targeted for completion in the first quarter of 2028.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is the Hyundai-POSCO steel mill being built?
On a 1,700 acre site near Donaldsonville in Ascension Parish, Louisiana, inside the 17,000 acre RiverPlex MegaPark on the west bank of the Mississippi River, according to Louisiana Economic Development.
How many jobs will the plant create?
More than 1,300 direct jobs with an average salary of about $95,000, plus an estimated 4,100 indirect jobs for about 5,400 total in the region, Louisiana Economic Development said.
When will construction finish and production start?
Construction is scheduled to continue through the end of 2028, with commercial steel production targeted for the first quarter of 2029, Hyundai-POSCO Louisiana Steel said after its air permit was approved.
Who is building the Hyundai-POSCO steel mill?
Hyundai Steel Company and POSCO, through the joint venture Hyundai-POSCO Louisiana Steel and as part of Hyundai Motor Group; no outside general contractor has been named publicly.
How much is Hyundai-POSCO investing in the Louisiana mill?
$5.8 billion for an electric arc furnace steel mill, a figure Gov. Jeff Landry's office has also described as nearly $6 billion, according to Louisiana Economic Development.
Sources
- 'Louisiana Wins Again,' Governor Jeff Landry & LED Secure $5.8 Billion Hyundai Steel Mill, Louisiana Economic Development, March 24, 2025
- Hyundai-POSCO Louisiana Steel Receives Air Permit Amid Environmental Concerns, ScrapMonster, Oct. 29, 2026
- $5.8B Hyundai-POSCO steel plant launches in Ascension Parish amid some opposition, WAFB, Sept. 4, 2026
- Hyundai Steel project moves ahead despite local pushback, Manufacturing Dive, Sept. 2, 2026