Crucible Metals, a Korea Zinc affiliate, plans a $6.6 billion refinery in Clarksville, Tennessee.
The project has a 20 year county tax abatement and $210 million in federal CHIPS funding, with construction targeted to start in early 2027.
Quick answer
Crucible Metals: $6.6 billion investment in Clarksville, Tenn. Stage: Financed. Timeline: Tennessee officials and Korea Zinc announced the investment Dec. 15, 2025. Crucible Metals held a launch event for the project, called Project Crucible, on April 1, 2026, after acquiring the former Nyrstar zinc plant property. The Clarksville-Montgomery County Industrial Development Board unanimously approved a 20 year property tax abatement on Aug. 26, 2026. Site preparation and engineering were underway as of August 2026, with construction planned to begin in early 2027 and take about 33 months. Initial zinc processing is planned for 2029, with full production across all metals targeted for early 2030. Likely to buy: site work and demolition, process piping and vessel installation, electrical and substation work, mechanical and hvac systems.

By Capex Wire NewsroomPublished 3 min read
Crucible Metals, a U.S. affiliate of South Korea's Korea Zinc, is building a critical minerals refinery valued at more than $6.6 billion on the site of a former zinc plant in Clarksville, Montgomery County, Tennessee, state and company officials announced Dec. 15, 2025.
What is being built
The project, which Korea Zinc calls Project Crucible, will rise on a 1,200 acre property connected to the former Nyrstar zinc smelter, Clarksville Now reported. The center 600 acres of that property are zoned industrial, and no rezoning is required for the new construction. The existing plant, renamed Crucible Zinc, will keep operating during construction before eventually being replaced. Korea Zinc has said the new refinery is designed to replicate its Onsan refinery in South Korea and will produce 13 metals, including zinc, lead, copper, silver and gold, along with several materials considered critical to semiconductors, aerospace and national security. Reported annual output includes about 300,000 tons of zinc, 200,000 tons of lead and more than 35,000 tons of copper.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.6 trillion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
Jobs and incentives
Crucible Metals is expected to retain all 300 existing employees at the site and add 420 new jobs, Josh Ward, executive director of the Clarksville-Montgomery County Industrial Development Board, told Clarksville Now. New positions are split into three pay tiers: 271 office and production jobs at a minimum $83,000 a year, 112 installation and maintenance jobs at $100,000, and 37 management jobs at $196,000. The Industrial Development Board unanimously approved a 20 year, 57% Montgomery County property tax abatement on Aug. 26, 2026, tied to the company maintaining those wage levels and completing a $6 billion appraisable investment. The U.S. Department of Commerce separately awarded Crucible Metals $210 million in direct CHIPS Act funding to support its smelter and critical minerals processing facility, according to the National Institute of Standards and Technology.
"Korea Zinc's decision to invest in Tennessee, which marks the single largest investment in state history, reinforces the importance of our strategic global recruitment efforts," Tennessee Deputy Gov. and Economic and Community Development Commissioner Stuart McWhorter said when the project was announced. Montgomery County Mayor Wes Golden called it a major economic milestone with important national security implications for the region.
Timeline and what happens next
Site preparation and engineering were underway as of August 2026, with construction planned to begin in early 2027 and take about 33 months, Clarksville Now reported. Initial zinc processing is planned to start in 2029, before the refinery expands to lead and copper production and reaches full output across all 13 metals in early 2030. A state hearing on a draft permit covering the project's impact on nearby waterways was scheduled for Nov. 16, 2026, with public comments accepted through Nov. 26, 2026, according to the Tennessee Department of Environment and Conservation. No cancellation, legal challenge or other change to the project has been reported.
| Item | Figure |
|---|---|
| Total investment | More than $6.6 billion |
| Site | 1,200 acres (former Nyrstar zinc plant) |
| Retained jobs | 300 |
| New jobs | 420 |
| Minimum new job salary | $83,000 a year |
| Federal CHIPS funding | $210 million |
| Construction start | Early 2027 |
| Full production target | Early 2030 |
Once the refinery is complete, the tax abatement is expected to generate more than $5 million a year for Montgomery County starting in 2029, climbing toward an estimated $31 million a year once it reaches full maturity after 20 years, Clarksville Now reported. During construction, Crucible has agreed to keep paying the roughly $252,000 a year in property taxes the former Nyrstar plant paid, so the county does not lose revenue while the new facility is built.
- Owner
- Crucible Metals
- Investment
- $6.6 billion (more than $6.6 billion, per Tennessee's Department of Economic and Community Development and Clarksville Now; one Clarksville Now article described Crucible Zinc as part of a larger $7.4 billion Korea Zinc investment across Tennessee, which includes a separate reopened mine in Smith County.)
- Location
- Clarksville, Montgomery County, Tennessee
- Type
- Critical minerals and metals refinery, new facility
- Stage
- Financed
- Timeline
- Tennessee officials and Korea Zinc announced the investment Dec. 15, 2025. Crucible Metals held a launch event for the project, called Project Crucible, on April 1, 2026, after acquiring the former Nyrstar zinc plant property. The Clarksville-Montgomery County Industrial Development Board unanimously approved a 20 year property tax abatement on Aug. 26, 2026. Site preparation and engineering were underway as of August 2026, with construction planned to begin in early 2027 and take about 33 months. Initial zinc processing is planned for 2029, with full production across all metals targeted for early 2030.
- Contractor / EPC
- Not announced
- Sources
- Tennessee Department of Economic and Community Development, Clarksville Now, Clarksville Now, Clarksville Now, National Institute of Standards and Technology, Tennessee Department of Environment and Conservation
Why it matters
A $6.6 billion refinery rebuilding a 1,200 acre former zinc plant site means site work, process piping, electrical and structural trades starting in 2027, plus 420 new jobs paying at least $83,000 a year.
What this project buys
- Site work and demolition
- Process piping and vessel installation
- Electrical and substation work
- Mechanical and HVAC systems
- Structural steel erection
- Material handling and conveyor systems
When to approach: Site prep and engineering are underway now, with construction bid packages likely opening in early 2027 for a roughly 33 month build. A state permit covering the project's impact on nearby waterways was still in public comment as of November 2026.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Crucible Metals building its Tennessee refinery?
On a 1,200 acre site in Clarksville, Montgomery County, Tennessee, connected to the former Nyrstar zinc smelter property.
How much is Crucible Metals investing?
Tennessee officials and Clarksville Now have put the project at more than $6.6 billion, which the state calls the largest single capital investment in Tennessee history.
How many jobs will it create?
Crucible Metals plans to retain all 300 existing zinc plant employees and add 420 new jobs, with new positions paying at least $83,000 a year, according to Clarksville Now.
When will construction start?
Site preparation and engineering were underway as of August 2026, with construction planned to begin in early 2027 and take about 33 months, Clarksville Now reported.
Who is building the Crucible Metals refinery?
No general contractor or engineering firm has been named. The project is run by Crucible Metals LLC, a U.S. affiliate Korea Zinc created to manage it.
Sources
- Korea Zinc Selects Tennessee for First U.S. Operations, Announces $6.6 Billion Investment, Tennessee Department of Economic and Community Development, Dec. 15, 2025
- Korea Zinc launches $6.6B 'Project Crucible' refinery project in Montgomery County, Clarksville Now, April 1, 2026
- Crucible Metals incentive approved, should bring $5 million in tax revenue by 2029, Clarksville Now, Aug. 26, 2026
- 6 things to know about plan for Crucible Metals: Jobs, bridge, not just zinc, Clarksville Now, Aug. 31, 2026
- CHIPS for America: Tennessee, National Institute of Standards and Technology, Nov. 20, 2026
- Public Hearing on Draft Aquatic Resource Alteration Permit for Crucible Metals, LLC in Montgomery County, Tennessee, Tennessee Department of Environment and Conservation, Nov. 16, 2026