Healthcare & Life Sciences · TX
Eli Lilly breaks ground on a $6.5 billion drug ingredient plant in Houston, Texas.
The active pharmaceutical ingredient campus at Generation Park will make ingredients for Lilly's oral GLP-1 drug orforglipron, with the full build not due until 2030.
Quick answer
Eli Lilly and Company: $6.5 billion investment in Houston, Texas. Stage: Under construction. Timeline: Lilly announced the project Sept. 23, 2025 at a news conference with Gov. Greg Abbott. Lilly broke ground at the 236 acre Generation Park site on Sept. 21, 2026. The Texas Department of Licensing and Regulation logged five shell building permits for the project on July 16, 2026, together worth about $378 million, with that phase of work due by the end of 2027. Lilly says the overall campus will not be complete until 2030. Likely to buy: site work and foundations, structural steel erection, mechanical and hvac, electrical and process utilities.

By Capex Wire NewsroomPublished 2 min read
Eli Lilly and Company broke ground Sept. 21, 2026 on a $6.5 billion plant at Generation Park in Houston, Texas, about a year after the drugmaker announced the project at a news conference with Gov. Greg Abbott.
What is being built
The roughly 1 million square foot facility sits on about 236 acres at Generation Park, a 4,300 acre business park on Houston's northeast side in Harris County, developed by McCord Development. Lilly says the plant will make active pharmaceutical ingredients, the chemical building blocks of its medicines, with a focus on small molecule drugs for cardiometabolic health, oncology, immunology and neuroscience. The company has said the site will produce ingredients for orforglipron, its investigational once-daily oral GLP-1 medicine for Type 2 diabetes and obesity. "Lilly's $6.5 billion capital investment expands our healthcare dominance in the Lone Star State," Abbott said at the September 2026 groundbreaking. Diane Tennenhouse, Lilly's Houston site head, said at the project's 2025 announcement, "This is built for the future."
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 23 projects like this$9.90/month · cancel anytime in one click
Jobs and timeline
Lilly says the finished plant will employ more than 600 people in engineering, science and laboratory roles, and expects about 4,000 construction jobs during the build. The Texas Department of Licensing and Regulation logged five separate shell building permits for the project on July 16, 2026, together valued at about $378 million, a fraction of the total $6.5 billion Lilly has pledged. That phase of construction is projected to finish by the end of 2027, while Lilly says the overall campus will not be complete until 2030. In a July 2026 statement, a Lilly spokesperson said, "Lilly Houston remains on track and is progressing as planned against its previously announced timeline."
| Item | Figure |
|---|---|
| Total announced investment | $6.5 billion |
| Site size | about 236 acres, roughly 1 million sq ft of building |
| Permanent jobs | more than 600 |
| Construction jobs | about 4,000 |
| July 2026 shell building permits (5) | about $378 million combined |
| Texas Enterprise Fund grant | $5.5 million |
Who is building it and what it will buy
Lilly has not publicly named a general contractor for the campus. The five shell building permits filed with the state in July 2026 ranged from about $9 million to $193 million each, covering structures with stairways and elevator shafts, the first visible phase of a project that will need mechanical, electrical, process piping, plumbing and fire protection trades for years as it builds out. The project was approved for the Texas Jobs, Energy, Technology and Innovation program and received a $5.5 million Texas Enterprise Fund grant. Lilly is also funding a workforce partnership tied to the nearby San Jacinto College Center for Biotechnology at Generation Park, though the company has not disclosed its dollar value.
What happens next
With the shell buildings due by the end of 2027 and the full campus targeted for 2030, Lilly is expected to file additional permits with Harris County and the state as construction moves from shell structures into process equipment and fit out. McCord Development's Generation Park has drawn other large life sciences projects nearby, including Bristol Myers Squibb's announced campus, and local officials have cited Houston's growing manufacturing base as a draw for further investment. Capex Wire found no report that Lilly has delayed or scaled back the project since the 2026 groundbreaking.
- Owner
- Eli Lilly and Company
- Investment
- $6.5 billion (Lilly's own announced total investment for the campus, Sept. 23, 2025)
- Location
- Houston, Harris County, Texas
- Type
- Healthcare and life sciences, new construction
- Stage
- Under construction
- Timeline
- Lilly announced the project Sept. 23, 2025 at a news conference with Gov. Greg Abbott. Lilly broke ground at the 236 acre Generation Park site on Sept. 21, 2026. The Texas Department of Licensing and Regulation logged five shell building permits for the project on July 16, 2026, together worth about $378 million, with that phase of work due by the end of 2027. Lilly says the overall campus will not be complete until 2030.
- Contractor / EPC
- Not announced
- Sources
- Office of the Texas Governor, Office of the Texas Governor, Community Impact (ABC13 Houston), Wesley Gardner, Community Impact, Wesley Gardner and Julianna Washburn
Why it matters
A $6.5 billion campus phased out to 2030 means years of work for mechanical, electrical, process piping and fire protection trades, but only a fraction of that spending has been filed with the state so far, so suppliers should track new Harris County permits rather than the headline figure alone.
What this project buys
- Site work and foundations
- Structural steel erection
- Mechanical and HVAC
- Electrical and process utilities
- Plumbing and medical gas piping
- Fire protection
When to approach: Lilly expects the campus to open in phases through 2030. The five shell building permits filed in July 2026 cover work due by the end of 2027; no general contractor has been named publicly.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Eli Lilly's new Houston plant?
At Generation Park, a 4,300-acre master-planned business park on Houston's northeast side in Harris County. Lilly's site covers about 236 acres.
How many jobs will the Lilly Houston plant create?
Lilly says the finished campus will employ more than 600 people in engineering, science and lab roles, plus about 4,000 construction jobs during the build.
When did construction start on Eli Lilly's Houston facility?
Lilly broke ground on Sept. 21, 2026, about a year after announcing the project. The company says the full campus will not be complete until 2030.
Who is building the Eli Lilly Houston plant?
Lilly has not publicly named a general contractor. Permits filed with the Texas Department of Licensing and Regulation in July 2026 cover five shell buildings tied to the project.
What will the Eli Lilly Houston plant make?
Active pharmaceutical ingredients for small molecule medicines, including orforglipron, Lilly's investigational oral GLP-1 drug for Type 2 diabetes and obesity.
Sources
- Governor Abbott Announces New Eli Lilly Manufacturing Investment In Harris County, Office of the Texas Governor, Sept. 23, 2025
- Governor Abbott Delivers Remarks At Lilly Groundbreaking In Houston, Office of the Texas Governor, Sept. 21, 2026
- Construction begins on Eli Lilly's $6.5B manufacturing campus in Generation Park, Community Impact (ABC13 Houston), Wesley Gardner, July 27, 2026
- Biotech boom: $6.5B manufacturing facility at Generation Park to expand life sciences in Houston, Community Impact, Wesley Gardner and Julianna Washburn, Oct. 28, 2025
See the project record on the Project Map →
28 other projects in Harris County, Texas have not broken ground →