Data Centers · NC

Engineered Land Solutions' $7 billion Project Delta data center faces new suit in North Carolina.

Environmental and community groups asked a judge to overturn Stokes County's September rezoning for the hyperscale campus, the second suit over the project this year.

Quick answer

Engineered Land Solutions: $7 billion investment in Walnut Cove, N.C. Stage: Announced. Timeline: Stokes County commissioners first approved the Project Delta rezoning 3-2 in January 2026. Residents and advocacy groups sued in March 2026, and the board voided that approval and restarted the process. Commissioners approved the rezoning again 3-2 on Sept. 14, 2026. A new lawsuit asking a judge to overturn that approval was reported Nov. 13, 2026. No construction start date has been announced. Likely to buy: site work and grading, heavy electrical and substation work, mechanical and cooling systems, fiber and data cabling.

Aerial view of farmland along a river under a clear blue sky
Illustrative photo. Photo: Marc Coenen / Pexels

By Capex Wire NewsroomPublished 4 min read

Environmental and community groups have asked a judge to overturn Stokes County, North Carolina's approval of land for a data center campus known as Project Delta, the second lawsuit this year over the proposed hyperscale project near Walnut Cove.

What is being built

The developer, Engineered Land Solutions (ELS), wants to build a data center campus on about 1,845 acres of forest and farmland along the Dan River in Stokes County, reported elsewhere as roughly 1,800 acres. Stokes County commissioners voted 3-2 on Sept. 14, 2026 to rezone the land from residential-agricultural to heavy industrial use, clearing the way for the project. ELS Chief Executive Drew Nations has committed to forgo development on 850 acres of the site to avoid known archaeological areas, add landscaped buffers and use a closed-loop cooling system, according to E&E News. No data center operator or tenant has been publicly identified for the campus.

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 5 projects like this

$9.90/month · cancel anytime in one click

A second lawsuit in 2026

WFAE and WFDD reported Nov. 13, 2026 that environmental advocates filed a new lawsuit against the Stokes County Board of Commissioners, asking a judge to overturn the September rezoning. Anne Harvey David, chief counsel for environmental justice at the Southern Coalition for Social Justice, said the board "relied on inaccurate and incomplete summaries" and "used AI-generated reports in an attempt to sort of support" a predetermined decision, according to WFAE. Stokes County officials did not respond to WFAE's request for comment by its deadline, and Engineered Land Solutions did not comment publicly in that report.

The September vote was commissioners' second attempt to approve the rezoning. They first approved it in January 2026 by the same 3-2 margin, with commissioners Rick Morris, Sonya Cox and Keith Wood voting yes and Chair Wayne Barneycastle and Brad Chandler voting no, according to E&E News. The Southern Coalition for Social Justice and the Southern Environmental Law Center sued in Stokes County Superior Court on March 12, 2026 on behalf of residents and groups including the National Hairston Clan, CleanAIRE NC, the Dan River Basin Association and 7 Directions of Service, arguing the county skipped procedural safeguards required under North Carolina law. The board then voided the January approval and restarted the process, and commissioners approved the rezoning again 3-2 on Sept. 14, 2026.

Jobs and tax revenue in dispute

Engineered Land Solutions says the project would create 250 to 500 jobs, and ELS spokesperson Pat Ryan has said it would generate $20 million a year in tax revenue at 50% completion and $40 million a year at full buildout, according to E&E News. Economist Michael Hicks of Shenandoah University, in a report commissioned by the Southern Environmental Law Center, used a lower base case of $1 billion in investment and estimated $20 million to $40 million in tax revenue over 10 years, not per year. "That is just I think not consistent with the observation of data center deployments around the country," Hicks said at a press conference reported by WUNC. ELS Chief Executive Drew Nations responded in a statement that the company stands by its $40 million a year projection at full buildout and that Hicks' report does not adequately explain why the project would fall short of that scale.

ItemFigure
Developer's full buildout estimatemore than $7 billion
Economist's base case for tax analysis$1 billion
Rezoned landabout 1,845 acres
Land set aside for archaeological protection850 acres
Jobs, per developer250 to 500
Developer's tax revenue claim at full buildout$40 million a year
Economist's tax revenue estimate$20 million to $40 million over 10 years

Who is building it and what the project would buy

Engineered Land Solutions has not publicly named a general contractor, architect or construction timeline for the campus, and the company has said it has not signed a customer and has no backup site, per E&E News. A project of the scale the developer describes would eventually need site work, heavy electrical and substation construction, mechanical and cooling systems, fiber connectivity and security infrastructure, but those contracts depend on the rezoning surviving its second legal challenge and on a tenant signing on to the campus.

What happens next

The new lawsuit asks a Stokes County judge to overturn the September 2026 rezoning vote, following the same path that led the board to void its first approval earlier in the year after a legal challenge. Opponents, including the Southern Coalition for Social Justice, the Southern Environmental Law Center and residents citing archaeological sites, water use and property values along the Dan River, have said they will keep fighting the project in court. Capex Wire found no report that Engineered Land Solutions has withdrawn or paused the project since the September vote.

Project fileNC
Owner
Engineered Land Solutions
Investment
$7 billion (developer's own estimate for full buildout, per Drew Nations/ELS cited by WUNC Sept. 4, 2026; an economist's county tax analysis used a lower $1 billion base case)
Location
Walnut Cove, Stokes County, North Carolina
Type
Data center campus, rezoning approved
Stage
Announced
Timeline
Stokes County commissioners first approved the Project Delta rezoning 3-2 in January 2026. Residents and advocacy groups sued in March 2026, and the board voided that approval and restarted the process. Commissioners approved the rezoning again 3-2 on Sept. 14, 2026. A new lawsuit asking a judge to overturn that approval was reported Nov. 13, 2026. No construction start date has been announced.
Contractor / EPC
Not announced
Sources
WFAE (WFDD), WUNC News (WFDD), WFAE (WFDD), E&E News by POLITICO (Climatewire), Arianna Skibell, Southern Environmental Law Center

Why it matters

A rezoning fight over a data center the developer values at up to $7 billion means trades should watch Stokes County court filings, not just the county's land use map, before committing bid resources to a project with no named tenant or contractor yet.

What this project buys

  • Site work and grading
  • Heavy electrical and substation work
  • Mechanical and cooling systems
  • Fiber and data cabling
  • Concrete and foundations
  • Security and fencing

When to approach: Not disclosed. No contractor, building permits or construction timeline have been announced, and the rezoning faces an active legal challenge.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is the Project Delta data center planned?

Near Walnut Cove in Stokes County, North Carolina, on about 1,845 acres of forest and farmland (reported elsewhere as roughly 1,800 acres) that commissioners rezoned from residential-agricultural to heavy industrial use.

How big is the Project Delta investment?

The developer, Engineered Land Solutions, has said the campus could top $7 billion at full buildout. An economist hired by opponents to study county tax revenue used a lower $1 billion base case in his analysis. No tenant or data center operator has been publicly identified.

Who is suing over the Stokes County data center rezoning?

A lawsuit reported Nov. 13, 2026 by WFAE and WFDD asks a judge to overturn the county commissioners' September 2026 approval. An earlier suit, filed in March 2026 by the Southern Coalition for Social Justice and the Southern Environmental Law Center on behalf of residents and groups including the National Hairston Clan, CleanAIRE NC and the Dan River Basin Association, challenged the county's first approval.

How many jobs would the Walnut Cove data center create?

Engineered Land Solutions says the project would create 250 to 500 jobs. The company has not disclosed a separate construction employment figure.

Has construction started on Project Delta?

No. Stokes County commissioners have twice voted to rezone the land, in January and September 2026, but no building permits, site contractor or construction timeline have been announced, and the September approval is now being challenged in court.