Data Centers · OH

QTS plans $10 billion data center campus in Van Wert, Ohio.

Phase one excavation is underway on a 902 acre, seven building campus that QTS says could create more than 1,500 construction jobs.

Quick answer

QTS Data Centers: $10 billion investment in Van Wert, Ohio. Stage: Under construction. Timeline: Announced May 29, 2026. Ground broken on phase one, with excavation underway as of Construction Review Online's Oct. 28, 2026 report. Building construction expected to start spring 2027, with a 5 to 6 year buildout for all seven buildings. Likely to buy: site work and grading, concrete and foundations, structural steel, electrical and high voltage.

Aerial view of excavation and earthwork at a rural construction site, similar to groundwork underway at the Van Wert campus
Illustrative photo. Photo: Tom Fisk / Pexels

By Capex Wire NewsroomPublished 3 min read

QTS Data Centers and the City of Van Wert announced plans May 29, 2026, for a data center campus expected to bring up to $10 billion in capital investment to Van Wert, Ohio, according to the company's press release. Construction Review Online reported Oct. 28, 2026, that ground had recently been broken on the project's phase one, with excavation underway.

What is being built

QTS says it expects to build seven data center buildings across approximately 902 acres, a site Van Wert Mayor Kenneth J. Markward called "the mega site." Phase one comprises four buildings of approximately 650,000 square feet each, Construction Review Online reported. "We've been waiting nearly twenty years to get an end-user into the mega site," Markward said at the announcement. QTS co-CEOs Tag Greason and David Robey said "this is a long-term investment in Van Wert."

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 5 projects like this

$9.90/month · cancel anytime in one click

Jobs and timeline

QTS expects the project to generate more than 1,500 construction jobs during a 5 to 6 year building phase, working with local building trades unions, plus about 200 full-time QTS positions once operating. Construction Review Online's October report said actual building construction is expected to begin in spring 2027, after the phase one excavation work underway now. QTS says the campus could generate $200 million in projected tax revenue over the next 20 years.

Power, water and what the project will buy

QTS is working with American Electric Power on the campus's power supply and says it will fund all project energy infrastructure improvements itself, with no cost impact to existing AEP Ohio customers. The company separately committed $3 million over three years to the AEP Ohio Neighbor to Neighbor program. For cooling, QTS says the campus will use a closed loop system that does not consume water once operational; the City of Van Wert has approved the company's water usage and the two sides are still discussing the best source for the one-time initial fill. Ongoing municipal water use for bathrooms, kitchens, irrigation and humidification is expected to be modest. The buildout will draw site work and grading, concrete and foundation, structural steel, electrical and high voltage, and mechanical and cooling contractors over the multiyear build.

Community and environment

QTS said it is contributing an initial $100,000 to the Vantage Career Center, a local technical school, as part of a broader community betterment fund covering education, workforce development, public safety and community amenities. "We truly appreciate the commitment to education, workforce development, and the future success of our region," said Vantage Career Center Superintendent Rick Turner. QTS says environmental review found a small impact to one stream on the property, below the federal threshold, and that a U.S. Fish and Wildlife Service review found the project is not expected to adversely affect any federally protected threatened or endangered species. The company says it will apply for an air permit to cover backup diesel generators, which it says will be tested only briefly once a month.

What happens next

Phase one site work and excavation continue now. QTS says vertical construction on the first four buildings is expected to begin in spring 2027, with the full seven-building, 902 acre campus taking 5 to 6 years to build out. No general contractor has been named publicly in the sources reviewed for this story.

ItemFigure
Total planned investmentUp to $10 billion
Campus size902 acres, 7 buildings
Phase one4 buildings, about 650,000 sq ft each
Construction jobsMore than 1,500
Permanent QTS jobsAbout 200
Projected tax revenue$200 million over 20 years
Community investment (Vantage Career Center)$100,000
AEP Ohio community program$3 million over 3 years
Project fileOH
Owner
QTS Data Centers
Investment
$10 billion (up to $10 billion as the campus is built out, per QTS; not a figure committed up front)
Location
Van Wert, Van Wert County, Ohio
Type
Data center campus, new construction
Stage
Under construction
Timeline
Announced May 29, 2026. Ground broken on phase one, with excavation underway as of Construction Review Online's Oct. 28, 2026 report. Building construction expected to start spring 2027, with a 5 to 6 year buildout for all seven buildings.
Contractor / EPC
Not announced
Sources
QTS Data Centers, Construction Review Online, QTS Data Centers

Why it matters

The $10 billion campus's 5 to 6 year buildout means years of work for site grading, concrete, structural steel, electrical and mechanical contractors around Van Wert, plus more than 1,500 construction jobs at peak.

What this project buys

  • Site work and grading
  • Concrete and foundations
  • Structural steel
  • Electrical and high voltage
  • Mechanical and cooling systems
  • Fiber and network infrastructure

When to approach: Phase one excavation underway now; vertical building construction and major trade subcontracts expected to start spring 2027.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is the new QTS data center in Ohio?

In Van Wert, Van Wert County, on a roughly 902 acre campus local officials call the mega site.

How many jobs will the QTS Van Wert campus create?

QTS says more than 1,500 construction jobs during the 5 to 6 year buildout, plus about 200 full-time QTS positions once operating.

When will construction start on the QTS Van Wert data center?

QTS and the city announced the project May 29, 2026. Phase one excavation was underway by late October 2026, and QTS expects building construction to start in spring 2027.

Who is building the QTS Van Wert campus?

QTS Data Centers, led by co-CEOs Tag Greason and David Robey, working with the City of Van Wert and American Electric Power.

Will the QTS Van Wert data center use a lot of water?

QTS says it uses a closed loop cooling system that does not consume water once operational, with the city approving a one-time fill and ongoing municipal use limited to bathrooms, kitchens, irrigation and humidification.