Hyundai commits $2.7 billion to expand its Ellabell, Georgia, EV plant toward 500,000 vehicles a year.
Hyundai will add 200,000 units of annual capacity and 3,000 jobs at its Bryan County Metaplant, weeks after an immigration raid hit a battery factory on the same campus.
Quick answer
Hyundai Motor Group: $2.7 billion investment in Ellabell, Ga. Stage: Under construction. Timeline: Hyundai Motor Group Metaplant America (HMGMA), near Savannah in Bryan County, Georgia, began as a $5.5 billion project that grew to $7.6 billion and opened in March 2025. On September 4, 2025, federal immigration agents raided an on site battery factory joint venture then under construction, detaining nearly 500 people, more than 300 of them South Korean nationals, which The Associated Press reported delayed that battery plant's startup by two to three months, to the first half of 2026. On September 18, 2025, Hyundai Motor Company announced a Phase 2 HMGMA expansion as part of its CEO Investor Day, committing $2.7 billion to add 200,000 units of annual capacity by 2028 and create 3,000 direct and indirect jobs in Georgia. The Atlanta Journal-Constitution reported the expansion would grow Hyundai's Ellabell workforce from 3,129 employees toward a previously stated target of at least 8,500 by 2031. Likely to buy: structural steel erection, electrical and controls for new assembly lines, mechanical and hvac, robotics and automation installation.

By Capex Wire NewsroomPublished 3 min read
Hyundai Motor Company will invest $2.7 billion to expand its electric vehicle plant in Ellabell, Georgia, the company said September 18, 2025, adding production capacity and 3,000 jobs at a campus still recovering from a federal immigration raid two weeks earlier. The expansion, which Hyundai calls Phase 2 of its Metaplant America (HMGMA), came as part of the company's 2025 CEO Investor Day in New York and Seoul.
What is being built
HMGMA, in Bryan County west of Savannah, opened in March 2025 after growing from an initial $5.5 billion project to $7.6 billion. Hyundai's September 2025 announcement adds $2.7 billion on top of that, funding new assembly capacity to add 200,000 vehicles of annual production by 2028, which Hyundai said would bring the plant's total capacity to 500,000 units a year. Jose Munoz, president and chief executive of Hyundai Motor Company, said in the company's release that "we are delivering comprehensive electrified portfolios across all segments, localizing production in key markets, and leveraging breakthrough technologies from Software-Defined Vehicles to next-generation batteries." The plant currently builds two models, the Ioniq 5 crossover and Ioniq 9 three row SUV, according to the Atlanta Journal-Constitution. Hyundai said HMGMA is expected to eventually produce a mix of 10 hybrid and electric models, and The Associated Press reported the expansion will bring the plant's first midsize pickup truck, part of a Hyundai pickup program developed with General Motors.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.7 trillion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
Jobs and timeline
Hyundai's release said the Phase 2 expansion will create 3,000 direct and indirect jobs in Georgia alongside the $2.7 billion investment over three years. The Atlanta Journal-Constitution reported the plant employed 3,129 workers as of June 2025, on a path toward a previously announced target of at least 8,500 employees by 2031. Georgia and local governments have pledged incentives for the project; the Associated Press put the figure at $2.1 billion in tax breaks and incentives, while the Atlanta Journal-Constitution described a package worth about $2 billion, without specifying how much is tied to this expansion specifically.
Who is building it
Hyundai has not named a general contractor for the Phase 2 construction. The automaker operates HMGMA directly, as it does its other U.S. assembly plants, and has said it will keep working with the regional construction and supplier base that built the original campus. Trip Tollison, the Savannah area's top economic development official, said "They are investing and relying on us to deliver," describing Hyundai as a company that moves fast on this site.
What the project will buy
Adding assembly lines for new hybrid, EV and pickup models means more structural steel work, electrical and controls installation for new production lines, mechanical and HVAC systems, and the robotics and automation equipment that Hyundai uses throughout the plant, along with site work and fire protection systems as the campus grows. On September 4, 2025, two weeks before the expansion announcement, federal immigration agents raided an on site battery factory, a joint venture under construction at the time, detaining nearly 500 people, more than 300 of them South Korean nationals working on battery technology. The Associated Press reported the raid delayed that battery plant's opening by two to three months, pushing its startup into the first half of 2026, but described the raid as a separate issue from the assembly plant expansion rather than a cause of it. Hyundai said at the time that its broader Georgia investment plans remained on track.
| Item | Figure |
|---|---|
| Phase 2 investment | $2.7 billion |
| Added annual capacity | 200,000 vehicles |
| Total capacity target (2028) | 500,000 vehicles a year |
| New jobs | 3,000 direct and indirect |
| Workforce as of June 2025 | 3,129 |
| Workforce target by 2031 | At least 8,500 |
| Models planned at HMGMA | 10 hybrid and EV models, up from 2 |
What happens next
Hyundai has not published a detailed construction schedule for the Phase 2 expansion. The company says it is working toward the 2028 capacity target while the on site battery joint venture recovers from the September 2025 raid and brings its own factory into operation in the first half of 2026. Georgia officials, including Gov. Brian Kemp, have continued to publicly back the project, with Kemp saying the state looks forward to working with Hyundai on its "continued growth and success for years to come."
- Owner
- Hyundai Motor Group
- Investment
- $2.7 billion (Investment Hyundai Motor Company announced for a Phase 2 capacity expansion at its Metaplant America (HMGMA), per the company's September 18, 2025 CEO Investor Day release.)
- Location
- Ellabell, Bryan County, Georgia
- Type
- Electric vehicle plant (bevs, phevs), expansion
- Stage
- Under construction
- Timeline
- Hyundai Motor Group Metaplant America (HMGMA), near Savannah in Bryan County, Georgia, began as a $5.5 billion project that grew to $7.6 billion and opened in March 2025. On September 4, 2025, federal immigration agents raided an on site battery factory joint venture then under construction, detaining nearly 500 people, more than 300 of them South Korean nationals, which The Associated Press reported delayed that battery plant's startup by two to three months, to the first half of 2026. On September 18, 2025, Hyundai Motor Company announced a Phase 2 HMGMA expansion as part of its CEO Investor Day, committing $2.7 billion to add 200,000 units of annual capacity by 2028 and create 3,000 direct and indirect jobs in Georgia. The Atlanta Journal-Constitution reported the expansion would grow Hyundai's Ellabell workforce from 3,129 employees toward a previously stated target of at least 8,500 by 2031.
- Contractor / EPC
- Not announced
- Sources
- Hyundai Motor Group Newsroom, The Atlanta Journal-Constitution, The Associated Press, via CBS News Atlanta
Why it matters
A second construction phase on an already massive campus, adding capacity for a midsize pickup and more hybrid and EV models, means continued work for contractors and suppliers in the Savannah area even as the site works through fallout from the September 2025 immigration raid.
What this project buys
- Structural steel erection
- Electrical and controls for new assembly lines
- Mechanical and HVAC
- Robotics and automation installation
- Site work and paving
- Fire protection
When to approach: Hyundai has said the $2.7 billion expansion will roll out over three years to reach its 2028 capacity target, with construction and tooling work for new model lines expected to ramp up well before that date; the company has not published a trade by trade bid schedule.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Hyundai expanding its Georgia EV plant?
At Hyundai Motor Group Metaplant America (HMGMA) in Ellabell, Bryan County, Georgia, west of Savannah.
How much is Hyundai investing in the Ellabell expansion?
$2.7 billion over three years, which Hyundai calls Phase 2 of HMGMA, announced September 18, 2025.
How many jobs will the expansion create?
Hyundai said the expansion will create 3,000 direct and indirect jobs in Georgia, part of a path toward a total Ellabell workforce of at least 8,500 by 2031, up from 3,129 employees at the time of the announcement.
What will the expanded plant build?
Hyundai said HMGMA is expected to build a mix of 10 hybrid and EV models, up from two today, including the plant's first midsize pickup truck, and to reach 500,000 vehicles of annual capacity by 2028.
Did the September 2025 ICE raid affect the expansion?
The raid hit an on site battery factory joint venture, not the assembly plant, and The Associated Press reported it delayed the battery plant's startup by two to three months. Hyundai said its broader Georgia expansion plans remained on track.
Sources
- Hyundai Motor Company Unveils Bold 2030 Vision and Product Roadmap at 2025 CEO Investor Day, Hyundai Motor Group Newsroom, Sept. 18, 2025
- 10 hybrid and EV models, 3K jobs part of Hyundai's next phase in Georgia, The Atlanta Journal-Constitution, Sept. 18, 2025
- Hyundai moving forward with $2.7 billion Georgia plant expansion after ICE raid, The Associated Press, via CBS News Atlanta, Sept. 19, 2025