Manufacturing · TN

SK On takes sole ownership of the Stanton, Tennessee, battery plant as its Ford joint venture dissolves.

SK On Tennessee became an independent company on May 21, 2026, taking full control of the Stanton battery plant after Ford and SK On dissolved their BlueOval SK joint venture.

Quick answer

SK On Tennessee: investment not disclosed in Stanton, Tenn. Stage: Under construction. Timeline: Ford and SK On formed the BlueOval SK joint venture in September 2021, planning a combined $11.4 billion investment in three battery plants, one on Ford's campus in Stanton, Tennessee, and two in Kentucky. The joint venture broke ground in Kentucky in December 2022, and the U.S. Department of Energy closed a $9.6 billion loan to the venture in December 2024. In December 2025, Ford and SK On agreed to dissolve the joint venture, with SK On Americas spokesperson Joe Guy Collier confirming the deal to WardsAuto; the companies expected it to close in the first quarter of 2026. On March 6, 2026, BlueOval SK notified Tennessee regulators it would lay off 150 employees at the Stanton site effective around May 5, 2026, ahead of the ownership change. The dissolution closed on May 21, 2026, when SK On Tennessee became an independent SK On subsidiary and took full ownership of the Stanton plant; a Ford subsidiary took full ownership of the two Kentucky plants in the same split. Likely to buy: process piping and hvac, electrical and controls, equipment installation and rigging, site utilities.

Steel frame of an industrial building under construction
Illustrative photo. Photo: Laura Cleffmann / Pexels

By Capex Wire NewsroomPublished 3 min read

SK On Tennessee became an independent company on May 21, 2026, taking full ownership of the battery plant under construction in Stanton, Tennessee, after its joint venture with Ford Motor Co. dissolved, SK On said in a statement. The change ends more than three years of joint ownership under the BlueOval SK venture and leaves SK On alone in charge of the Haywood County plant, which the company still expects to start production in 2028.

What is being built

The Stanton plant is a lithium ion battery manufacturing facility on Ford's BlueOval City campus, originally planned to supply batteries for Ford electric vehicles. Ford and SK On formed BlueOval SK in September 2021 to build the Stanton plant along with two battery plants in Kentucky, in what Ford called the largest manufacturing commitment in its history at the time, a combined $11.4 billion investment across all three sites. No investment figure specific to the Stanton plant alone has been publicly disclosed. The joint venture broke ground in Kentucky in December 2022, and the U.S. Department of Energy closed a $9.6 billion loan to the venture in December 2024 to help finance all three plants.

Capex Wire

Get there first: every project owner on the U.S. Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.7 trillion

in announced or filed value

Subscribe for $9.90/month

Cancel anytime in one click.

Jobs and timeline

As demand for electric vehicles slowed and the federal EV tax credit ended on September 30, 2025, Ford said it no longer needed the battery capacity it had originally planned for, and the two companies agreed in December 2025 to dissolve BlueOval SK. SK On Americas spokesperson Joe Guy Collier confirmed the planned dissolution to WardsAuto at the time. On March 6, 2026, BlueOval SK notified Tennessee workforce officials it would lay off 150 employees at the Stanton site, with the cuts effective around May 5, 2026, according to a state WARN notice reported by The Daily Memphian. The affected workers kept their pay and benefits for 60 days after the notice. The dissolution closed on May 21, 2026, when SK On Tennessee launched as an independent SK On subsidiary. SK On Tennessee Chief Executive Officer Michael Adams said in the company's announcement that the move marks "the start of an exciting new era for our company," giving it "greater flexibility to make strategic decisions" and letting it "respond more quickly to market demands." SK On has not disclosed a current employee count for the Stanton site or new hiring plans, saying only that hiring updates will come as the company progresses.

Who is building it

SK On Tennessee now owns and operates the Stanton plant outright. No general contractor has been named for the facility's remaining construction. Under the dissolved joint venture, a Ford subsidiary took full ownership of BlueOval SK's two Kentucky battery plants in the same split, while Ford shifted its plans for its own Stanton operations away from electric vehicles. Ford says it will produce gasoline powered pickup trucks at a renamed Tennessee Truck Plant on the same campus starting in 2029, and that the Ford employees tied to that truck production were not affected by the battery plant layoffs.

What the project will buy

With production still two years off, the Stanton plant will need continued work on process piping, electrical and control systems, equipment installation and the interior buildout specific to battery cell manufacturing lines, along with site utilities and fire protection systems sized for a large scale battery plant. SK On has not published a new bid schedule or contractor list since taking sole ownership, and it is not clear how much of the plant's shell and infrastructure was completed under the former joint venture.

ItemFigure
Original combined investment, 3 plants$11.4 billion
DOE loan to joint venture$9.6 billion
Stanton layoffs150 employees
Ownership change closedMay 21, 2026
Targeted production start2028

What happens next

SK On Tennessee says it will spend the near term strengthening operations, systems and workforce development at the Stanton site as it works toward the 2028 production target. The company has not said whether it will change the plant's design, capacity or product mix now that it owns the facility outright, though it has said it plans to supply batteries from Stanton to customers beyond Ford, including for stationary energy storage systems. No new regulatory filings or construction permits tied specifically to the ownership change have been reported as of November 2026.

Project fileTN
Owner
SK On Tennessee
Investment
Not disclosed (Ford and SK On's original 2021 agreement covered a combined $11.4 billion for three battery plants, one in Stanton and two in Kentucky. No investment figure specific to the Stanton plant alone has been publicly disclosed.)
Location
Stanton, Haywood County, Tennessee
Type
EV and energy storage battery cell plant
Stage
Under construction
Timeline
Ford and SK On formed the BlueOval SK joint venture in September 2021, planning a combined $11.4 billion investment in three battery plants, one on Ford's campus in Stanton, Tennessee, and two in Kentucky. The joint venture broke ground in Kentucky in December 2022, and the U.S. Department of Energy closed a $9.6 billion loan to the venture in December 2024. In December 2025, Ford and SK On agreed to dissolve the joint venture, with SK On Americas spokesperson Joe Guy Collier confirming the deal to WardsAuto; the companies expected it to close in the first quarter of 2026. On March 6, 2026, BlueOval SK notified Tennessee regulators it would lay off 150 employees at the Stanton site effective around May 5, 2026, ahead of the ownership change. The dissolution closed on May 21, 2026, when SK On Tennessee became an independent SK On subsidiary and took full ownership of the Stanton plant; a Ford subsidiary took full ownership of the two Kentucky plants in the same split.
Contractor / EPC
Not announced
Sources
SK On (press release), Supply Chain Dive, The Daily Memphian

Why it matters

A single new owner now controls the Stanton battery plant's direction after a joint venture breakup and layoffs stalled momentum, meaning contractors and suppliers still have a shot at site work and equipment buildout before a 2028 production target, once SK On Tennessee sets its own construction pace.

What this project buys

  • Process piping and HVAC
  • Electrical and controls
  • Equipment installation and rigging
  • Site utilities
  • Interior fit out for battery cell production lines
  • Fire protection and safety systems

When to approach: SK On Tennessee says it is preparing the Stanton site for production targeted to begin in 2028. The company has not published a new construction or bid schedule since taking sole ownership in May 2026.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is the SK On Tennessee battery plant located?

On Ford's BlueOval City campus in Stanton, Haywood County, Tennessee.

Who owns the Stanton battery plant now?

SK On Tennessee, a new, independent U.S. subsidiary of SK On, became the sole owner and operator on May 21, 2026, after the BlueOval SK joint venture with Ford dissolved.

When will the Stanton plant start production?

SK On says production is expected to begin in 2028.

What happened to jobs at the plant before the ownership change?

BlueOval SK laid off 150 employees at the Stanton facility effective around May 5, 2026, according to a state WARN notice reported by The Daily Memphian. SK On Tennessee has not disclosed a current headcount or new hiring plans beyond saying updates will come as the company progresses.

What happened to Ford's side of the joint venture?

A Ford subsidiary took full ownership of the venture's two Kentucky battery plants. Ford has scrapped its EV plans for the Stanton campus and says it will build gasoline powered pickup trucks there, at the renamed Tennessee Truck Plant, starting in 2029.