Capex WireMore than $1.7 trillion in U.S. capital projects on the map, with new ones every day. Just $9.90/month, cancel anytime.Subscribe ›
Sunday, Nov. 22, 2026 · U.S. editionNov. 22, 2026How we reportLog inSubscribe to Capex Wire

U.S. capital projects before the bid list closes.

Semiconductors & Electronics · OH

Intel installs the first structural truss at its $28 billion Ohio chip campus in New Albany.

Crews raised the first major steel truss for Intel's first New Albany fab in October 2026, as the chipmaker holds to a 2030 to 2031 start date for a campus it once planned to open in 2025.

Quick answer

Intel Corporation: $28 billion investment in New Albany, Ohio. Stage: Under construction. Timeline: Intel announced the Ohio One campus in January 2022 and broke ground that year, originally targeting production in 2025. In February 2025, Naga Chandrasekaran, Intel's chief global operations officer, told employees the company would push completion of the first fab, known as Mod 1, to 2030, with operations starting between 2030 and 2031. The second fab, Mod 2, is now expected to finish construction in 2031 and begin operations in 2032. Intel said it had completed the fab's below grade basement level in late 2024, calling it the project's go vertical milestone. In October 2026, crews installed the first major structural truss for Mod 1, Intel said, marking the start of above ground steel erection. No fab has opened at the site as of November 2026. Likely to buy: structural steel erection, concrete and foundations, electrical and controls, mechanical, process piping and cleanroom buildout.

Tower cranes at a semiconductor fab construction site
Illustrative photo. Photo: Mike van Schoonderwalt / Pexels

By Capex Wire NewsroomPublished 3 min read

Intel installed the first major structural truss at its Ohio One chip campus in New Albany in October 2026, the company said, a construction milestone that keeps the $28 billion project moving after two rounds of delays pushed its opening from 2025 into the next decade. Intel is still holding to the 2030 to 2031 timeline it set in February 2025 for the first of two planned fabs on the roughly 1,000 acre site east of Columbus.

What is being built

Intel's Ohio One campus will eventually house two leading edge chip factories, called Mod 1 and Mod 2, that the company says together represent an investment of more than $28 billion. Intel broke ground on the site in 2022 after announcing the project in January of that year, originally aiming to start production in 2025. The company has since pushed that date back twice, most recently in a February 28, 2025 message from Naga Chandrasekaran, Intel's executive vice president and chief global operations officer, who told Ohio employees the company needed to align fab start dates with market demand and manage its capital responsibly. Intel has not disclosed the combined square footage of the two fabs.

Capex Wire

Get there first: every project owner on the U.S. Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.7 trillion

in announced or filed value

Subscribe for $9.90/month

Cancel anytime in one click.

Jobs and timeline

Intel has said the Ohio One project is expected to create about 3,000 permanent company jobs and 7,000 construction jobs over the life of the build. Under the current schedule, Intel plans to complete construction of Mod 1 in 2030 and begin operations there between 2030 and 2031. Mod 2 is expected to finish construction in 2031, with operations starting in 2032. Intel said it completed the below grade basement level of the first fab in late 2024, a milestone it called going vertical, before beginning the above ground steel structure. The October 2026 truss installation is the next visible step in that above ground build, Intel said, as crews assemble the steel skeleton that will support the fab's roof and process floors.

Who is building it

Intel has not publicly named a general contractor for Ohio One's current construction phase. The company has said it is sourcing labor and materials from Ohio based suppliers and contractors where possible as part of its broader commitment to the state. In November 2024, Intel received $1.5 billion in funding tied to the federal CHIPS and Science Act for the Ohio One project, part of a broader slate of federal awards the company has received for its U.S. fab network.

What the project will buy

With two fabs still years from completion, Ohio One will continue to need structural steel, concrete, mechanical and electrical trades, and the specialized cleanroom and process piping buildout that semiconductor fabs require once their shells are enclosed. Intel has said it will proceed at what it calls a slower, more deliberate construction pace than originally planned, while keeping the flexibility to accelerate work if customer demand for its foundry business picks up. No schedule for individual trade bid packages has been published.

ItemFigure
InvestmentMore than $28 billion
SiteAbout 1,000 acres, New Albany, Licking County
Permanent jobsAbout 3,000
Construction jobsAbout 7,000
Mod 1 construction complete2030
Mod 1 operations start2030 to 2031
Mod 2 construction complete2031
Mod 2 operations start2032

What happens next

Intel says construction will continue at Ohio One through the rest of this decade, with above ground steel work, building enclosure and eventually tool installation still ahead for Mod 1 before it can begin operations in 2030 or 2031. The company has repeatedly said its long term commitment to the Ohio site has not changed even as it pushed back the opening date twice, citing the need to match fab construction to actual demand from foundry customers. Intel has not announced a further revision to the timeline since the February 2025 update, and no additional state or federal funding commitments tied specifically to the October 2026 truss milestone have been reported.

Project fileOH
Owner
Intel Corporation
Investment
$28 billion (Intel says it plans to invest more than $28 billion to build two leading edge chip factories at the site; the company has not disclosed a more precise total.)
Location
New Albany, Licking County, Ohio
Type
Semiconductor fab, new construction (two fabs, Mod 1 and Mod 2)
Stage
Under construction
Timeline
Intel announced the Ohio One campus in January 2022 and broke ground that year, originally targeting production in 2025. In February 2025, Naga Chandrasekaran, Intel's chief global operations officer, told employees the company would push completion of the first fab, known as Mod 1, to 2030, with operations starting between 2030 and 2031. The second fab, Mod 2, is now expected to finish construction in 2031 and begin operations in 2032. Intel said it had completed the fab's below grade basement level in late 2024, calling it the project's go vertical milestone. In October 2026, crews installed the first major structural truss for Mod 1, Intel said, marking the start of above ground steel erection. No fab has opened at the site as of November 2026.
Contractor / EPC
Not announced
Sources
Intel Corporation Newsroom, Manufacturing Dive (Construction Dive), ServeTheHome

Why it matters

A 1,000 acre campus with two chip fabs still under construction means years of structural, mechanical and cleanroom buildout work ahead, even on a timeline Intel has pushed back twice, giving contractors and suppliers a long runway to get on site before production bid packages ramp up.

What this project buys

  • Structural steel erection
  • Concrete and foundations
  • Electrical and controls
  • Mechanical, process piping and cleanroom buildout
  • Site utilities and earthwork
  • Equipment rigging and installation

When to approach: Structural steel erection and shell construction are underway now. Intel says it will keep building at a slower pace than originally planned, with mechanical, electrical, process piping and cleanroom fit out work expected to ramp up as the shell is enclosed ahead of a targeted 2030 completion for the first fab.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is Intel building its Ohio One chip fabs?

In New Albany, Licking County, Ohio, on a roughly 1,000 acre campus east of Columbus.

How much is Intel investing in Ohio One?

More than $28 billion to build two leading edge chip factories, known as Mod 1 and Mod 2, Intel says.

When will the Ohio One fabs start production?

Intel now plans to complete construction of the first fab, Mod 1, in 2030 and begin operations between 2030 and 2031. The second fab, Mod 2, is expected to finish construction in 2031 and begin operations in 2032.

What construction milestone did Intel just reach at Ohio One?

In October 2026, crews installed the first major structural truss for Mod 1, starting above ground steel erection after finishing the fab's basement level in late 2024.

How many jobs will the Ohio One project create?

Intel has said the project is expected to create about 3,000 permanent Intel jobs plus 7,000 construction jobs over the course of the build.

Sources

More capital projects