U.S. capital projects before the bid list closes.

Semiconductors & Electronics · NY

Micron pours first concrete at its $100 billion Clay, New York chip campus, ahead of schedule.

Foundation work on the four fab megafab began in July, more than a quarter ahead of plan, with Bechtel leading construction in Onondaga County.

Quick answer

Micron: $100 billion investment in Clay, N.Y. Stage: Under construction. Timeline: Groundbreaking Jan. 16, 2026. First concrete foundations poured in July 2026, more than a quarter ahead of schedule. Micron and New York officials have targeted around 2030 for the first fab to begin producing memory chips. Likely to buy: cleanroom construction, process piping and ultrapure water, electrical and substation, hvac and exhaust.

Aerial view of concrete foundations at a construction site in an early building phase
Illustrative photo. Photo: Peter Dyllong / Pexels

By Capex Wire NewsroomPublished 3 min read

Micron Technology has poured the first concrete foundations for its planned $100 billion semiconductor campus in Clay, New York, more than a quarter ahead of schedule, Gov. Kathy Hochul's office and Engineering News-Record reported.

The milestone, reached in July 2026, marked the shift from site preparation to vertical construction at the 1,377 acre White Pine Commerce Park site in Onondaga County, less than six months after Micron broke ground on Jan. 16, 2026.

What is being built

Micron plans up to four semiconductor fabrication plants at the Clay campus to produce DRAM memory chips, each spanning roughly 1.2 million square feet, The Register reported in January. The company has said the full four fab build out could cost up to $100 billion over more than 20 years. The Register reported the project would displace 500 acres of woods and wetlands at the site.

Capex Wire

Get there first: every project owner on the U.S. Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.7 trillion

in announced or filed value

Subscribe for $9.90/month

Cancel anytime in one click.

Jobs and timeline

New York officials say the project is expected to support up to 50,000 jobs statewide, including about 9,000 direct Micron positions once the campus is fully staffed, and more than 4,500 construction jobs at its peak, according to the governor's office and ENR. Micron and the state have targeted around 2030 for the first fab to begin producing chips. "This is the largest private investment in New York State history, and it's already delivering for New Yorkers, our state economy, and our local businesses," Hochul said in a statement from her office.

Who is building it

Micron named Bechtel as the engineering, procurement and construction contractor for the first fab, with Jacobs serving as architectural and engineering design partner and Gilbane Building Company handling preconstruction and site infrastructure work, the company said in a statement reported by Intelligent CIO. Sanjay Mehrotra, Micron's chairman, president and chief executive, said the company "is increasing our U.S. investments to more than $250 billion through 2035 to meet that moment." New York based contractors had been awarded about $675 million in work through July, more than half of the total contract value awarded so far, and more than 80% of workers on site to date had been New York residents, Micron said.

What the project will buy

MetricFigure
Full campus investmentUp to $100 billion over 20-plus years
Jobs statewide at full build outUp to 50,000, including about 9,000 direct Micron positions
Construction jobs at peakMore than 4,500
Site size1,377 acres at White Pine Commerce Park, Clay, N.Y.
GroundbreakingJan. 16, 2026
First concrete pouredJuly 2026

The work ahead calls for cleanroom construction, process piping and ultrapure water systems, substation level electrical work, HVAC and exhaust systems, structural steel erection and specialty gas systems, the trades Capex Wire tracks for fabs of this type.

What happens next

Accounts differ on the schedule for Micron's remaining fabs at Clay. The Register reported in January that the first two fabs are set to come online in 2030, with the other two not finished until 2041, as part of a project the outlet said would take 20 years in total. Micron has not set a firm completion date for the full four fab campus. New York now counts 156 semiconductor and supply chain companies employing more than 34,000 workers in the state, according to the governor's office. Micron and Bechtel did not respond to ENR's request for comment on the July schedule.

Project fileNY
Owner
Micron
Investment
$100 billion (Up to $100 billion over more than 20 years for the full four fab Clay campus, as described by Micron and New York state officials. Micron separately raised its nationwide U.S. investment plan to more than $250 billion through 2035, a figure not specific to this site.)
Location
Clay, Onondaga County, New York
Type
Semiconductor fab, new facility
Stage
Under construction
Timeline
Groundbreaking Jan. 16, 2026. First concrete foundations poured in July 2026, more than a quarter ahead of schedule. Micron and New York officials have targeted around 2030 for the first fab to begin producing memory chips.
Contractor / EPC
Bechtel
Sources
Office of Governor Kathy Hochul, Engineering News-Record, Intelligent CIO, The Register

Why it matters

The first fab alone calls for cleanroom fit out, ultrapure water and specialty gas systems, substation level electrical work and heavy structural steel, with three more fabs planned behind it.

What this project buys

  • Cleanroom construction
  • Process piping and ultrapure water
  • Electrical and substation
  • HVAC and exhaust
  • Structural steel erection
  • Specialty gas systems

When to approach: Bechtel, Jacobs and Gilbane are already on site for the first fab. Trade bid packages are expected to keep opening as vertical construction continues toward the targeted 2030 startup.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is Micron's new semiconductor fab in New York?

In Clay, Onondaga County, at the 1,377 acre White Pine Commerce Park site, according to Gov. Kathy Hochul's office and The Register.

How many jobs will Micron's Clay, NY fab create?

New York officials say the project is expected to support up to 50,000 jobs statewide, including about 9,000 direct Micron positions and more than 4,500 construction jobs at peak, according to the governor's office and Engineering News-Record.

When will construction start and when will the fab open?

Micron broke ground on Jan. 16, 2026 and poured its first concrete foundations in July 2026, more than a quarter ahead of schedule. The first fab is targeted to begin producing memory chips around 2030, according to the governor's office and ENR.

Who is building Micron's New York fab?

Bechtel is the engineering, procurement and construction contractor for the first fab, with Jacobs as architectural and engineering design partner and Gilbane Building Company handling preconstruction and site infrastructure, Micron said in a statement reported by Intelligent CIO.

How much is Micron investing in the Clay, New York project?

Up to $100 billion over more than 20 years for as many as four fabs at the Clay campus, according to state and trade press reports. Micron has separately said it is raising its nationwide U.S. semiconductor investment plan to more than $250 billion through 2035.