Data Centers · GA

Effingham County, Georgia, approves the site plan for OpenAI's $20 billion Project Camellia data center.

Effingham County commissioners approved the site plan for OpenAI's six-building Project Camellia data center on Nov. 17, 2026, while pushing a decision on future data center applications to January.

Quick answer

OpenAI: $20 billion investment in Rincon, Ga. Stage: Filed / permitted. Timeline: OpenAI announced Project Camellia on July 22, 2026, proposing a four building data center campus in the Savannah Gateway Industrial Hub near Rincon. Effingham County commissioners postponed a decision on the site plan in early November, then approved the revised, six building site plan on Nov. 17, 2026. OpenAI's power contract with Georgia Power calls for 3.2 gigawatts delivered in phases between 2028 and 2032, with the company projecting the facility will open in 2028. Likely to buy: site work and grading, concrete and structural work, electrical and substation construction, backup generator installation.

Large industrial building under construction in a rural landscape
Illustrative photo. Photo: Andy Coffie / Pexels

By Capex Wire NewsroomPublished 3 min read

Effingham County, Georgia, commissioners approved the site plan for OpenAI's Project Camellia data center campus on Nov. 17, 2026, clearing a key local hurdle for the $20 billion project while delaying a separate vote on limiting future data center applications until January.

What is being built

Project Camellia is OpenAI's data center campus planned for the Savannah Gateway Industrial Hub, a roughly 2,600 acre industrial park near Rincon that includes 1,600 undeveloped acres, according to the Atlanta Journal-Constitution. OpenAI first disclosed the project in a July 2026 state regulatory filing describing a four building campus totaling 4.4 million square feet. An OpenAI project engineer told commissioners the company has since revised the plan into six smaller buildings, which the engineer said reduces concrete use and improves site access for construction crews and first responders. OpenAI's own announcement describes the Savannah Gateway Industrial Hub as "a pre-existing industrially zoned warehouse project" and says the company is contracting with Georgia Power for 3.2 gigawatts of power, delivered in phases between 2028 and 2032.

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 5 projects like this

$9.90/month · cancel anytime in one click

Jobs and timeline

The Atlanta Journal-Constitution reported OpenAI's regulatory filing projects the data center will employ 400 workers in six figure jobs when it opens in 2028, growing to 1,000 employees by 2032. OpenAI's own project page does not give that figure, saying instead the project "will create thousands of construction and permanent on site jobs and prioritize local contractors and businesses." Commissioner Roger Burdette told WTOC a development agreement between OpenAI and the county is "the next step" after the site plan vote, and no construction start date or general contractor has been announced.

Who is building it and what it will buy

OpenAI is developing the project directly, with Georgia Power as its contracted utility; Georgia Power senior vice president Aaron Mitchell has said the utility is "working every day to help ensure that growth from data centers and other large-energy users" brings reliability and lower prices for customers. The local engineering firm Thomas and Hutton is working with OpenAI on the site, including a stormwater plan using retention ponds to direct water around the buildings, according to WTOC. The company has committed to a 20 foot berm and a 300 foot vegetative buffer along Hodgeville Road, four backup diesel generators limited to life safety systems, and no on site natural gas generation for its computing systems, with a noise study underway and more sound barriers possible if needed.

ItemFigure
OpenAI's stated investment$20 billion
Contracted power3.2 gigawatts
Original filing's building size4.4 million sq ft (4 buildings)
Revised building count6 buildings
Projected jobs at opening (2028)400
Projected jobs by 20321,000
Community benefit commitment$80 million over the project's life

What happens next

Commissioners put off a separate decision on a proposed pause on certain future data center applications until January, after Burdette said he wanted input from other municipalities on conditional zoning first; a draft resolution had already stated any such pause would not apply to Project Camellia. OpenAI has committed to paying the full cost of the electric service infrastructure the project needs, which under Georgia Public Service Commission rules cannot be passed on to existing ratepayers, and to an $80 million community benefit commitment over the project's life covering schools, public safety, health care and workforce training, on top of what it says will make it the county's largest taxpayer.

Project fileGA
Owner
OpenAI
Investment
$20 billion (OpenAI's own $20 billion figure, first reported in a July 2026 regulatory filing; the Atlanta Journal-Constitution has not confirmed a breakdown, and OpenAI's own project page does not restate the number.)
Location
Rincon, Effingham County, Georgia
Type
Data center campus, Project Camellia, site plan approved
Stage
Filed / permitted
Timeline
OpenAI announced Project Camellia on July 22, 2026, proposing a four building data center campus in the Savannah Gateway Industrial Hub near Rincon. Effingham County commissioners postponed a decision on the site plan in early November, then approved the revised, six building site plan on Nov. 17, 2026. OpenAI's power contract with Georgia Power calls for 3.2 gigawatts delivered in phases between 2028 and 2032, with the company projecting the facility will open in 2028.
Contractor / EPC
Not announced
Sources
WTOC, The Atlanta Journal-Constitution, OpenAI

Why it matters

A privately funded, $20 billion data center campus with a 3.2 gigawatt power contract means years of site work, substation and backup generation construction and fiber buildout in the Savannah area, even before a general contractor or detailed schedule is public.

What this project buys

  • Site work and grading
  • Concrete and structural work
  • Electrical and substation construction
  • Backup generator installation
  • Fiber and utility infrastructure
  • Stormwater and drainage infrastructure

When to approach: Commissioner Roger Burdette said a development agreement is the next step for the project; no construction start date or general contractor has been announced. A noise study and a stormwater plan using retention ponds, led by engineering firm Thomas and Hutton, are both still in development.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is OpenAI's Project Camellia data center?

In the Savannah Gateway Industrial Hub near Rincon, in Effingham County, Georgia, about a 30 minute drive from downtown Savannah.

How much will Project Camellia cost and how big is it?

OpenAI has cited a $20 billion investment figure in state filings. The project is contracted for 3.2 gigawatts of power from Georgia Power, delivered in phases between 2028 and 2032, and its original state filing described a four building, 4.4 million square foot campus; the site plan Effingham County approved on Nov. 17, 2026, divides that into six smaller buildings.

When will construction start and when will it open?

Effingham County approved the project's site plan on Nov. 17, 2026; commissioner Roger Burdette said a development agreement is the next step, and no construction start date has been announced. OpenAI has projected the facility will begin opening in 2028.

How many jobs will Project Camellia create?

The Atlanta Journal-Constitution reported OpenAI's filings project 400 workers in six figure jobs when the facility opens in 2028, rising to 1,000 employees by 2032; OpenAI's own project page says only that it will create thousands of construction and permanent on site jobs.

Who is building Project Camellia?

OpenAI is developing the project itself, working with Georgia Power on its electricity supply and with the Effingham County Industrial Development Authority on the deal; the local engineering firm Thomas and Hutton is working on the site's stormwater plan. No general contractor has been named publicly.