Samsung SDI buys GM's stake in $3.5 billion battery plant in New Carlisle, Indiana.
Samsung SDI took full ownership of the SynergyCells battery plant on Aug. 11, 2026, buying out GM's 49.99% stake months after GM paused construction amid slowing U.S. EV demand.
Quick answer
Samsung SDI: $3.5 billion investment in New Carlisle, Ind. Stage: Under construction. Timeline: GM and Samsung SDI announced the joint venture in April 2023. Indiana officials announced the project on June 13, 2023, projecting 1,700 manufacturing jobs and more than 30 GWh of annual capacity on a 656-acre site at the Indiana Enterprise Center. Construction began in early 2024, and the companies finalized their joint venture agreement, SynergyCells, in August 2024, saying mass production would begin in 2027 rather than the originally planned 2026. In November 2025, St. Joseph County economic development director Bill Schalliol said some construction workers had been laid off as the venture redesigned its product line. On May 14, 2026, GM confirmed it was pausing construction entirely. On Aug. 11, 2026, Samsung SDI announced it had acquired GM's entire 49.99% stake in SynergyCells, becoming sole owner of the plant. Likely to buy: site work and foundations, structural steel erection, electrical and substation, mechanical and hvac.

By Capex Wire NewsroomPublished 3 min read
Samsung SDI said Aug. 11, 2026, that it has acquired General Motors' entire 49.99% stake in SynergyCells, the joint venture building an electric vehicle battery plant in New Carlisle, Indiana, making the South Korean company the plant's sole owner. The deal ends a three-year partnership that began as one of Indiana's largest-ever economic development announcements, and it follows a construction pause GM confirmed in May 2026 amid slowing U.S. electric vehicle demand.
What is being built
SynergyCells is a lithium ion battery cell plant on a 656-acre site at the Indiana Enterprise Center near New Carlisle, in St. Joseph County, according to Indiana's 2023 economic development announcement and Inside INdiana Business. GM and Samsung SDI announced the venture in April 2023 and said it would invest more than $3 billion, later finalized at $3.5 billion, to build a 2.5 million-square-foot facility with more than 30 GWh of annual capacity, producing nickel-rich prismatic and cylindrical cells for GM electric vehicles. Construction began in early 2024. Gov. Eric Holcomb said at the time the investment was proof that "Indiana has turned it up and shifted into a higher gear." GM had turned to Samsung SDI as a cell supplier after recalling Chevrolet Bolt EVs over LG-made battery cells blamed for fire risk, according to the Associated Press.
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 69 projects like this$9.90/month · cancel anytime in one click
Ownership change
Samsung SDI's Aug. 11 statement said the ownership change "was made in consideration of market changes since the joint venture was announced, including the slower-than-expected growth of EV demand," and that the two companies "have now decided to seek other forms of cooperation other than the joint venture." The price GM received for its stake was not disclosed. Samsung SDI said the deal gives it "its first independently operated battery production base in North America." In the same release, Samsung SDI and GM signed a separate agreement to jointly develop next generation prismatic battery cells for potential future GM electric vehicles, which the companies said would feature high energy density and fast charging. A Samsung SDI official, not named in the release, said the move is meant "to continue the strategic partnership with GM" while reflecting recent market changes.
Jobs and timeline
Indiana's 2023 announcement projected 1,700 manufacturing jobs at the completed plant and more than 1,000 construction jobs during the build; some later coverage of the venture has cited a lower figure of about 1,600 jobs. GM and Samsung SDI finalized their joint venture agreement in August 2024 and said then that mass production, originally targeted for 2026, would not begin until 2027. St. Joseph County economic development director Bill Schalliol said in November 2025 that an unspecified number of construction workers were laid off as the venture redesigned its product line. On May 14, 2026, GM spokesperson Kevin Kelly confirmed the company was pausing construction "to align production capacity with current demand," a decision GM tied to a $7.2 billion fourth quarter charge for realigning its EV investments after the federal EV purchase tax credit ended Sept. 30, 2025. Schalliol said at the time that some construction crews on the GM-Samsung SDI site were shifting to nearby Amazon Web Services and Microsoft data center projects in the area while GM and Samsung SDI worked out a path forward.
Who is building it
Samsung SDI now owns and operates the New Carlisle plant outright; no general contractor has been named for the site's remaining construction. GM keeps a supply relationship through the new prismatic battery development agreement but no longer holds an ownership stake in the plant. Samsung SDI said it will initially use the facility to produce batteries for stationary energy storage systems, to meet what it called fast-growing U.S. demand, before potentially adding the jointly developed prismatic EV cells later.
| Item | Figure |
|---|---|
| Original joint venture investment | $3.5 billion |
| Samsung SDI's acquired stake | 49.99% (GM's full stake) |
| Planned annual capacity | more than 30 GWh |
| Projected manufacturing jobs | 1,700 (2023 estimate) |
| Site size | 656 acres, Indiana Enterprise Center |
| Construction paused | May 14, 2026 |
| Ownership change closed | Aug. 11, 2026 |
What happens next
Samsung SDI has not published a new construction schedule, bid package or contractor list for the New Carlisle site since taking full ownership. The company says the plant remains under construction, but it has not said when work beyond site infrastructure will resume or whether the facility's footprint or capacity will change under the new ESS-first production plan. St. Joseph County said it would continue finishing infrastructure projects in the Indiana Enterprise Center area in the meantime.
- Owner
- Samsung SDI
- Investment
- $3.5 billion (Original joint venture investment GM and Samsung SDI announced in 2023 and finalized in 2024. The price Samsung SDI paid for GM's 49.99% stake in August 2026 was not disclosed.)
- Location
- New Carlisle, St. Joseph County, Indiana
- Type
- Battery plant (cells), new construction
- Stage
- Under construction
- Timeline
- GM and Samsung SDI announced the joint venture in April 2023. Indiana officials announced the project on June 13, 2023, projecting 1,700 manufacturing jobs and more than 30 GWh of annual capacity on a 656-acre site at the Indiana Enterprise Center. Construction began in early 2024, and the companies finalized their joint venture agreement, SynergyCells, in August 2024, saying mass production would begin in 2027 rather than the originally planned 2026. In November 2025, St. Joseph County economic development director Bill Schalliol said some construction workers had been laid off as the venture redesigned its product line. On May 14, 2026, GM confirmed it was pausing construction entirely. On Aug. 11, 2026, Samsung SDI announced it had acquired GM's entire 49.99% stake in SynergyCells, becoming sole owner of the plant.
- Contractor / EPC
- Not announced
- Sources
- Samsung SDI (press release), Electrek, WardsAuto (via Manufacturing Dive), Korea JoongAng Daily, Inside INdiana Business, Indiana Economic Development Corporation, Associated Press (via Indianapolis Business Journal)
Why it matters
A single new owner now controls the New Carlisle plant's direction after a joint venture pause stalled momentum, meaning contractors and suppliers still have a shot at site work, equipment installation and buildout once Samsung SDI sets its own construction pace and product mix.
What this project buys
- Site work and foundations
- Structural steel erection
- Electrical and substation
- Mechanical and HVAC
- Process piping
- Fire protection
When to approach: Samsung SDI has not published a new construction schedule, bid package or contractor list for the New Carlisle site since taking full ownership on Aug. 11, 2026. The company says the plant remains under construction but has not said when work beyond site infrastructure will resume.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Who owns the battery plant in New Carlisle, Indiana, now?
Samsung SDI became the sole owner on Aug. 11, 2026, after acquiring General Motors' entire 49.99% stake in their SynergyCells joint venture.
Why did GM sell its stake in the New Carlisle battery plant?
Samsung SDI said the ownership change reflects market changes since the 2023 announcement, including slower than expected U.S. EV demand, after GM had already paused construction in May 2026.
How many jobs will the New Carlisle battery plant create?
Indiana's 2023 announcement projected 1,700 manufacturing jobs, though some later coverage of the venture has cited about 1,600; Samsung SDI has not published an updated figure since taking ownership.
When will construction resume and production start?
Samsung SDI has not set a new schedule since the Aug. 11, 2026 ownership change. Before the pause, mass production was targeted for 2027.
What will the plant make now?
Samsung SDI says it will start by producing batteries for stationary energy storage systems, before potentially adding prismatic EV cells it is jointly developing with GM under a separate agreement.
Sources
- SAMSUNG SDI, General Motors Sign New Battery Development Agreement, Continuing Their Strategic Partnership, Samsung SDI (press release), Aug. 11, 2026
- GM exits $3.5B Indiana battery plant as Samsung SDI takes full control, Electrek, Aug. 11, 2026
- Samsung SDI acquires GM's stake in EV battery plant in Indiana, WardsAuto (via Manufacturing Dive), Aug. 12, 2026
- Samsung SDI, GM end $3.5B battery plant venture in Indiana, to co-develop prismatic batteries, Korea JoongAng Daily, Aug. 11, 2026
- GM to pause construction of EV battery plant in New Carlisle, officials say, Inside INdiana Business, May 14, 2026
- Gov. Holcomb announces largest EV investment in state history attracting a more than $3B battery plant, Indiana Economic Development Corporation, June 13, 2023
- GM delays Indiana EV battery factory, but finalizes joint venture deal with Samsung, Associated Press (via Indianapolis Business Journal), Aug. 28, 2024