Data Centers · GA

Williams Brothers Development wins zoning approval for $1 billion data center in McDuffie County, Georgia.

McDuffie County commissioners voted 4-1 to approve Project Azalea, a data center on a 200-acre site near the Columbia County line, after a review found the area lacks enough power to serve it yet.

Quick answer

Williams Brothers Development: $1 billion investment in McDuffie County, Ga. Stage: Announced. Timeline: A public listening session was held March 10, 2026, where residents submitted 74 questions in advance. The McDuffie County Board of Commissioners approved the rezoning 4-1 on March 17, 2026. No construction start date or completion date has been announced. Likely to buy: site grading and earthwork, electrical and substation work, water and sewer utility construction, structural and building shell construction.

Server equipment inside a modern data center
Illustrative photo. Photo: panumas nikhomkhai / Pexels

By Capex Wire NewsroomPublished 2 min read

Williams Brothers Development has won zoning approval to build a data center campus worth about $1 billion in McDuffie County, Georgia. The McDuffie County Board of Commissioners voted 4-1 on March 17, 2026 to approve the project, known as Project Azalea, after a public listening session the week before where residents submitted 74 questions about the plan in advance, according to the Augusta Chronicle and WRDW/WAGT.

What is being built

Project Azalea would rise on a 200-acre portion of property bordered by Randall Hunt Road, near the Columbia County line. At full build-out, the campus is expected to cover about 1.5 million square feet across six buildings, the Augusta Chronicle reported. The property sits within the "Countryside" character area of the county's comprehensive plan, and the commission's vote granted a zoning exception allowing a data center use there. The exact tenant that will run the facility has not been disclosed.

Capex Wire

Get there first: every project owner on the U.S. Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.7 trillion

in announced or filed value

Subscribe for $9.90/month

Cancel anytime in one click.

Jobs and timeline

The CSRA Regional Commission, in a state required review, estimates the project will create about 125 full-time positions once the center is operating. WRDW/WAGT reported that the county manager had not clarified whether that figure includes construction jobs or only permanent data center staff. Neither a groundbreaking date nor a completion timeline has been announced, and no building permits have been reported filed for the site.

Who is building it

Williams Brothers Development, based in Gainesville, Georgia, is the developer behind Project Azalea. The Augusta Chronicle reported that the company oversees other data center projects across the state. Company representative Cameron Grogan presented the plan at the March 10 listening session, where county staff and residents raised questions about traffic, noise and water use. No general contractor or design firm has been announced for construction.

What the project will buy

Developers cited an adjacent Jefferson Electric Cooperative substation as a reason for choosing the site, pointing to favorable power access. But the state required Development of Regional Impact report, completed Feb. 13, found there is not currently enough energy supply available to serve the project, according to WRDW/WAGT, meaning utility upgrades are likely before construction can start. Once building plans advance, the project will also need site grading, water and sewer connections, and the electrical and mechanical systems that a data center of that size requires.

What happens next

County officials project the data center could generate about $25 million a year in local tax revenue once fully built, including $4.6 million in county ad valorem taxes and $9 million in school ad valorem taxes, according to CSRA Regional Commission figures cited by the Augusta Chronicle. The first phase alone is projected to generate about $8.5 million. The regional review identified 18 outside parties that could be affected by the project, including Fort Gordon, Augusta-Richmond County, Jefferson County and Columbia County, where at least two other data center projects are advancing on sites about five miles away. The advisory DRI report does not limit McDuffie County's authority over the project, and the rezoning approval is the only vote reported so far.

Project fileGA
Owner
Williams Brothers Development
Investment
$1 billion (Investment estimate at full build-out, per a state required Development of Regional Impact review cited by the Augusta Chronicle; not a single disclosed construction budget.)
Location
McDuffie County, Georgia
Type
Data center, new construction
Stage
Announced
Timeline
A public listening session was held March 10, 2026, where residents submitted 74 questions in advance. The McDuffie County Board of Commissioners approved the rezoning 4-1 on March 17, 2026. No construction start date or completion date has been announced.
Contractor / EPC
Not announced
Sources
Augusta Chronicle via AOL, WRDW/WAGT

Why it matters

A rezoning vote in a rural Georgia county signals more data center construction work moving into the Augusta area's supply chain, from electrical substation upgrades to the site work, water and sewer connections a six-building campus will need.

What this project buys

  • Site grading and earthwork
  • Electrical and substation work
  • Water and sewer utility construction
  • Structural and building shell construction
  • HVAC and cooling systems
  • Fiber and telecommunications infrastructure

When to approach: No building permits have been filed and no construction schedule has been announced; bid activity is not expected until the power supply gap identified in the state review is resolved.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is the new Project Azalea data center in Georgia?

On a 200-acre site bordered by Randall Hunt Road in McDuffie County, Georgia, near the Columbia County line, according to the Augusta Chronicle.

How many jobs will Project Azalea create?

About 125 full-time positions once operating, per a CSRA Regional Commission estimate cited by WRDW/WAGT. It is not clear whether that includes construction jobs.

When will construction start on the McDuffie County data center?

No construction start date has been announced. The county's state required review found there is not currently enough power supply to serve the project.

Who is building the McDuffie County data center?

Williams Brothers Development, a Gainesville, Georgia, company that the Augusta Chronicle says oversees other data center projects in the state.

How big is the Project Azalea data center campus?

About 1.5 million square feet across six buildings at full build-out, according to the Augusta Chronicle.