Hut 8 is building a data center campus valued at up to $10 billion in West Feliciana Parish, Louisiana.
The River Bend campus is already under construction, with Entergy Louisiana supplying power and tenant Fluidstack signed to lease capacity.
Quick answer
Hut 8: $10 billion investment in West Feliciana Parish, La. Stage: Under construction. Timeline: Hut 8, Entergy Louisiana and Louisiana Economic Development announced River Bend on Dec. 17, 2025, saying construction was already underway. Jacobs, the project's engineering and construction partner, said in a December 2025 release tied to the announcement that commercial operations are targeted for the second quarter of 2027, with up to 1,000 construction workers on site at the peak of Phase I. No specific site work start date or completion date beyond that target has been published. Likely to buy: electrical and substation construction, mechanical and liquid cooling systems, structural steel erection, site civil work and earthwork.

By Capex Wire NewsroomPublished 3 min read
Hut 8 is building a data center campus valued at up to $10 billion in West Feliciana Parish, Louisiana, with construction already underway on the first phase, the company, the state and its utility partner announced Dec. 17, 2025.
What is being built
The River Bend campus will draw an initial 330 megawatts of utility capacity from Entergy Louisiana, with room to scale to as much as 1,000 MW, according to joint announcements from Hut 8, Entergy and Louisiana Economic Development (LED). Of that initial capacity, 245 MW of critical IT load is committed to tenant Fluidstack. Hut 8 is paying for the generation, transmission and substation upgrades the site needs, Entergy said.
LED and Entergy describe Phase I as representing up to $10 billion in investment, including Hut 8's spending on data center infrastructure. Construction Dive, citing Hut 8's own release, put the same Phase I figure at approximately $10 billion. A separate Louisiana Quality Jobs incentive application on file with the state used a company specific estimate covering a narrower slice of the project than the Phase I total.
"Louisiana continues to win," Gov. Jeff Landry said in the companies' joint announcement. "Hut 8's investment in River Bend builds on our track record of attracting global-scale projects in the industries of the future." Hut 8 CEO Asher Genoot called the project "a testament to the power of partnership," crediting state and local leaders, Entergy and "the determination of the people of Louisiana."
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.6 trillion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
Jobs and timeline
Hut 8 said construction was already underway when the December 2025 announcement was made, with up to 1,000 construction workers expected on site at the peak of Phase I. LED estimates the project will support at least 75 direct, permanent jobs once operating, plus 193 indirect jobs in the region, for a total of 268. The companies are targeting commercial operations by the second quarter of 2027. No specific construction start date or completion date beyond that target has been published.
Who is building it
Jacobs, the Dallas based engineering and construction firm, is Hut 8's engineering, procurement and construction management partner for River Bend, working alongside data center infrastructure supplier Vertiv, according to Construction Dive. "Jacobs brings decades of global expertise in delivering complex infrastructure for advanced facilities to some of the most discerning clients in the world," Jacobs CEO Bob Pragada said in Hut 8's release. J.P. Morgan and Goldman Sachs are named as underwriters on project level financing expected to cover up to 85% of total costs, Construction Dive reported.
Fluidstack has signed a 15 year lease for capacity at River Bend. WAFB, the Baton Rouge television station, reported the site will supply AI computing capacity used by Anthropic under that deal, though Hut 8's and Entergy's own announcements name only Fluidstack as the tenant.
| Item | Figure |
|---|---|
| Phase I investment | Up to $10 billion |
| Initial utility capacity | 330 MW, scalable to 1,000 MW |
| Committed tenant load | 245 MW (Fluidstack) |
| Peak construction jobs | About 1,000 |
| Direct permanent jobs | 75+ (268 total with indirect) |
| Target operations | Second quarter of 2027 |
What happens next
Local officials are counting on the project for a large jump in tax revenue. West Feliciana Parish President Kenny Havard said the facility will generate an additional $90 million a year for local government once operating, on top of the roughly $41 million the parish currently collects, split a third each among the parish, the sheriff's office and the school system. "This can be a win, win, win for Louisiana," Havard said. Hut 8 also plans to participate in Louisiana's Quality Jobs incentive program and in the state's sales and use tax rebate on data center equipment under Act 730 of the 2024 legislative session, according to Entergy and LED. With construction already active and a 2027 operating target, bid packages for electrical, mechanical and site work tied to Phase I are likely open now through completion of the first phase.
- Owner
- Hut 8
- Investment
- $10 billion (up to $10 billion for Phase I, including Hut 8's data center infrastructure spending, per Entergy and Louisiana Economic Development; Construction Dive reported the same Phase I at approximately $10 billion, citing Hut 8. A separate Louisiana Quality Jobs filing used a company specific estimate of about $2.9 billion, covering a narrower slice of the project.)
- Location
- West Feliciana Parish, Louisiana
- Type
- AI data center campus, Phase I under construction
- Stage
- Under construction
- Timeline
- Hut 8, Entergy Louisiana and Louisiana Economic Development announced River Bend on Dec. 17, 2025, saying construction was already underway. Jacobs, the project's engineering and construction partner, said in a December 2025 release tied to the announcement that commercial operations are targeted for the second quarter of 2027, with up to 1,000 construction workers on site at the peak of Phase I. No specific site work start date or completion date beyond that target has been published.
- Contractor / EPC
- Jacobs (engineering, procurement and construction management), with Vertiv on data center infrastructure
- Sources
- Entergy, Louisiana Economic Development, Construction Dive, WAFB, Louisiana Board of Commerce and Industry
Why it matters
A data center campus with up to $10 billion in Phase I investment and up to 1,000 construction workers at peak means active demand now for electrical, substation and mechanical trades, plus a projected $90 million a year in new parish tax revenue once it operates.
What this project buys
- Electrical and substation construction
- Mechanical and liquid cooling systems
- Structural steel erection
- Site civil work and earthwork
- Fiber and low voltage data cabling
- Standby generator installation
When to approach: Construction is already active, so bid packages for electrical, substation, mechanical and site work tied to Phase I are likely open now through the 2027 operating target. No subcontractors beyond EPC partner Jacobs and infrastructure supplier Vertiv have been named.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Hut 8's River Bend data center?
In West Feliciana Parish, Louisiana, a rural parish on the Mississippi River northwest of Baton Rouge.
How much is Hut 8 investing in River Bend?
Entergy Louisiana and Louisiana Economic Development say Phase I represents up to $10 billion, including Hut 8's data center infrastructure spending. A separate state incentive filing and the tenant lease deal use different, smaller and larger figures tied to different parts of the project, so the numbers are not directly comparable.
How many jobs will the project create?
Louisiana Economic Development estimates at least 75 direct, permanent jobs once the facility operates, plus 193 indirect jobs, for 268 total. Hut 8 says about 1,000 construction workers will be on site at the peak of Phase I.
When will River Bend start operating?
Hut 8 said construction was already underway as of its December 2025 announcement, with commercial operations targeted for the second quarter of 2027.
Who is building River Bend?
Jacobs is Hut 8's engineering, procurement and construction management partner, working with Vertiv on data center infrastructure, according to Construction Dive. Tenant Fluidstack has signed a 15 year lease for capacity at the site.
Sources
- Hut 8 Selects Entergy, Southeast Louisiana for $10 Billion Artificial Intelligence Data Center, Entergy, Dec. 17, 2025
- Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center, Louisiana Economic Development, Dec. 17, 2025
- Jacobs starts $10B Louisiana data center, Construction Dive, Dec. 22, 2025
- Hut 8 facility expected to generate $90 million annually for local government, WAFB, Dec. 17, 2025
- Commercial Inducement Board agenda, Feb. 25, 2026 (Louisiana Quality Jobs application 20250208-QJ), Louisiana Board of Commerce and Industry, Feb. 25, 2026


