Manufacturing · Under construction

LG Energy Solution

LG Energy Solution is building a battery plant in Queen Creek, AZ, with an estimated $3.5 billion investment.

Queen Creek, Maricopa County, Arizona

Investment

$3.5 billion

estimated investment per Rhodium Group-MIT/CEEPR Clean Investment Monitor (CC BY 4.0)

Project fileAZ
Owner
LG Energy Solution
Investment
$3.5 billion (estimated investment per Rhodium Group-MIT/CEEPR Clean Investment Monitor (CC BY 4.0))
Location
Queen Creek, Maricopa County, Arizona
Address
Southeast corner of Ironwood and Pecos roads
Sector
Manufacturing
Type
Battery plant (cells, modules), new construction
Stage
Under construction
Construction start
Not disclosed
Completion
Not disclosed
Contractor / EPC
Not announced
Source
Clean Investment Monitor (Rhodium Group-MIT/CEEPR), Nov. 20, 2026
Added to the map
Nov. 20, 2026

What this project buys

  • Site work and foundations
  • Structural steel erection
  • Electrical and substation
  • Mechanical and HVAC
  • Process piping
  • Fire protection

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in Arizona

  • Nov. 26, 2026
    Applied Materials, Inc.open record

    Semiconductor equipment plant, building conversion

    Applied Materials is converting a 181,655 sq ft building in Chandler, AZ into a semiconductor equipment plant, with more than $200 million planned.

    Chandler, AZSemiconductors & Electronics$200 millionFinanced
  • Nov. 22, 2026
    Tombstone Resources, LLCopen record

    Data center and battery energy storage system campus, proposed

    Tombstone Resources, tied to SpaceX, seeks a Cochise County permit for a 6 GW, nine building data center campus.

    Cochise, AZData Centers$50 billionAnnounced
  • Nov. 20, 2026
    Owner hidden

    Battery storage project, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Maricopa County, AZPower & Energy$120.2 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery storage project plus solar power plant, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation

    Cochise County, AZPower & Energy$208.4 millionUnder construction
  • Nov. 20, 2026
    Owner hidden

    Battery storage project plus solar power plant, new construction

    Likely to buy: Site work and foundations, Battery container installation, Electrical and substation