Capex WireMore than $126 billion in U.S. capital projects on the map, with new ones every day. Just $9.90/month, cancel anytime.Subscribe ›
Thursday, Nov. 19, 2026 · U.S. editionNov. 19, 2026How we reportLog inSubscribe to Capex Wire

U.S. capital projects before the bid list closes.

Power & Energy · Filed / permitted

Owner hidden

Battery storage, 300 MW in Kings County, New York.

Kings County, New York

Investment

Not disclosed

EIA does not report project cost

Project fileNY
Owner
Owner hidden
Investment
Not disclosed (EIA does not report project cost)
Location
Kings County, New York
Address
Owner hidden
Sector
Power & Energy
Type
Battery storage, 300 MW
Stage
Filed / permitted
Construction start
Not disclosed
Completion
Oct. 31, 2028
Design firm
Owner hidden
Contractor / EPC
Owner hidden
Source
Federal energy filing (EIA), Sept. 30, 2026
Added to the map
Nov. 17, 2026

Owner hidden

Get there first: every project owner on the U.S. Project Map.

The owner and source of this project are hidden in the open version. They are part of the full Project Map. Subscribers see every owner, address, design firm and source on the Project Map. $9.90 per month. Cancel anytime in one click.

What this project buys

  • Site work and concrete pads
  • Battery enclosure installation
  • Electrical and medium voltage
  • Substation and interconnection
  • Fire protection
  • Controls and commissioning

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in New York

  • Nov. 19, 2026
    TE Connectivity plcopen record

    Manufacturing and R&D facility conversion, optical connectivity products

    Conversion of a vacant former Sam's Club into an optical connectivity R&D and manufacturing plant. More than 800 jobs.

    Henrietta, NYSemiconductors & Electronics$60 millionAnnounced
  • Nov. 17, 2026
    GlobalFoundriesopen record

    Semiconductor fab, 300mm, new construction

    GlobalFoundries broke ground Nov. 13 on a new 300mm fab in Malta, about $10 billion, due online in 2029. Builder not announced.

    Malta, NYSemiconductors & Electronics$10 billionUnder construction
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 280 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Genesee County, NYPower & EnergyNot disclosedUnder construction
  • Nov. 17, 2026
    Owner hidden

    Offshore wind, 810 MW

    Likely to buy: Marine construction and vessels, Foundation fabrication, Subsea and export cable

    Kings County, NYPower & EnergyNot disclosedUnder construction
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 240 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    St Lawrence County, NYPower & EnergyNot disclosedAnnounced