Power & Energy · Filed / permitted

Owner hidden

Natural gas combustion turbine, 448 MW in Oklahoma County, Oklahoma.

Oklahoma County, Oklahoma

Investment

Not disclosed

EIA does not report project cost

Project fileOK
Owner
Owner hidden
Investment
Not disclosed (EIA does not report project cost)
Location
Oklahoma County, Oklahoma
Address
Owner hidden
Sector
Power & Energy
Type
Natural gas combustion turbine, 448 MW
Stage
Filed / permitted
Construction start
Not disclosed
Completion
Feb. 28, 2029
Design firm
Owner hidden
Contractor / EPC
Owner hidden
Source
Federal energy filing (EIA), Sept. 30, 2026
Added to the map
Nov. 17, 2026

Owner hidden

Get there first: every project owner on the U.S. Project Map.

The owner and source of this project are hidden in the open version. They are part of the full Project Map. Subscribers see every owner, address, design firm and source on the Project Map. $9.90 per month. Cancel anytime in one click.

What this project buys

  • Gas turbine installation
  • Mechanical and piping
  • Electrical and substation
  • Concrete and foundations
  • Gas interconnect
  • Controls and instrumentation

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

More projects in Oklahoma

  • Nov. 19, 2026
    Public Service Company of Oklahoma (AEP)open record

    Natural gas power plant, two combustion turbine units (expansion of existing campus)

    PSO broke ground on two new 450 MW gas turbines at its Northeastern Energy Campus near Oologah.

    Oologah, OKPower & Energy$539.8 millionUnder construction
  • Nov. 17, 2026
    Owner hidden

    Natural gas combined cycle, 1,373 MW

    Likely to buy: Gas and steam turbine installation, Heat recovery steam generators, Mechanical and piping

    Comanche County, OKPower & EnergyNot disclosedAnnounced
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 258 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Stephens County, OKPower & EnergyNot disclosedUnder construction
  • Nov. 17, 2026
    Owner hidden

    Battery storage, 200 MW + Solar photovoltaic, 200 MW

    Likely to buy: Site work and concrete pads, Battery enclosure installation, Electrical and medium voltage

    Le Flore County, OKPower & EnergyNot disclosedAnnounced
  • Nov. 17, 2026
    Owner hidden

    Solar photovoltaic, 400 MW

    Likely to buy: Site work and grading, Pile driving and racking, Module installation

    Muskogee County, OKPower & EnergyNot disclosedAnnounced