Oil, Gas & LNG · LA

Black Bayou Gas Storage starts construction on 44.4 Bcf salt cavern project in Cameron Parish, Louisiana.

Site work began Nov. 11 after a limited notice to proceed from FERC. The first four caverns are targeted for service in late 2028, with more than 1,000 construction jobs at peak.

Quick answer

Black Bayou Gas Storage LLC: $1.6 billion investment in West Hackberry, La. Stage: Under construction. Timeline: FERC Limited Notice to Proceed Oct. 20, 2026. Site work began Nov. 11, 2026. Initial in-service targeted for late 2028. Likely to buy: cavern drilling and solution mining, pipeline construction, compression and mechanical, electrical and instrumentation.

Aerial view of a pump pad, piping and brine pond at a U.S. Strategic Petroleum Reserve salt cavern storage site on the Gulf Coast
Illustrative photo. Photo: U.S. Department of Energy / Wikimedia Commons, Public domain

By Capex Wire StaffPublished 2 min read

Black Bayou Gas Storage LLC has started construction on a natural gas storage facility with 44.4 billion cubic feet of working capacity near West Hackberry, Louisiana, in Cameron Parish, the company said Nov. 13, 2026.

Site work began Nov. 11. It follows a Limited Notice to Proceed that the Federal Energy Regulatory Commission, known as FERC, issued Oct. 20. The company, which does business as Black Bayou Energy Hub and is based in Lafayette, holds a FERC Certificate of Public Convenience and Necessity for the project.

The scope

  • Site: 2,500 acres on the Black Bayou salt dome. The company says it controls the entire dome, which extends into Calcasieu Parish.
  • Initial phase: four caverns with 44.4 billion cubic feet of certificated working gas capacity.
  • Rates: up to 1.6 billion cubic feet a day of injection and 2.0 billion cubic feet a day of withdrawal.
  • Pipe: a dual-header pipeline system connecting to 13 interstate pipelines.
  • Schedule: first in-service targeted for late 2028.

The company expects more than 1,000 construction jobs at peak and 23 direct permanent jobs.

"With our FERC approvals in hand, we have moved from planning to building," Chief Executive Officer Tad Lalande said in the release. Daniel James, senior vice president of development, called the start of construction an important milestone.

Capex Wire

Get there first: every project owner on the U.S. Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $126 billion

in announced or filed value

Subscribe for $9.90/month

Cancel anytime in one click.

The money

The construction release gives no cost. Louisiana Economic Development put the company's investment at $1.6 billion in a Sept. 10, 2026, announcement. That figure covers both the Cameron Parish gas infrastructure and an expansion of the Lafayette headquarters, and the state did not split it. The agency identified Mercuria as the majority equity sponsor and controlling investor.

The state offered $1 million from its Economic Development Award Program for infrastructure improvements, plus LED FastStart workforce services. The company is expected to take part in the High Impact Jobs and Industrial Tax Exemption programs.

Who buys the service

Black Bayou says it will offer high-deliverability, multi-cycle storage along with balancing, wheeling and blending. Target customers are LNG export terminals, local distribution companies, power generators, marketers and gas producers. No customer contracts were named.

What is not disclosed

No contractor is named in the company release, the BIC Magazine report or the state announcement. That includes the cavern drilling and solution mining contractor, the pipeline contractor and the compression supplier. The engineering firm, the pipeline mileage, the compressor horsepower and the scope allowed under the limited notice were not disclosed. The timing of any later phase was not given.

Project fileLA
Owner
Black Bayou Gas Storage LLC
Investment
$1.6 billion (state figure of Sept. 10, 2026; covers Cameron Parish gas infrastructure and Lafayette headquarters expansion, split not disclosed)
Location
West Hackberry, Cameron Parish, Louisiana
Type
Salt cavern natural gas storage and header pipeline system
Stage
Under construction
Timeline
FERC Limited Notice to Proceed Oct. 20, 2026. Site work began Nov. 11, 2026. Initial in-service targeted for late 2028.
Contractor / EPC
Not announced
Sources
Black Bayou Energy Hub via PR Newswire, BIC Magazine, Louisiana Economic Development

Why it matters

Site work has started on a project the state values at $1.6 billion, and no drilling, pipeline or compression contractor has been named in public. Suppliers in Southwest Louisiana should find out who holds those packages now.

What this project buys

  • Cavern drilling and solution mining
  • Pipeline construction
  • Compression and mechanical
  • Electrical and instrumentation
  • Site work and civil
  • Process piping

When to approach: Under construction now. More than 1,000 construction jobs expected at peak. Contractors not announced.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.