Capex WireMore than $1.8 trillion in U.S. capital projects on the map, with new ones every day. Just $9.90/month, cancel anytime.Subscribe ›
Saturday, Nov. 28, 2026 · U.S. editionNov. 28, 2026How we reportLog inSubscribe to Capex Wire

U.S. capital projects before the bid list closes.

Oil, Gas & LNG · LA

Woodside's $17.5 billion Louisiana LNG terminal passes 28 percent built in Calcasieu Parish.

Trains and storage tanks are rising on the Calcasieu Parish site as Woodside and contractor Bechtel push toward a 2029 first cargo for the three train export terminal.

Quick answer

Woodside Energy Group Ltd: $17.5 billion investment in Calcasieu Parish, La. Stage: Under construction. Timeline: Final investment decision in April 2025. Groundbreaking in September 2025. By the end of the second quarter of 2026, Trains 1, 2 and 3 were 35, 25 and 18 percent complete, respectively, and overall project completion reached 28 percent by August 2026. Target first LNG cargo in 2029. Likely to buy: process piping and welding, structural steel erection, electrical and instrumentation, tank construction and roofing.

A large spherical industrial gas storage tank with a staircase at an energy facility
Illustrative photo. Photo: Jan van der Wolf / Pexels

By Capex Wire NewsroomPublished 2 min read

Woodside Energy's Louisiana LNG export terminal in Calcasieu Parish is now 28 percent complete, the company said in project updates, as construction crews push forward on three liquefaction trains and two large storage tanks on the site between Houston and New Orleans. Drone footage released in August showed structural steel erected on Trains 1 and 2, concrete piling underway for Train 3, and roof panel installation starting on the first of two LNG storage tanks.

What is being built

The $17.5 billion project calls for three liquefaction trains with capacity to produce up to 16.5 million metric tons of LNG a year, on permits that allow expansion to as much as 27.6 million tons annually, according to Louisiana Economic Development. Two storage tanks, each holding 235,000 cubic meters, are under construction alongside the trains. Woodside reported that by the end of the second quarter of 2026, Train 1 was 35 percent complete, Train 2 was 25 percent complete and Train 3 was 18 percent complete. Bechtel is the general contractor, Louisiana LNG President Sarah Bairstow said at a September 2025 groundbreaking ceremony, adding that about 85 percent of construction spending has gone to local suppliers and labor.

Capex Wire

Get there first: every project owner on the Project Map.

Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.

more than $1.8 trillion

in announced or filed value

See the owner, address and source for 134 projects like this

$9.90/month · cancel anytime in one click

Jobs and timeline

Woodside reached its final investment decision on the project in April 2025, and Louisiana Economic Development called it the largest foreign direct investment in state history. Crews broke ground that September, and the site workforce had grown to nearly 900 construction personnel by that month. Woodside has not disclosed a current on-site headcount for 2026. The company is targeting first LNG cargo in 2029.

MilestoneStatus or figure
Overall completion28 percent, per drone survey published August 2026
Train 1 / Train 2 / Train 335% / 25% / 18% complete at end of Q2 2026
CapacityUp to 16.5 million tons LNG per year; permitted to 27.6 million tons
Storage tanksTwo tanks, 235,000 cubic meters each, under construction
Construction workforceNearly 900 on site as of September 2025
Target first cargo2029

Who is building it

Bechtel holds the engineering, procurement and construction contract for the terminal. In June 2026, Woodside sold a 40 percent stake in Louisiana LNG Infrastructure LLC, the entity that owns the project, to infrastructure investor Stonepeak, bringing in a financial partner alongside Woodside's operating role. Woodside Energy Group Ltd is the parent company behind the U.S. project entity, Woodside Energy USA Services Inc., which holds the underlying state incentive filings for the site.

What happens next

Woodside's near term priorities are finishing construction on all three trains, advancing the LNG jetty and completing the walls of the storage tanks before roof installation, the company has said. With steel erection now underway on two of the three trains and tank construction progressing, companies that supply process piping, electrical and instrumentation, structural steel and insulation work are likely to see continued demand on the site through the rest of the decade as the project moves toward its 2029 target.

Project fileLA
Owner
Woodside Energy Group Ltd
Investment
$17.5 billion (Final investment decision capital cost, per Woodside and Louisiana Economic Development)
Location
Calcasieu Parish, Louisiana
Type
Oil, gas and LNG facility, new investment
Stage
Under construction
Timeline
Final investment decision in April 2025. Groundbreaking in September 2025. By the end of the second quarter of 2026, Trains 1, 2 and 3 were 35, 25 and 18 percent complete, respectively, and overall project completion reached 28 percent by August 2026. Target first LNG cargo in 2029.
Contractor / EPC
Bechtel
Sources
Ocean News & Technology, Offshore Engineer (OE Digital), Energy Tech, Louisiana Economic Development (Opportunity Louisiana)

Why it matters

A $17.5 billion LNG terminal with three trains under simultaneous construction and tanks still being built means years of ongoing demand for piping, steel, electrical and insulation trades in Southwest Louisiana.

What this project buys

  • Process piping and welding
  • Structural steel erection
  • Electrical and instrumentation
  • Tank construction and roofing
  • Marine and jetty construction
  • Insulation and coatings

When to approach: Ongoing through 2029; bid activity continues as Trains 2 and 3 and the two storage tanks move through steel erection, piling and roof work.

Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.

Frequently asked questions

Where is Woodside's Louisiana LNG terminal?

In Calcasieu Parish, Louisiana, on the Calcasieu River between Houston and New Orleans, near the existing Cameron LNG terminal.

How much is Woodside investing in Louisiana LNG?

Woodside's final investment decision put the project at $17.5 billion, according to Louisiana Economic Development.

How far along is construction?

The project was 28 percent complete as of a drone survey published in August 2026, with Train 1 at 35 percent, Train 2 at 25 percent and Train 3 at 18 percent complete at the end of the second quarter of 2026.

Who is the general contractor?

Bechtel, named by Louisiana LNG President Sarah Bairstow at the project's September 2025 groundbreaking.

When will the terminal start exporting LNG?

Woodside is targeting first LNG cargo in 2029. The U.S. Department of Energy has given the project until the end of 2029 to begin exports to non free trade agreement countries.

Sources

More capital projects