Woodside's $17.5 billion Louisiana LNG terminal passes 28 percent built in Calcasieu Parish.
Trains and storage tanks are rising on the Calcasieu Parish site as Woodside and contractor Bechtel push toward a 2029 first cargo for the three train export terminal.
Quick answer
Woodside Energy Group Ltd: $17.5 billion investment in Calcasieu Parish, La. Stage: Under construction. Timeline: Final investment decision in April 2025. Groundbreaking in September 2025. By the end of the second quarter of 2026, Trains 1, 2 and 3 were 35, 25 and 18 percent complete, respectively, and overall project completion reached 28 percent by August 2026. Target first LNG cargo in 2029. Likely to buy: process piping and welding, structural steel erection, electrical and instrumentation, tank construction and roofing.

By Capex Wire NewsroomPublished 2 min read
Woodside Energy's Louisiana LNG export terminal in Calcasieu Parish is now 28 percent complete, the company said in project updates, as construction crews push forward on three liquefaction trains and two large storage tanks on the site between Houston and New Orleans. Drone footage released in August showed structural steel erected on Trains 1 and 2, concrete piling underway for Train 3, and roof panel installation starting on the first of two LNG storage tanks.
What is being built
The $17.5 billion project calls for three liquefaction trains with capacity to produce up to 16.5 million metric tons of LNG a year, on permits that allow expansion to as much as 27.6 million tons annually, according to Louisiana Economic Development. Two storage tanks, each holding 235,000 cubic meters, are under construction alongside the trains. Woodside reported that by the end of the second quarter of 2026, Train 1 was 35 percent complete, Train 2 was 25 percent complete and Train 3 was 18 percent complete. Bechtel is the general contractor, Louisiana LNG President Sarah Bairstow said at a September 2025 groundbreaking ceremony, adding that about 85 percent of construction spending has gone to local suppliers and labor.
Capex Wire
Get there first: every project owner on the Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $1.8 trillion
in announced or filed value
See the owner, address and source for 134 projects like this$9.90/month · cancel anytime in one click
Jobs and timeline
Woodside reached its final investment decision on the project in April 2025, and Louisiana Economic Development called it the largest foreign direct investment in state history. Crews broke ground that September, and the site workforce had grown to nearly 900 construction personnel by that month. Woodside has not disclosed a current on-site headcount for 2026. The company is targeting first LNG cargo in 2029.
| Milestone | Status or figure |
|---|---|
| Overall completion | 28 percent, per drone survey published August 2026 |
| Train 1 / Train 2 / Train 3 | 35% / 25% / 18% complete at end of Q2 2026 |
| Capacity | Up to 16.5 million tons LNG per year; permitted to 27.6 million tons |
| Storage tanks | Two tanks, 235,000 cubic meters each, under construction |
| Construction workforce | Nearly 900 on site as of September 2025 |
| Target first cargo | 2029 |
Who is building it
Bechtel holds the engineering, procurement and construction contract for the terminal. In June 2026, Woodside sold a 40 percent stake in Louisiana LNG Infrastructure LLC, the entity that owns the project, to infrastructure investor Stonepeak, bringing in a financial partner alongside Woodside's operating role. Woodside Energy Group Ltd is the parent company behind the U.S. project entity, Woodside Energy USA Services Inc., which holds the underlying state incentive filings for the site.
What happens next
Woodside's near term priorities are finishing construction on all three trains, advancing the LNG jetty and completing the walls of the storage tanks before roof installation, the company has said. With steel erection now underway on two of the three trains and tank construction progressing, companies that supply process piping, electrical and instrumentation, structural steel and insulation work are likely to see continued demand on the site through the rest of the decade as the project moves toward its 2029 target.
- Owner
- Woodside Energy Group Ltd
- Investment
- $17.5 billion (Final investment decision capital cost, per Woodside and Louisiana Economic Development)
- Location
- Calcasieu Parish, Louisiana
- Type
- Oil, gas and LNG facility, new investment
- Stage
- Under construction
- Timeline
- Final investment decision in April 2025. Groundbreaking in September 2025. By the end of the second quarter of 2026, Trains 1, 2 and 3 were 35, 25 and 18 percent complete, respectively, and overall project completion reached 28 percent by August 2026. Target first LNG cargo in 2029.
- Contractor / EPC
- Bechtel
- Sources
- Ocean News & Technology, Offshore Engineer (OE Digital), Energy Tech, Louisiana Economic Development (Opportunity Louisiana)
Why it matters
A $17.5 billion LNG terminal with three trains under simultaneous construction and tanks still being built means years of ongoing demand for piping, steel, electrical and insulation trades in Southwest Louisiana.
What this project buys
- Process piping and welding
- Structural steel erection
- Electrical and instrumentation
- Tank construction and roofing
- Marine and jetty construction
- Insulation and coatings
When to approach: Ongoing through 2029; bid activity continues as Trains 2 and 3 and the two storage tanks move through steel erection, piling and roof work.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Frequently asked questions
Where is Woodside's Louisiana LNG terminal?
In Calcasieu Parish, Louisiana, on the Calcasieu River between Houston and New Orleans, near the existing Cameron LNG terminal.
How much is Woodside investing in Louisiana LNG?
Woodside's final investment decision put the project at $17.5 billion, according to Louisiana Economic Development.
How far along is construction?
The project was 28 percent complete as of a drone survey published in August 2026, with Train 1 at 35 percent, Train 2 at 25 percent and Train 3 at 18 percent complete at the end of the second quarter of 2026.
Who is the general contractor?
Bechtel, named by Louisiana LNG President Sarah Bairstow at the project's September 2025 groundbreaking.
When will the terminal start exporting LNG?
Woodside is targeting first LNG cargo in 2029. The U.S. Department of Energy has given the project until the end of 2029 to begin exports to non free trade agreement countries.
Sources
- Drone Footage Captures Louisiana LNG Construction Progress at 28 Percent, Ocean News & Technology, Aug. 6, 2026
- Woodside Marks Construction Milestone at $17.5B Louisiana LNG Scheme, Offshore Engineer (OE Digital), Sept. 16, 2025
- Woodside Contracts 900 Construction Workers to Complete Louisiana LNG Terminal by 2029, Energy Tech, Sept. 18, 2025
- Woodside Energy project page, Louisiana Economic Development (Opportunity Louisiana), April 28, 2025
See the project record on the Project Map →
7 other projects in Calcasieu Parish, Louisiana have not broken ground →