- Owner
- Oglethorpe Power Corporation
- Investment
- $3.3 billion (Company-announced capital investment; matches the USDA Rural Utilities Service loan amount announced separately.)
- Location
- Monroe County, Georgia
- Sector
- Power & Energy
- Type
- Natural gas combined cycle, 1,425 MW, two units
- Stage
- Under construction
- Construction start
- May 7, 2026
- Completion
- June 30, 2029
- Contractor / EPC
- TIC - The Industrial Company (a Kiewit subsidiary)
- Source
- Oglethorpe Power Corporation (press release), May 7, 2026
- Added to the map
- Nov. 17, 2026
What this project buys
- Gas and steam turbine installation
- Heat recovery steam generators
- Mechanical and piping
- Electrical and substation
- Concrete and foundations
- Controls and instrumentation
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.