Amazon starts construction on $7 billion data center campus in Wheatfield, Indiana.
More than 350 construction workers are already on the 304-acre Jasper County site, on land owned by NIPSCO near the Schahfer Generating Station.
Quick answer
Amazon: $7 billion investment in Wheatfield, Ind. Stage: Under construction. Timeline: Approved by Jasper County officials June 17, 2026. Groundbreaking reported Nov. 16, 2026. Completion date not disclosed. Likely to buy: site work and utilities, concrete and foundations, structural steel, electrical and high voltage.

By Capex Wire StaffPublished 2 min read
Amazon has broken ground on a $7 billion data center campus in Wheatfield, Indiana, where more than 350 construction workers are already on site, Northwest Indiana Business Magazine reported Nov. 16.
The campus covers 304 acres in Jasper County. County officials approved the project June 17. The land is owned by NIPSCO, the Merrillville-based utility, and sits near the Schahfer Generating Station, the magazine reported in June, when the project was known as Project Rise.
"It's the start of a long-term partnership with Jasper County," Roger Wehner, vice president of economic development at Amazon, said in a press release quoted by the magazine.
What Amazon agreed to pay for
- $98 million paid in advance to the county, part of the $7 billion investment.
- $25 million to expand public water service in Wheatfield Township, which will bring municipal water to the town of Wheatfield for the first time.
- All water and wastewater infrastructure the campus needs.
The campus will not use public water systems and will supply its own water, according to the June report. The buildings will be cooled mostly with outside air, with water-based cooling needed about 2% of the year. Amazon will also restore 425 acres of natural habitat in the Kankakee River watershed with the Shirley Heinze Land Trust.
Capex Wire
Get there first: every project owner on the U.S. Project Map.
Hundreds of projects have not broken ground yet. See who is building each one, with address, design firm and source, before the bid list closes.
more than $126 billion
in announced or filed value
Subscribe for $9.90/monthCancel anytime in one click.
Power
NIPSCO is building a 400-megawatt peaker plant at the site. Testimony to the Indiana Office of Utility Consumer Counselor put the cost of construction and financing of that plant at $643.7 million, the magazine reported.
Jobs and the wider program
The June report put the campus at 250 expected jobs. The site now generates $70,000 a year in property taxes, and annual revenue to local government is expected to exceed $20 million over 10 years.
The Wheatfield campus is part of $15 billion that Amazon has committed to data centers in northern Indiana. The company broke ground on an $11 billion campus in New Carlisle in 2024.
What is not disclosed
The two reports opened for this story do not name the general contractor, the design firm or the electrical and mechanical contractors. They do not give the number of buildings, the square footage, the power capacity of the campus or a completion date. The schedule for the NIPSCO peaker plant is also not given.
- Owner
- Amazon
- Investment
- $7 billion ($7 billion campus, per company figures reported by Northwest Indiana Business Magazine)
- Location
- Wheatfield, Jasper County, Indiana
- Type
- Data center campus, new construction
- Stage
- Under construction
- Timeline
- Approved by Jasper County officials June 17, 2026. Groundbreaking reported Nov. 16, 2026. Completion date not disclosed.
- Contractor / EPC
- Not announced
- Sources
- Northwest Indiana Business Magazine, Northwest Indiana Business Magazine
Why it matters
The job is live, with crews on site and a multi-building campus ahead. Subcontractors and suppliers should find out who holds the main contract, since the builder was not named in the published reports.
What this project buys
- Site work and utilities
- Concrete and foundations
- Structural steel
- Electrical and high voltage
- Mechanical and cooling
- Water and wastewater infrastructure
When to approach: Under construction now, with more than 350 workers on site. Builder not named in the sources opened.
Typical scopes for a project of this type. This is an editorial estimate, not a list of awarded or advertised packages.
Sources
- Amazon starts construction on $7B data center, Northwest Indiana Business Magazine, Nov. 16, 2026
- Officials approve Jasper County Amazon data center, Northwest Indiana Business Magazine, June 18, 2026